10000 results found for 'DOE'

10000 results found for 'DOE'
Order results by

A list of search results

  • 22 October 2025
    Business & Finance, Business development, Cables, Clean Fuels, Grid Connection, Innovation, Outlook & Strategy, Transition, Vessels

    Jan De Nul has launched its first XL cable-laying vessel (CLV), Fleeming Jenkin, with the final vessel construction phase now starting, including sea trials. Jan De Nul announced in October 2023 that it had placed an order for Fleeming Jenkin at China’s CMHI Haimen shipyard, followed by an order for another identical vessel, named William Thomson, last May, deemed the […]

  • 16 January 2026
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The US District Court for the District of Columbia has granted a preliminary injunction sought by Equinor for its Empire Wind 1 offshore wind farm, allowing construction activities to resume on the project that was more than 60 per cent complete at the time when the US government issued a stop-work order in December 2025. […]

  • 8 September 2025
    Business & Finance, Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Ørsted’s Greater Changhua 2b offshore wind project in Taiwan will be commissioned in the third quarter of 2026 instead of later this year due to a damaged export cable. The 300 MW offshore wind farm is part of the 920 MW Greater Changhua 2b and 4 project, currently under construction 35-60 kilometres off the coast of Changhua […]

  • 24 September 2025
    Authorities, Planning & Permitting

    Plans to develop a 1 GW offshore wind farm off Île d’Oléron have hit a setback, as the tender process closed without receiving any bids. According to the French government, the AO7 tender was not the subject of any offer at the end of the application period. The tender was launched in October 2022. The […]

  • 10 February 2026
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    Chantiers de l’Atlantique has completed the construction and integration of two offshore electrical substations for the 660 MW Nordseecluster A offshore wind farm, currently under construction off the German coast. Each of the topsides is approximately 40 metres long and 22 metres high, with one weighing about 1,800 tonnes, while the other one comes in […]

  • 16 January 2026
    Authorities, Business & Finance, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    All five developers with offshore wind farms under construction in the US are now fighting the suspension order issued by the US Department of the Interior (DOI) in December 2025, as Vineyard Wind, a company owned 50:50 by Avangrid and Copenhagen Infrastructure Partners (CIP), said on 15 January that it filed for a temporary restraining […]

  • 19 January 2026
    Fixed-Bottom, Foundations, Grid Connection, Offshore Platforms, Project Updates, Supply Chain, Wind Farm Update

    Smulders has been awarded an engineering, procurement and construction (EPC) contract for the jacket foundation that will support the offshore substation of the 600 MW Dunkerque offshore wind farm in France. Final assembly and delivery of the jacket will take place at Smulders’s French yard in Fos‑sur‑Mer, the company said via social media. French transmission […]

  • 2 February 2026
    Contracts & Tenders, Foundations, Grid Connection, Offshore Platforms, Project Updates, Supply Chain, Wind Farm Update

    Smulders has contracted KCI Offshore Engineering, a subsidiary of Sif Group, for the design of the jacket foundation that will support the offshore substation (OSS) for the 600 MW Dunkerque offshore wind farm in France. Under the contract, KCI will perform the basic and detailed design, including fabrication-suitable design and certification of the OSS jacket […]

  • 27 August 2025
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    [NOTE: This article was updated on 27 and 28 August with statements from Oceantic Network and US Wind.] The US Department of the Interior (DOI) will seek to cancel its approval of the Construction and Operations Plan (COP) granted to US Wind for its 2 GW Maryland Offshore Wind Project last year. In a recent […]

  • 20 October 2025
    Business & Finance, Infrastructure

    The Danish wind turbine manufacturer, Vestas, has decided to put on hold its plans to open its biggest factory in Poland, as European demand falters, according to Reuters. In 2024, Vestas announced that it would build a second offshore wind turbine manufacturing facility in Poland. The factory, which was expected to open in 2026, would […]

  • 5 February 2026
    Contracts & Tenders, Equipment, Floating Wind, Supply Chain, Vessels

    MacGregor will supply a 400-tonne active heave compensated (AHC) subsea crane for a new floating wind construction vessel (FWCV) that Jiangsu Dajin Heavy Industry is building in China for the South Korean company HANA Shipping. MacGregor is scheduled to deliver the crane at the end of 2027, with the vessel’s delivery following in Q2 2028. […]

  • 28 November 2025
    Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    A vessel traffic survey is scheduled to start in the coming days at the Bowdun offshore wind farm site in Scotland. The survey is due to commence on 1 December and is expected to be completed by 15 December, depending on weather conditions, according to a Notice to Mariners issued recently by the developer Thistle […]

  • 5 September 2025
    Authorities, Business & Finance, Project Updates, Wind Farm Update

    Revolution Wind, a joint venture (JV) between Ørsted and a consortium led by Skyborn Renewables, filed a complaint in the US District Court for the District of Columbia on 4 September, challenging the stop-work order issued by the US Department of the Interior’s (DOI) Bureau of Ocean Energy Management (BOEM). The states of Connecticut and […]

  • 24 November 2025
    Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The foundations for the two offshore substations have been installed at the Nordseecluster offshore wind farm site in the German North Sea. According to the CEO of RWE Offshore Wind, Sven Utermöhlen, a jacket foundation, including four piles and one transition piece, was installed at the end of last week. The offshore platforms were loaded […]

  • 16 February 2026
    Contracts & Tenders, Energy Islands, Grid Connection, Onshore Infrastructure, Supply Chain

    Belgian transmission system operator (TSO) Elia has opened a tender for civil construction works on the Princess Elisabeth Energy Island, the world’s first artificial energy island. The TSO is looking for a contractor carry out the works required to host AC and related infrastructure on Princess Elisabeth Island (PEI) in the Belgian exclusive economic zone […]

  • 26 November 2025
    Ports & Logistics, Vessels

    The Port of Rotterdam Authority has opened market consultation for a new 45-hectare terminal at the north-western corner of the Maasvlakte, intended to support offshore wind activities. The new terminal is planned to feature logistics infrastructure for storage, transport, (pre-)assembly and delivery of wind turbine and foundation components. Under the plan, the terminal will feature […]

  • 15 September 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    The developers behind the 1.5 GW Navigator North offshore wind farm in Australia have announced that they do not plan to participate in the state’s first round auction. The Navigator North offshore wind farm is being developed by a joint venture between Origin Energy and Renewable Energy Systems (RES). In July 2024, the project was […]

  • 17 October 2025
    Grid Connection, Offshore Platforms

    The Dutch/German transmission system operator (TSO) TenneT Germany has commenced the commissioning of the 900 MW DolWin5 offshore grid connection system. Following the completion of the installation campaign in the summer, the consortium of Aibel and Seatrium, together with Hitachi Energy and TenneT, started commissioning as planned in the autumn, said the TSO. In addition […]

  • 8 January 2026
    Business development, Fixed-Bottom, Foundations, Innovation, Research & Development, Supply Chain

    A consortium comprising AF Gruppen, Multiconsult, DOF, Semar, and the Norwegian University of Science and Technology (NTNU) is set to launch a new project to develop and test technology for the industrial-scale production of gravity-based concrete foundations (GBS). The BetongVIND project, scheduled to commence this month, has a total budget exceeding NOK 20 million (approximately […]

  • 17 September 2025
    Business & Finance, Business development, Floating Wind, R&D, Research & Development

    Japan’s Floating Offshore Wind Power Technology Research Association (FLOWRA) and the European Marine Energy Centre (EMEC) signed a memorandum of understanding (MoU) to explore technology development cooperation in the field of floating offshore wind. Under the agreement, FLOWRA and EMEC will explore the possibilities of establishing and managing an offshore test and demonstration site for […]

  • 25 September 2025
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Nexans has completed the final export cable campaign at the Dieppe Le Tréport offshore wind farm in France, developed by Eoliennes en Mer Dieppe Le Tréport (EMDT), a joint venture between Ocean Winds, Sumitomo Corporation, and Banque des Territoires. The operation, which involves the installation of two 225 kV High-Voltage Alternating Current (HVAC) export cables […]

  • 9 March 2026
    Vessels

    The first steel has been cut for the first of Deutsche Offshore Schifffahrt’s (DO) four construction commissioning service operation vessels (C‑CSOVs), ordered by Schoeller Holdings. The vessel, named DO Joule, is being built at the CSSC Huangpu Wenchong Shipyard in Guangzhou, China. The C-CSOV is scheduled to be delivered in May 2027, with the subsequent […]

  • 9 January 2026
    Business & Finance, Vessels

    The Maersk wind turbine installation vessel (WTIV), being built by Seatrium, has recently completed sea trials and is due for delivery at the end of February, according to the vessel owner. The new WTIV, which is planned to be deployed on Equinor’s Empire Wind offshore wind project in the US, was launched to sea at […]

  • 19 January 2026
    Business & Finance, Cables, Grid Connection, Outlook & Strategy, Vessels

    Norway-headquartered subsea services provider OMS Group has signed contracts with Norwegian shipbuilder Ulstein for the design and construction of two cable-laying vessels (CLVs). Designed by Ulstein Design & Solutions, the ULSTEIN SX252 vessels will be 130 metres long and 22 metres wide and will have a capacity of up to 6,500 tonnes of cable. “This […]

  • 17 February 2026
    Business development, Floating Wind, Foundations, Innovation, Research & Development, Wind Turbines

    A new European project focused on offshore testing infrastructure for high-power floating wind turbines was officially launched at a kick-off meeting in Nantes, France, this month. The project is co-financed by the Interreg Atlantic Area programme through the European Regional Development Fund. Named HiPoTeSis (High Power Test Sites to consolidate industrialisation of Floating Offshore Wind […]

  • 1 December 2025
    Business & Finance, Vessels

    Singapore’s Seatrium has launched arbitration proceedings against an affiliate of Maersk Offshore Wind, escalating a contract dispute over a wind turbine installation vessel (WTIV) that Maersk sought to terminate in October, the shipbuilder said. Seatrium Energy International (SEI) issued its notice of arbitration on 28 November, seeking declarations that Maersk’s affiliate Phoenix II A/S wrongfully […]