Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Vessels›Brave Tern Starts Prepping for Taiwanese Offshore Wind Odyssey
Vessels

March 30, 2020 · about 6 years ago

Brave Tern Starts Prepping for Taiwanese Offshore Wind Odyssey

Fred. Olsen Windcarrier’s wind farm installation vessel Brave Tern has arrived in the Port of Esbjerg in Denmark to start mobilising for the 640MW Yunlin offshore wind project in Taiwan. Brave Tern arrived in Esbjerg after completing a charter with Prysmian Group, the company said. In March 2019, Si

1 minutes read
  • LinkedIn
  • X
  • Email
Brave Tern Starts Prepping for Taiwanese Offshore Wind Odyssey
Fred. Olsen Windcarrier/Martin Wasmund

Fred. Olsen Windcarrier’s wind farm installation vessel Brave Tern has arrived in the Port of Esbjerg in Denmark to start mobilising for the 640MW Yunlin offshore wind project in Taiwan.

Brave Tern arrived in Esbjerg after completing a charter with Prysmian Group, the company said.

In March 2019, Siemens Gamesa awarded Fred. Olsen Windcarrier with a contract to transport and install 80 Siemens Gamesa 8.0-167 DD wind turbines on the Yunlin wind farm located some six kilometres off the southwest coast of Taiwan.

The installation will be split into two phases which will be carried out in 2020 and 2021, respectively.

After installing the Yunlin wind turbines, Brave Tern will start another project in Taiwan.

The jack-up will also transport and install the 62 MHI Vestas Offshore V174-9.5MW wind turbines on the Changfang and Xidao (CFXD) offshore wind farms.

Located some 11-25 kilometres west of Taiwan, the wind farms have a combined capacity of 589MW and are scheduled to be fully operational in 2023.

This installation project will also be divided into two phases across 2022 and 2023.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Vessels

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Victoria Identifies Preferred Transmission Route for First Offshore Wind Projects
  2. 2China Three Gorges Connects First Qingzhou V & VII Offshore Wind Turbines to Grid
  3. 3Ørsted's First UK Offshore Wind Farm Marks 20 Years of Operation
  4. 4German Offshore Wind Vessel Operator Acquires 50 Pct Stake in Norwegian Crewing Company

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free