319 results found for 'Inch Cape'

319 results found for 'Inch Cape'
Order results by

A list of search results

  • 16 June 2025
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Dajin Heavy Industry has produced the first three monopiles for the Inch Cape offshore wind farm, the company said on 16 June, a few days after CNOOD-Wenchong Heavy Industries (CWHI) announced it had completed the first monopiles from the batch it is delivering for the 1 GW project in Scotland. Dajin cut the first steel for […]

  • 13 June 2025
    Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    China’s CNOOD-Wenchong Heavy Industries (CWHI) has completed the manufacturing of the first monopiles for the 1,080 MW Inch Cape offshore wind project in Scotland. The monopiles are 11.5 metres in diameter, up to 110 metres in length, and have a maximum weight of 2,300 tonnes. The first cutting and rolling of monopiles was carried out […]

  • 30 June 2022
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Inch Cape Offshore Limited, a joint venture (JV) between the Edinburgh-based Red Rock Power Limited and Ireland’s energy company Electricity Supply Board (ESB), has selected Siemens Energy-Iemants consortium to deliver the onshore and offshore substation package for the Inch Cape wind farm offshore Scotland. Siemens Energy will be responsible to design and build the onshore […]

  • 14 December 2021
    Contracts & Tenders, R&D, Technology, Wind Farm Update

    Offshore engineering consultancy SLPE has been awarded the contract to provide detailed design of wind turbine foundations for Red Rock Power Limited and ESB’s Inch Cape Offshore Wind Farm. Inch Cape successfully applied earlier this year to remove the 1 GW capacity cap from its consent, allowing it to select the most powerful turbines on […]

  • 12 May 2025
    Contracts & Tenders, Fixed-Bottom, Supply Chain

    UK-based Tekmar Group has been awarded a contract to provide grouting services for the 1.1 GW Inch Cape offshore wind farm in Scotland. Under the contract, Tekmar Group will deliver a specialist grouting solution for key offshore wind infrastructure. The work is scheduled to commence in September 2025. According to the company, grouting is an […]

  • 7 February 2022
    Operations & Maintenance, Ports & Logistics, Wind Farm Update

    Inch Cape Offshore Limited, a joint venture between the Edinburgh-based Red Rock Power Limited and Ireland’s energy company Electricity Supply Board (ESB), has selected Montrose Port as the future operations and maintenance (O&M) base for the Inch Cape offshore wind farm. Should the Inch Cape project be awarded a Contract for Difference (CfD) this summer, […]

  • 8 December 2014
    R&D, Wind Farm Update

    On October 11, an offshore meteorological mast was installed at the Inch Cape offshore wind farm site, which will gather accurate wind resource, wind direction and wind velocity data.  Our reader Marc Pearce has sent some recently taken photographs of the Inch Cape met mast to Offshore WIND. The complete structure of the 169.5 m high met mast […]

  • 14 April 2025
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    Energy and marine consultancy company ABL will provide marine warranty survey (MWS) services for the Inch Cape offshore wind farm during the entire construction period of the 1.1 GW project in Scotland. ABL will act as marine warranty surveyor for the transport and installation of the jacket and monopile foundations, offshore substation platform, wind turbines, […]

  • 23 January 2024
    Fixed-Bottom, Grid Connection, Onshore Infrastructure, Project Updates, Wind Farm Update

    Civil engineering contractor, Careys, is set to start work at the brownfield site of the former Cockenzie coal-fired power station on the East Lothian coast as the next phase of the 1.1 GW Inch Cape offshore wind farm substation gets underway in Scotland. Contracted by Siemens Energy, Careys will be responsible for the construction of […]

  • 27 January 2025
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    ESB and Red Rock Renewables have reached a financial close on the 1,080 MW Inch Cape offshore wind farm in Scotland, and the project will now progress into its offshore construction phase. The Scottish offshore wind project has reached a financial close, securing a GBP 3.5 billion financing package from shareholders and lenders, comprising 22 […]

  • 28 July 2016
    Business & Finance, Environment, Operations & Maintenance, Technology, Wind Farm Update

    Renewable energy consultancy SgurrEnergy has secured an operations and maintenance (O&M) contract for the Inch Cape Offshore Met Mast off the coast of Angus, Scotland. The scope of the 16 month contract includes offshore inspection and maintenance, recertification, project management, weather forecasting, data recovery and detailed reporting through SgurrDataPortal. In addition, the role includes the […]

  • 18 November 2019
    Jobs & Recruitment

    Red Rock Power has appointed Adam Ezzamel as Project Director of the Inch Cape offshore wind farm in Scotland. According to Red Rock Power, Ezzamel will engage with the project’s key stakeholders in the coming weeks. This June, the Scottish government approved the proposed changes to the wind farm which allow for the installation of […]

  • 9 September 2022
    Contracts & Tenders, Environment, R&D, Wind Farm Update

    Inch Cape Offshore Limited (ICOL), a joint venture between Red Rock Power Limited and Electricity Supply Board (ESB), has appointed JBA Consulting (JBA) to gather information about the installation phases of the 1.1 GW Inch Cape offshore wind farm in Scotland. For the task, JBA will use its strategic and operation planning software ForeCoast Marine to […]

  • 28 January 2025
    Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    CNOOD-Wenchong Heavy Industries (CWHI) and Inch Cape Offshore, a joint venture between ESB and Red Rock Renewables, have marked the first steel cutting for the transition pieces that will be installed at the 1.1 GW Inch Cape offshore wind farm. The transition pieces (TPs) will be manufactured at CWHI’s Zhongshan and Longxue yards in China and […]

  • 5 July 2024
    Fixed-Bottom, Grid Connection, Offshore Platforms

    Two transformers for the 1.1 GW Inch Cape offshore wind farm have completed their overland and sea journey from Zagreb, Croatia. The transformers traveled via Rotterdam, Netherlands, before arriving at the Smulders yard in Wallsend, the UK. The 545 MVA transformers were manufactured by Koncar Power Transformers company located in Zagreb. Now that the units […]

  • 6 June 2011

      The Crown Estate’s investment of £1 million in the Inch Cape offshore wind site, part of the Scottish Territorial Waters leasing round, has secured the future of the project after the dissolution of the consortium initially awarded the lease. The £1 million sum has enabled work on the site to continue to plan, and […]

  • 26 May 2010
    Business & Finance, Wind Farm Update

    The Crown Estate and SeaEnergy PLC are pleased to confirm developments concerning SeaEnergy Renewables Limited’s (SERL) interest in the Inch Cape Offshore Wind Farm (Inch Cape). In February 2009, The Crown Estate awarded the Inch Cape site to a consortium comprised of SERL, SeaEnergy’s 80% owned subsidiary, and RWE npower renewables as a part of […]

  • 5 August 2021
    Authorities, Technology, Wind Farm Update

    Scottish Ministers have agreed to vary the section 36 consent granted to Inch Cape Offshore Ltd – removing the 1 GW maximum generating capacity of their 72-turbine offshore wind project located off the Angus coastline. The variation of consent does not increase the number of turbines and will not affect any of the other permissions […]

  • 19 November 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    The consortium of NKT and Boskalis Subsea Cables & Flexibles has signed a Pre-Construction Agreement (PCA) for the delivery and installation of an export cable system for the 784MW Inch Cape offshore wind project in the UK.

  • 30 September 2014
    Technology

    Inch Cape Offshore Limited has successfully deployed a ZephIR 300 lidar on the historic Bell Rock lighthouse, 17km off the Angus coast. ZephIR 300 has been mounted on a platform on the north east of the lighthouse using a specially designed support frame measuring wind direction and wind velocity and will augment wind measurements from […]

  • 3 October 2014
    Business & Finance, Wind Farm Update

    Components of Inch Cape Offshore Limited’s met mast are nearing completion at East Lothian based steel fabrication company Had-Fab. The specialist fabrication company is responsible for the manufacturing of the innovative lattice mast to be used for measuring wind speeds at the Inch Cape Offshore Wind Farm site. Had-Fab has been contracted to produce the […]

  • 29 May 2017
    Authorities, Grid Connection, Wind Farm Update

    Inch Cape Offshore Limited (ICOL) has submitted a scoping report for the revised 784MW Inch Cape offshore wind farm to the Scottish Ministers.

  • 17 April 2014

    Inch Cape Offshore Limited, the developer of the proposed Inch Cape Offshore Wind Farm, will hold community consultations on its onshore electrical infrastructure, which is planned to be set up in Cockenzie, East Lothian News informs. Residents of East Lothian are invited to attend these events in order to get an insight into the plans […]

  • 14 November 2018
    Business & Finance

    Red Rock Power Ltd is holding a supply chain event in Scotland to help companies get involved in the Inch Cape offshore wind project.

  • 1 October 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain, Wind Turbines

    Vestas has signed a conditional order agreement with Inch Cape Offshore Limited (ICOL), a joint venture between ESB and Red Rock Renewables, to supply V236-15.0 MW wind turbines for the 1.1 GW Inch Cape offshore wind farm in Scotland. The agreement is for the supply, installation, and commissioning of 72 V236-15.0 MW wind turbines, and […]

  • 16 January 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Foundations, Supply Chain

    Inch Cape Offshore Wind Limited (ICOL) has signed capacity reservation agreements with Chinese manufacturers Dajin Offshore Heavy Industry (Dajin Offshore) and CNOOD-Wenchong Heavy Industries (CWHI) for XXL monopile foundations for the Inch Cape offshore wind farm. The agreements secure the supply, fabrication, and delivery of monopile foundations for the 1.1 GW wind farm which is […]