115 results found for 'Changfang and Xidao'

115 results found for 'Changfang and Xidao'
Order results by

A list of search results

  • 17 July 2023
    Wind Farm Update

    All 62 three-legged jacket foundations have been installed at the 589 MW Changfang and Xidao wind farms offshore Taiwan, according to Dennis Sanou, CEO of Changfang Xidao Offshore Wind Farms at Copenhagen Offshore Partners. Century Wind Power was responsible for manufacturing the jacket foundations, with the last one being built a few days ago. Boskalis […]

  • 28 June 2021
    Ports & Logistics, Vessels, Wind Farm Update

    The loading of the pin-piles for the Changfang and Xidao offshore wind farm has started at the Port of Kaohsiung in Taiwan. The first of the 186 locally-manufactured pin-piles are being loaded onto Boskalis’s Bokalift 1 heavy-lift vessel. Boskalis and Hwa Chi Construction Co, through a joint venture, are in charge of the transport and installation of […]

  • 24 February 2020
    Business & Finance

    Watson Farley & Williams (WFW) has advised on the project financing of the Changfang and Xidao offshore wind projects in Taiwan.

  • 11 April 2022
    Environment, Ports & Logistics, Technology, Vessels

    Boskalis will convert a number of vessels within its Offshore Energy division, including the crane ships Bokalift 1 and Bokalift 2, into hybrid vessels through the retrofitting of energy storage systems, or ‘power packs’. The modifications will be completed over the next two years and will also be carried out on two construction support vessels […]

  • 8 December 2021
    Wind Farm Update

    CTCI Machinery Corporation (CTCI MAC) has completed the manufacture and acceptance of the second and final batch of pin piles that the company produced for the jacket foundations that will be installed at the Changfang & Xidao offshore wind farm off central coast of Taiwan. The company completed the production of 69 pin piles in […]

  • 1 April 2020
    Business & Finance, Wind Farm Update

    Deutsche Bank has closed a deal contingent interest rate swap on TWD 90 billion (around EUR 2.7 billion) project finance for the development of the 589 MW Changfang and Xidao wind farm off Changhua County, Taiwan. The investment consortium, led by Copenhagen Infrastructure Partners (CIP) through its funds CI II and CI III, with two […]

  • 31 January 2024
    Manufacturing, Supply Chain

    Danish wind turbine maker Vestas has completed the first local hub-nacelle assembly and testing of the V174 offshore wind turbine nacelle at its factory in Taichung Port, Taiwan. Following the complete local assembly of hub components in 2023, Vestas has, for the first time, accomplished the merging and testing of nacelles and hubs in Taiwan, […]

  • 12 November 2021
    Vessels, Wind Farm Update

    The conversion of Boskalis’ Bokalift 2 crane vessel is expected to be completed in the coming months, after which its new crane will be installed, allowing the vessel to enter service on Taiwan’s Changfang & Xidao offshore wind project in early 2022, according to an update in the company’s half-year report. In October 2019, the […]

  • 2 June 2021
    Wind Farm Update

    CTCI Machinery Corporation (CTCI MAC) has completed the production of all 48 pin piles for the jacket foundations that will be installed on the first phase of the Changfang & Xidao offshore wind farm in Taiwan. The company, a subsidiary of Taiwanese engineering services provider CTCI, said that all the 48 pin piles were manufactured […]

  • 30 June 2020
    Contracts & Tenders

    MHI Vestas has signed a purchase agreement with Taiwan’s Yeong Guan Energy Technology Group (YGG) to source additional components for the upcoming production of V174 turbines to be installed off Taiwan. The agreement covers rotor hubs, hub plates, and nacelle base frames. The V174-9.5 MW turbines provided by MHI Vestas are due to be installed […]

  • 15 November 2022
    Wind Farm Update

    First power has been produced from the 589 MW Changfang & Xidao offshore wind farms in Taiwan, according to an update shared on social media by Dennis Sanou, CEO of the Changfang & Xidao Projects at Copenhagen Offshore Partners. The offshore wind project will comprise 62 Vestas 9.5 MW wind turbines, the first of which was […]

  • 10 July 2020
    Vessels

    Fred. Olsen Windcarrier’s jack-up vessel Brave Tern has arrived in Taiwan to work on the Yunlin offshore wind project. On 20 April, Brave Tern began its journey from the Port of Esbjerg in Denmark to Taiwan to transport and install turbines at the Yunlin wind farm. The 640 MW project will feature 80 Siemens Gamesa […]

  • 2 April 2020

    We bring you the ten most-read articles on OffshoreWIND.biz for the month of March 2020. Siemens Gamesa 11MW Turbine Prototype Goes Full Tilt Siemens Gamesa’s prototype SG 11.0-193 DD Flex wind turbine has produced 11MW of power, the turbine maker said. ABB Tech for Japanese Wind Turbine Installation Vessel ABB has won a contract to […]

  • 23 August 2023
    Fixed-Bottom, Project Updates, Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel, Bold Tern, has installed 31 out of 62 Vestas V174-9.5 MW wind turbines at the Changfang and Xidao offshore wind project in Taiwan. The first wind turbine was installed in July 2022 by the jack-up vessel Bold Tern some 15 kilometres off the coast of Changhua County. The project aims […]

  • 6 November 2019
    Vessels

    Huisman has received an order from Boskalis to deliver an offshore mast crane (OMC) for its crane vessel Bokalift 2. With a lifting capacity of 4,000mt at 100m above deck, this crane is capable of lifting jackets for wind turbines off the deck of the vessel, Huisman said. According to the company, a fly jib […]

  • 21 April 2020
    Vessels

    Fred. Olsen Windcarrier’s jack-up Brave Tern has started her journey to Taiwan to begin working on the Yunlin offshore wind project. Brave Tern departed the Port of Esbjerg in Denmark on Monday, 20 April, Fred. Olsen Windcarrier said. The jack-up is heading to Taiwan to start the installation job on the 640 MW wind farm. […]

  • 23 August 2022
    Contracts & Tenders, Wind Farm Update

    Correll Group has secured a contract with Seaway Offshore Cables for the termination and testing of cables for the Changfang & Xidao (CFXD) offshore wind farms in Taiwan. The contract covers 58 inter-array and seven offshore export subsea cables for CFXD. “We are delighted to have been awarded this project and to be again working […]

  • 9 March 2023
    Business & Finance, Vessels

    Boskalis’s new offshore wind foundation installation vessel Bokalift 2, which went into service last year after being converted from a drillship into a crane vessel, is currently undergoing modifications in the Netherlands before its scheduled work in the United States. Bokalift 2 arrived in the Port of Rotterdam in mid-February for the final outfitting ahead […]

  • 29 October 2019
    Vessels

    Boskalis is planning to convert an existing hull to create the crane vessel Bokalift 2 for deployment at Copenhagen Infrastructure Partners’ (CIP) two offshore wind farms in Taiwan. In July, Boskalis and Hwa Chi Construction Co established a joint venture to transport and install offshore foundations at CIP’s Changfang and the Xidao offshore wind farms. The parties will transport […]

  • 6 August 2020
    Operations & Maintenance, Wind Farm Update

    Copenhagen Infrastructure Partners (CIP) has teamed up with two Taiwanese companies to build an offshore wind farm operations and maintenance base in Changhua County, Taiwan. CIP has partnered with CECI Engineering Consultants, Inc. and Reiju Construction to build the O&M base. The project is currently in its design stage and is expected to be issued […]

  • 2 April 2020
    Vessels

    Bakker Sliedrecht has secured a contract to renew, modify, extend and integrate all electrotechnical installations of Boskalis’ new crane vessel Bokalift 2. Bakker Sliedrecht is responsible for the engineering, production, supply, installation, testing and commissioning of all electrical systems and installations during the conversion. The high voltage installations and the drive systems for the main […]

  • 25 April 2022
    Ports & Logistics, Wind Farm Update

    Wind turbine manufacturer Vestas has, together with its partner Tien Li Offshore Wind Technology, produced the first V174- 9.5MW™ blade at its facilities in Taiwan. The blade will be installed in 2022 at Copenhagen Infrastructure Partners’ Changfang offshore wind project and is the result of close collaboration with local suppliers and investments in local capabilities, […]

  • 30 March 2020
    Vessels

    Fred. Olsen Windcarrier’s wind farm installation vessel Brave Tern has arrived in the Port of Esbjerg in Denmark to start mobilising for the 640MW Yunlin offshore wind project in Taiwan. Brave Tern arrived in Esbjerg after completing a charter with Prysmian Group, the company said. In March 2019, Siemens Gamesa awarded Fred. Olsen Windcarrier with […]

  • 18 June 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Foundations, Supply Chain

    CSBC-DEME Wind Engineering (CDWE), a joint venture between Belgium’s DEME and Taiwanese shipbuilder CSBC, has secured a new offshore wind contract in Taiwan. CDWE has been selected by Copenhagen Infrastructure Partners (CIP) to transport and install foundations for the 500 MW Fengmiao 1 offshore wind project. The deal marks the first foundation installation contract signed […]

  • 7 November 2019
    Contracts & Tenders

    CSBC-DEME Wind Engineering (CDWE) has secured a contract for the transportation and installation of foundations at the Zhong Neng offshore wind project in Taiwan. The joint venture has also signed a Preferred Bidder Agreement (PBA) for the transportation and installation of wind turbines at the project. In order to implement the localization policy required by […]

  • 14 September 2023
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    All inter-array cables have been laid at the 589 MW Changfang and Xidao offshore wind farms in Taiwan, according to Dennis Sanou, CEO of Changfang Xidao Offshore Wind Farms at Copenhagen Offshore Partners. The installation of approximately 73 kilometres of 66kV inter-array cables that are used to connect turbine strings started in May this year. […]