  • 16 October 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The first eight XXL monopile foundations for the 1.1 GW Inch Cape offshore wind farm in Scotland, produced by China’s CNOOD-Wenchong Heavy Industries (CWHI), have arrived in the Port of Leith ahead of the installation work, which will start before the end of the year. CWHI sent off the monopiles on 31 August aboard the […]

  • 31 July 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The substation platform and jacket foundation for the Inch Cape offshore wind farm have departed from the Smulders yard in Wallsend, Newcastle, and are en route to their site off the Angus coast in Scotland. The Siemens Energy Offshore Transformer Module (OTM) and its jacket foundation sailed at sunset yesterday (30 July) down the River […]

  • 23 October 2025
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    The first of the two 85-kilometre export cables for the Scottish Inch Cape offshore wind farm has been installed by Enshore Subsea using the cable laying vessel (CLV) CMOS Installer. Operating from the Port of Blyth, the vessel laid the 220 kV, three-phase cable manufactured by Ningbo Orient Wires & Cables (Orient Cable) in three […]

  • 9 September 2025
    Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Dajin Heavy Industry has sent away the first batch of six monopiles that will be installed at the 1.1 GW Inch Cape offshore wind farm in Scotland. The first six monopiles have set sail from Dajin Heavy Industry’s Penglai facility, according to the latest social media post by the Chinese company. Dajin cut the first […]

  • 11 September 2025
    Infrastructure, Operations & Maintenance

    Construction of an operations and maintenance (O&M) base to serve the 1.1 GW Inch Cape offshore wind farm is underway at Montrose Port in Angus, Scotland. Montrose-based main contractor Pert Bruce Construction is building the O&M base office, a 600-square-metre warehouse, and quayside facilities, as well as the communications systems for the Scottish offshore wind […]

  • 4 August 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The offshore jacket foundation and substation platform have been installed at the Inch Cape offshore wind farm site in the North Sea. The Siemens Energy Offshore Transformer Module (OTM) and its 68-metre jacket foundation are now in position 21 kilometres from the Angus coast, Scotland, having been installed by Heerema Marine Contractors’ semi-submersible crane vessel […]

  • 16 June 2025
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Dajin Heavy Industry has produced the first three monopiles for the Inch Cape offshore wind farm, the company said on 16 June, a few days after CNOOD-Wenchong Heavy Industries (CWHI) announced it had completed the first monopiles from the batch it is delivering for the 1 GW project in Scotland. Dajin cut the first steel for […]

  • 12 May 2025
    Contracts & Tenders, Fixed-Bottom, Supply Chain

    UK-based Tekmar Group has been awarded a contract to provide grouting services for the 1.1 GW Inch Cape offshore wind farm in Scotland. Under the contract, Tekmar Group will deliver a specialist grouting solution for key offshore wind infrastructure. The work is scheduled to commence in September 2025. According to the company, grouting is an […]

  • 27 August 2025
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    The initial section of the first export cable for the Inch Cape offshore wind farm has left the Port of Blyth and is currently en route for installation off the coast of Scotland. The cable-lay vessel, CMOS Installer, has left the port with the 28-kilometre section of the 220 kV, three-phase export cable. Each of […]

  • 3 September 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    China’s CNOOD-Wenchong Heavy Industries (CWHI) has sent off the first 8 XXL monopiles for the 1.1 GW Inch Cape offshore wind farm off the east coast of Scotland. Manufactured at CWHI’s Qinzhou yard, the monopiles were shipped on 31 August aboard the COSCO vessel XIAN TAI KOU. The shipment is en route to Forth Ports […]

  • 2 July 2025
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    OEG has won a multi-million-pound contract to support the construction phase of the 1.1 GW Inch Cape offshore wind farm in Scotland until the project becomes operational in 2027. Under the contract, OEG will supply an integrated package of specialist topside and marine services, including marine coordination, high voltage, and ancillary port services. These will […]

  • 3 November 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    Dajin Heavy Industry has shipped the third and final batch of monopiles for the 1.1 GW Inch Cape offshore wind farm in Scotland. The final batch of eight monopiles has set sail from Dajin Heavy Industry’s Dajin Penglai facility. With this shipment, all 22 monopiles for the project have now been dispatched. The roll-on/roll-off operations […]

  • 13 June 2025
    Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    China’s CNOOD-Wenchong Heavy Industries (CWHI) has completed the manufacturing of the first monopiles for the 1,080 MW Inch Cape offshore wind project in Scotland. The monopiles are 11.5 metres in diameter, up to 110 metres in length, and have a maximum weight of 2,300 tonnes. The first cutting and rolling of monopiles was carried out […]

  • 18 August 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Vessels, Wind Farm Update

    Heerema Marine Contractors’ semi-submersible crane vessel (SSCV) Sleipnir has completed the installation of the pin piles and jacket foundation for the East Anglia Three offshore substation at the offshore wind farm’s site in the UK. According to a weekly notice of operations from the developer, ScottishPower Renewables, issued on 11 August, Sleipnir arrived at the East Anglia Three […]

  • 14 October 2025
    Business & Finance, Business development, Vessels

    Dajin Heavy Industry has launched its first self-built heavy deck carrier designed to transport XXL components and equipment for the offshore wind, oil, and gas industries. The vessel is the first of four of the same type that the company is currently building, and could be the first in a fleet of 20 heavy deck carriers […]

  • 27 August 2025

    F.lli Righini Srl, a leading engineering and manufacturing company in offshore energy solutions, has successfully delivered numerous Jacket Pile Grippers (JPGs) for multiple offshore wind projects across the North Sea and Baltic Sea. These tailor-made systems play a critical role in the precise installation of jacket foundations for Wind Turbine Generators and Offshore Substations, contributing […]

  • 14 April 2025
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    Energy and marine consultancy company ABL will provide marine warranty survey (MWS) services for the Inch Cape offshore wind farm during the entire construction period of the 1.1 GW project in Scotland. ABL will act as marine warranty surveyor for the transport and installation of the jacket and monopile foundations, offshore substation platform, wind turbines, […]

  • 23 September 2025
    Business & Finance, Contracts & Tenders, Supply Chain

    EnBW has selected HTM Helicopter Travel Munich and HeliService to provide helicopter transport services for the company’s offshore wind farms in the German North Sea. HTM Helicopter Travel Munich and HeliService were selected to provide aerial and related services for EnBW’s Hohe See, Albatros, and He Dreiht offshore wind farms in Germany. EnBW plans to […]

  • 20 March 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    Seabed preparation activities are scheduled to begin at the Inch Cape offshore wind farm site in Scotland at the end of March. N-Sea, which has been contracted for the job, will start the work within the array site and the export cable corridor on or around 30 March and continue until November 2025. Seabed preparation […]

  • 18 March 2025
    Business & Finance, Cables, Contracts & Tenders, Fixed-Bottom, Grid Connection, Supply Chain

    UK-headquartered Enshore Subsea has secured an export cable installation contract for one of Scotland’s largest offshore wind projects, the 1.1 GW Inch Cape. The Inch Cape offshore wind farm will feature two 85-kilometre, 220 kV, three-phase export cables, each delivered in three sections and requiring offshore field joints. Under the contract, Enshore Subsea will be […]

  • 18 March 2025
    Infrastructure, Manufacturing, Ports & Logistics, Supply Chain

    CNOOD-Wenchong Heavy Industries (CWHI) has completed the construction of its flagship Qinzhou Yard in China, now one of the world’s largest and most advanced XXXL monopile manufacturing facilities in operation today, said the company. The new facility has an annual production capacity of 100 XXXL monopiles, each with a maximum diameter of 15 metres and […]

  • 13 March 2025
    Business & Finance, Contracts & Tenders, Supply Chain

    Inch Cape Offshore Limited (ICOL), a joint venture between ESB and Red Rock Renewables, has awarded a contract to OES Group to supply 54 external and internal Impressed Current Cathodic Protection (ICCP) systems to protect the offshore wind project’s monopile and transition piece foundations. The ICCC anodes will be produced in OES Group’s new dedicated […]

  • 28 February 2025
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Construction activities on the Scottish Inch Cape offshore wind farm are scheduled to start this April with construction work within the project’s export cable corridor. According to a Notice to Mariners from the project team, the work will commence with operations at the export cable landfall site on or around 1 April 2025 with construction […]

  • 27 February 2025
    Contracts & Tenders, Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Jan De Nul will deploy its heavy-lift vessel Les Alizés for the monopile installation at the Inch Cape offshore wind farm in Scotland. The company was announced as one of the project suppliers at the beginning of this year as ESB and Red Rock Renewables reached financial close on the 1,080 MW Inch Cape project. […]

  • 26 February 2025
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Geophysical survey operations and a static fishing gear survey are taking place within the Inch Cape offshore wind farm site and its associated export cable corridor from 19 February until the end of April. On behalf of Inch Cape Offshore Limited, a joint venture between ESB and Red Rock Renewables, the Dutch company N-Sea is […]

  • 25 February 2025
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    Taylor Hopkinson has been awarded a quality assurance/quality control (QA/QC) surveillance contract for the Inch Cape offshore wind farm in Scotland. Taylor Hopkinson will support the fabrication and construction of Scotland’s 1.1 GW Inch Cape offshore wind farm, being jointly developed by Red Rock Renewables and ESB. The company and Brunel’s global presence spans all […]