181 results found for 'V236-15.0 MW'

181 results found for 'V236-15.0 MW'
Order results by

A list of search results

  • 28 March 2025
    Business & Finance, Manufacturing, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Vestas has signed a firm order with Copenhagen Infrastructure Partners (CIP) for the Fengmiao 1 offshore wind project in Taiwan. For the 495 MW offshore wind farm off the coast of Taichung, Vestas will supply 33 V236-15.0 MW wind turbines and has also signed a long-term service agreement. This is Vestas’ first firm order for […]

  • 12 March 2025
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    EnBW is laying the first submarine cable of the internal wind farm cabling that connects all 64 Vestas V236-15.0 MW turbines of the 960 MW He Dreiht offshore wind farm. Seaway7 has been commissioned with the task. In 2022, EnBW awarded the company an engineering, procurement, installation, and commissioning (EPIC) contract for the inter-array cables for the He […]

  • 25 April 2025
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The first of 64 Vestas V236-15.0 MW wind turbines has been installed at EnBW’s He Dreiht project site offshore Germany. Completed on 24 April, the project milestone also marks the first time Vestas’s flagship wind turbine has been installed at an offshore wind farm. “With the installation of the first V236-15.0 MW, we have reached […]

  • 1 April 2025
    Business & Finance, Fixed-Bottom, Manufacturing, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Vestas has secured a firm order for the Nordlicht 1 offshore wind project in Germany, for which the Danish OEM will deliver 68 of its V236-15.0 MW wind turbines. The total order of 1,020 MW for Vattenfall’s wind farm that has a grid connection capacity of 980 MW includes an additional 40 MW to use […]

  • 13 June 2025
    Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    China’s CNOOD-Wenchong Heavy Industries (CWHI) has completed the manufacturing of the first monopiles for the 1,080 MW Inch Cape offshore wind project in Scotland. The monopiles are 11.5 metres in diameter, up to 110 metres in length, and have a maximum weight of 2,300 tonnes. The first cutting and rolling of monopiles was carried out […]

  • 13 March 2025
    Business & Finance, Contracts & Tenders, Supply Chain

    Inch Cape Offshore Limited (ICOL), a joint venture between ESB and Red Rock Renewables, has awarded a contract to OES Group to supply 54 external and internal Impressed Current Cathodic Protection (ICCP) systems to protect the offshore wind project’s monopile and transition piece foundations. The ICCC anodes will be produced in OES Group’s new dedicated […]

  • 23 April 2025
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    SK oceanplant has started the production of jacket foundations that will be installed on the 495 MW Fengmiao 1 offshore wind farm in Taiwan. SK oceanplant announced today (23 April) that it held a ceremony for the offshore wind project at its yard in Goseong County, South Gyeongsang Province, South Korea. The jacket foundations will […]

  • 22 April 2025
    Business & Finance

    Google has signed a power purchase agreement (PPA) with Denmark’s Copenhagen Infrastructure Partners for electricity generated at the 495 MW Fengmiao 1 offshore wind farm in Taiwan. The agreement in Taiwan is not only Google’s first offshore wind PPA in the country but also its debut in the Asia Pacific region. CIP was awarded capacity […]

  • 13 May 2025
    Business development, Research & Development

    Germany’s Energie Baden-Württemberg (EnBW) has initiated public consultation for its Mimer offshore wind farm, which is being developed in Sweden and could feature up to 114 turbines. EnBW is inviting authorities, organisations, and the public to submit comments at an early stage to collect views and information that may influence the content of the upcoming […]

  • 1 May 2025
    Business & Finance, Contracts & Tenders, Jobs & Recruitment, Supply Chain

    Lautec has been awarded a consultancy framework agreement for inspection services for the 495 MW Fengmiao 1 offshore wind farm in Taiwan. As part of the agreement, Lautec will provide fabrication supervisors, quality inspectors, and HSE inspectors to oversee fabrication and construction quality throughout the manufacturing phase. The company will be responsible for ensuring that […]

  • 20 March 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    Seabed preparation activities are scheduled to begin at the Inch Cape offshore wind farm site in Scotland at the end of March. N-Sea, which has been contracted for the job, will start the work within the array site and the export cable corridor on or around 30 March and continue until November 2025. Seabed preparation […]

  • 25 March 2025
    Business & Finance, Cables, Contracts & Tenders, Grid Connection, Supply Chain

    SPIE Wind Connect, part of SPIE, has been awarded a contract by Van Oord for the termination and testing of inter-array cables on the offshore wind farm that Ecowende will build at Hollandse Kust (west) lot VI in the Netherlands. The project scope involves the termination and testing of 52 66 kV inter-array cables on […]

  • 16 June 2025
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Dajin Heavy Industry has produced the first three monopiles for the Inch Cape offshore wind farm, the company said on 16 June, a few days after CNOOD-Wenchong Heavy Industries (CWHI) announced it had completed the first monopiles from the batch it is delivering for the 1 GW project in Scotland. Dajin cut the first steel for […]

  • 25 February 2025
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    Taylor Hopkinson has been awarded a quality assurance/quality control (QA/QC) surveillance contract for the Inch Cape offshore wind farm in Scotland. Taylor Hopkinson will support the fabrication and construction of Scotland’s 1.1 GW Inch Cape offshore wind farm, being jointly developed by Red Rock Renewables and ESB. The company and Brunel’s global presence spans all […]

  • 5 May 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    With the start of scour protection activities, the offshore construction work for the first phase of RWE’s 1.6 GW Nordseecluster wind project has commenced. The Nordseecluster A offshore wind farm is the first phase of the 1.6 GW Nordseecluster development that will be built north of the island of Juist in Germany. The works are […]

  • 9 July 2025
    Business & Finance, Contracts & Tenders, Supply Chain

    LS Marine Solution has been selected as the preferred bidder for the submarine cable installation work at the Shinan Ui offshore wind project in South Korea. The 390 MW offshore wind farm is being developed by a consortium led by Hanwha Ocean and SK Eternics. Construction is scheduled to begin in 2025, with submarine cable […]

  • 20 January 2025
    Contracts & Tenders, Fixed-Bottom, Foundations, Supply Chain

    The first cutting and rolling of monopiles, which will be installed at the 1.1 GW Inch Cape offshore wind farm in Scotland, have been completed by CNOOD-Wenchong Heavy Industries (CWHI) in China. CWHI hosted representatives from Inch Cape Offshore Limited, a joint venture company held equally by Red Rock Power and ESB, at its Qinzhou […]

  • 14 March 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The first eight foundations for RWE’s Nordseecluster A offshore wind farm in Germany have been offloaded at the Buss Terminal in the port of Eemshaven, the Netherlands. The foundations, of the TP-less monopile type, were delivered by Dajin Heavy Industry which manufactured them at its Penglai facility in China. Dajin produced the first foundation for […]

  • 11 February 2025
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    The developer of the Inch Cape offshore wind farm has awarded a contract to UK-based Granada Cranes to provide 72 davit crane units on one of Scotland’s largest offshore wind projects. Granada Cranes has been contracted to design and supply two separate types of davit cranes, each to suit the mixed use of jacket and […]

  • 9 May 2025
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Copenhagen Infrastructure Partners (CIP), on behalf of its fund Copenhagen Infrastructure V (CI V), has entered into an agreement to divest a 10 per cent stake in the 495 MW Fengmiao 1 offshore wind farm in Taiwan to Mitsui O.S.K. Lines (MOL). The transaction is subject to customary closing conditions, filing for Foreign Investment Approval […]

  • 12 May 2025
    Contracts & Tenders, Fixed-Bottom, Supply Chain

    UK-based Tekmar Group has been awarded a contract to provide grouting services for the 1.1 GW Inch Cape offshore wind farm in Scotland. Under the contract, Tekmar Group will deliver a specialist grouting solution for key offshore wind infrastructure. The work is scheduled to commence in September 2025. According to the company, grouting is an […]

  • 28 February 2025
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Construction activities on the Scottish Inch Cape offshore wind farm are scheduled to start this April with construction work within the project’s export cable corridor. According to a Notice to Mariners from the project team, the work will commence with operations at the export cable landfall site on or around 1 April 2025 with construction […]

  • 16 June 2025
    Business & Finance, Fixed-Bottom

    Energie Baden-Württemberg (EnBW) and Bonn-based DHL Group have signed a power purchase agreement (PPA) for 20 MW of generation capacity from the 960 MW He Dreiht offshore wind farm. The PPA relates to approximately 80 GWh of green electricity per year and has a term of ten years. The agreement will cover approximately 16 per […]

  • 2 July 2025
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    OEG has won a multi-million-pound contract to support the construction phase of the 1.1 GW Inch Cape offshore wind farm in Scotland until the project becomes operational in 2027. Under the contract, OEG will supply an integrated package of specialist topside and marine services, including marine coordination, high voltage, and ancillary port services. These will […]

  • 28 January 2025
    Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    CNOOD-Wenchong Heavy Industries (CWHI) and Inch Cape Offshore, a joint venture between ESB and Red Rock Renewables, have marked the first steel cutting for the transition pieces that will be installed at the 1.1 GW Inch Cape offshore wind farm. The transition pieces (TPs) will be manufactured at CWHI’s Zhongshan and Longxue yards in China and […]

  • 26 February 2025
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Geophysical survey operations and a static fishing gear survey are taking place within the Inch Cape offshore wind farm site and its associated export cable corridor from 19 February until the end of April. On behalf of Inch Cape Offshore Limited, a joint venture between ESB and Red Rock Renewables, the Dutch company N-Sea is […]