480 results found for 'changhua'

480 results found for 'changhua'
Order results by

A list of search results

  • 11 December 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Ørsted has sold a 50 per cent ownership share in the Greater Changhua 4 offshore wind farm to Taiwanese insurance company Cathay Life Insurance, and its affiliate Cathay Wind Power Holdings, for approximately DKK 11.6 billion (around EUR 1.55 billion). The 583 MW Greater Changhua 4 is part of the 920 MW offshore wind project […]

  • 15 November 2024
    Cables, Contracts & Tenders, Fixed-Bottom, Grid Connection, Project Updates, Supply Chain, Wind Farm Update

    Poseidon Cables, a UK-based company specialised in subsea cable installation, termination and testing, has secured a contract with Norwegian subsea services provider NCT Offshore for work on Ørsted’s 920 MW Greater Changhua 2b & 4 offshore wind farms in Taiwan. Last year, NCT Offshore was awarded the installation contract for the 66 kV inter-array cables […]

  • 13 November 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first batch of suction bucket jacket foundations, which will be installed at the Greater Changhua 2b and 4 offshore wind farms, have arrived at the Port of Taichung in Taiwan. The initial batch of foundations has arrived from HSG Sungdong in South Korea, the supplier of 33 units for the 920 MW Greater Changhua […]

  • 12 February 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The offshore substation topside for Ørsted’s Greater Changhua 2b and 4 wind farms has departed from Singapore and is en route to Taichung Port in Taiwan. The construction of the offshore substation that will be installed at the Greater Changhua 2b and 4 wind farm sites commenced in 2023 at Seatrium‘s Pioneer yard in Singapore. […]

  • 24 March 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The offshore substation (OSS) of the Greater Changhua 2b and 4 offshore wind project has been installed at its designated location 47 kilometres off the southwest coast of Taiwan. The OSS components were transported to the site by Boskalis’s vessels Mighty Servant 3 and Transshelf, and the installation of the substation was carried out by […]

  • 18 April 2025
    Fixed-Bottom, Grid Connection, Onshore Infrastructure, Project Updates, Wind Farm Update

    The first onshore substation of the 920 MW Greater Changhua 2b and 4 offshore wind project in Taiwan has been connected to the Taiwan Power Company (Taipower) onshore substation in the Changhua Coastal Industrial Park. The energisation of the onshore substation for the Greater Changhua 2b part of the project was delivered by Ørsted’s EPC contractor […]

  • 2 December 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The first batch of four jacket foundations, manufactured by Petrovietnam Technical Services Corporation (PTSC), has set sail from Vietnam. The units will be installed at Ørsted’s Greater Changhua 2b & 4 offshore wind farms in Taiwan. To celebrate this milestone, PTSC and others held a special ceremony on 1 December, with Vietnam’s Prime Minister Phạm […]

  • 19 March 2025
    Vessels

    Cadeler’s recently delivered wind turbine installation vessel, Wind Maker, has arrived in Taichung, Taiwan, from where it will sail out to the Greater Changhua 2b and 4 offshore wind project sites. Wind Maker set sail from Singapore and has arrived in Taichung, marking an important milestone for the Greater Changhua 2b and 4 offshore wind […]

  • 16 April 2025
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The first of 66 Siemens Gamesa 14 MW wind turbines that will make up the Greater Changhua 2b & 4 offshore wind farm in Taiwan has been installed. The major milestone for Ørsted’s 920 MW offshore wind project also marks a milestone for Siemens Gamesa, whose SG 14-236 DD wind turbine model is installed offshore […]

  • 18 February 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    Ørsted has commenced the offshore construction for the 920 MW Greater Changhua 2b and 4 offshore wind farms, located 35-60 kilometres off the coast of Changhua County, Taiwan. Greater Changhua 2b and 4 were awarded in June 2018 as part of Taiwan’s first competitive price-based auction, which had no mandatory local content requirements. In July […]

  • 11 April 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The first suction bucket jacket (SBJ) foundation has been installed at the Greater Changhua 2b and 4 offshore wind farm site in Taiwan, where wind turbine installation is also set to begin soon. The foundations are being installed by Heerema Marine Contractors’ heavy lift vessel Aegir, which was also used to install the project’s substation […]

  • 21 March 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    On 19 March, Shinfox Far East Energy announced that the company installed the first jacket foundation at the 300 MW Taipower Offshore Wind Project Phase II (TPC Changhua Phase II) in Taiwan. The jacket, taller than a 20-story building and heavier than 10 Boeing 747s, will provide solid support for the wind turbines, Shinfox Far […]

  • 19 November 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    CSBC-DEME Wind Engineering (CDWE) has completed the first offshore installation campaign for the Hai Long offshore wind project in Taiwan, with all jacket foundations installed at Hai Long 2. The overall project includes two offshore wind farms, namely the 518 MW Hai Long 2 and the 504 MW Hai Long 3. Hai Long 2 is […]

  • 13 November 2024
    Business & Finance, Vessels

    Glomar Offshore has been awarded a multi-year framework contract by TenneT for the supply of Emergency Response and Rescue Vessels (ERRVs) and Safety Standby Vessels (SSVs) in the German sector of the North Sea. Under the terms of the contract, Glomar Offshore will provide fully equipped ERRVs to ensure the highest levels of safety for […]

  • 12 November 2024
    Authorities, Fixed-Bottom, Planning & Permitting

    Synera Renewable Energy Group (SRE Group) has submitted the administrative contract for the 800 MW Formosa 6 offshore wind project to Taiwan’s Energy Administration, Ministry of Economic Affairs. The submission of the administrative contract, which is said to be on schedule, comes at a critical juncture in addressing the export sector’s demands for renewable power […]

  • 3 April 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    CSBC-DEME Wind Engineering (CDWE) has completed the final international transportation and load-out of pin piles for the 1,022 MW Hai Long offshore wind project in Taiwan. EEW Korea Heavy Pipe Construction (EEW KHPC) was responsible for the production of 156 out of 219 pin piles for the Hai Long offshore wind farm under a contract […]

  • 27 March 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    CSBC-DEME Wind Engineering (CDWE), utilising its Green Jade vessel, has installed the offshore topside on the jacket foundation for the Hai Long 3 offshore wind farm in Taiwan. CDWE placed the offshore topside on the jacket, which was installed at the site in August 2024. The offshore substation at the Hai Long 2 phase is […]

  • 7 March 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    CSBC-DEME Wind Engineering (CDWE) has started the 2025 installation campaign for the 1 GW Hai Long offshore wind project in Taiwan. The 1,022 MW Hai Long project comprises two offshore wind farms, the 518 MW Hai Long 2 and the 504 MW Hai Long 3, and is being developed in three phases. Hai Long 2 is […]

  • 21 April 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first Siemens Gamesa 14-222 DD turbine has been installed at the Hai Long 2A offshore wind farm in Taiwan, which is being developed by a joint venture between Northland Power, Mitsui & Co., and Gentari. The Hai Long project comprises two offshore wind farms, the 518 MW Hai Long 2 and the 504 MW […]

  • 19 March 2025
    Business & Finance, Contracts & Tenders, Grid Connection, Offshore Platforms, Supply Chain

    Bluestream Offshore, a subsidiary of OEG Energy, has been awarded a contract by transmission system operator (TSO) TenneT for the retrofit installation of a corrosion protection system on the SylWin alpha offshore converter station for the SylWin1 offshore grid connection in Germany. The award is for the subsea installation of an Impressed Current Cathodic Protection […]

  • 6 February 2025
    Business & Finance, Fixed-Bottom

    Ørsted has reported 2024 earnings from its operational offshore wind farms of DKK 23.8 billion (approximately EUR 3.2 billion), up by 20 per cent compared to 2023. The global offshore wind developer said on 6 February the increase was mainly due to the ramp-up of generation at Greater Changhua 1 and 2a offshore wind project […]

  • 3 February 2025
    Business & Finance, Contracts & Tenders, Operations & Maintenance, Supply Chain, Vessels

    The first of two M-class wind installation vessels, named Wind Maker, has been delivered to Denmark-headquartered Cadeler. The company has also signed the first contracts for its second M-class vessel, Wind Mover. Cadeler, a provider of offshore wind installation, operations and maintenance services, celebrated the naming of Wind Maker at the Hanwha Ocean shipyard in […]

  • 10 September 2024
    Fixed-Bottom, Grid Connection, Onshore Infrastructure, Project Updates, Supply Chain, Wind Farm Update

    Two people who remained hospitalised after the first person was pronounced dead following the CO2 leak at the Hai Long onshore substation in Taiwan have also passed away, a Hai Long Offshore Wind spokesperson confirmed to offshoreWIND.biz. On 20 August, several on-site workers at the Hai Long Changhua onshore substation, part of the 1,022 MW […]

  • 27 August 2024
    Fixed-Bottom, Foundations, Grid Connection, Onshore Infrastructure, Project Updates, Wind Farm Update

    This article was updated at 10:15 CET on 28 August 2024 after a response from Hai Long Offshore Wind. The CO2 leak that hospitalised 17 people working at the Hai Long onshore substation site in Changhua, Taiwan, on 20 August has claimed at least one life. On 27 August, the Hai Long Offshore Wind consortium […]

  • 5 September 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Copenhagen Infrastructure Partners (CIP) and China Steel Corporation (CSC) have organised a ceremony to mark the completion of the construction of the 300 MW Zhong Neng offshore wind farm in Taiwan. The Zhong Neng offshore wind project was constructed by a team led by Copenhagen Offshore Partners (COP), CIP’s exclusive offshore wind development partner, and […]

  • 21 August 2024
    Onshore Infrastructure, Project Updates, Wind Farm Update

    Seventeen people working on the Hai Long Changhua onshore substation, part of the Hai Long offshore wind project in Taiwan, were hospitalised on 20 August after a carbon dioxide leak at the substation. First reported by Taiwanese media citing information provided by Changhua County Fire Department, the incident is said to have left 14 on-site […]