  • 13 November 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first batch of suction bucket jacket foundations, which will be installed at the Greater Changhua 2b and 4 offshore wind farms, have arrived at the Port of Taichung in Taiwan. The initial batch of foundations has arrived from HSG Sungdong in South Korea, the supplier of 33 units for the 920 MW Greater Changhua […]

  • 19 November 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    CSBC-DEME Wind Engineering (CDWE) has completed the first offshore installation campaign for the Hai Long offshore wind project in Taiwan, with all jacket foundations installed at Hai Long 2. The overall project includes two offshore wind farms, namely the 518 MW Hai Long 2 and the 504 MW Hai Long 3. Hai Long 2 is […]

  • 13 November 2024
    Business & Finance, Vessels

    Glomar Offshore has been awarded a multi-year framework contract by TenneT for the supply of Emergency Response and Rescue Vessels (ERRVs) and Safety Standby Vessels (SSVs) in the German sector of the North Sea. Under the terms of the contract, Glomar Offshore will provide fully equipped ERRVs to ensure the highest levels of safety for […]

  • 12 November 2024
    Authorities, Fixed-Bottom, Planning & Permitting

    Synera Renewable Energy Group (SRE Group) has submitted the administrative contract for the 800 MW Formosa 6 offshore wind project to Taiwan’s Energy Administration, Ministry of Economic Affairs. The submission of the administrative contract, which is said to be on schedule, comes at a critical juncture in addressing the export sector’s demands for renewable power […]

  • 10 September 2024
    Fixed-Bottom, Grid Connection, Onshore Infrastructure, Project Updates, Supply Chain, Wind Farm Update

    Two people who remained hospitalised after the first person was pronounced dead following the CO2 leak at the Hai Long onshore substation in Taiwan have also passed away, a Hai Long Offshore Wind spokesperson confirmed to offshoreWIND.biz. On 20 August, several on-site workers at the Hai Long Changhua onshore substation, part of the 1,022 MW […]

  • 27 August 2024
    Fixed-Bottom, Foundations, Grid Connection, Onshore Infrastructure, Project Updates, Wind Farm Update

    This article was updated at 10:15 CET on 28 August 2024 after a response from Hai Long Offshore Wind. The CO2 leak that hospitalised 17 people working at the Hai Long onshore substation site in Changhua, Taiwan, on 20 August has claimed at least one life. On 27 August, the Hai Long Offshore Wind consortium […]

  • 21 August 2024
    Onshore Infrastructure, Project Updates, Wind Farm Update

    Seventeen people working on the Hai Long Changhua onshore substation, part of the Hai Long offshore wind project in Taiwan, were hospitalised on 20 August after a carbon dioxide leak at the substation. First reported by Taiwanese media citing information provided by Changhua County Fire Department, the incident is said to have left 14 on-site […]

  • 12 October 2018
    Contracts & Tenders, Wind Farm Update

    Ørsted has signed a contract with Taiwan-based Formosa Heavy Industries for the manufacture of jacket foundation pin piles for the two Changhua offshore wind farms with a combined capacity of 900MW.

  • 5 September 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Copenhagen Infrastructure Partners (CIP) and China Steel Corporation (CSC) have organised a ceremony to mark the completion of the construction of the 300 MW Zhong Neng offshore wind farm in Taiwan. The Zhong Neng offshore wind project was constructed by a team led by Copenhagen Offshore Partners (COP), CIP’s exclusive offshore wind development partner, and […]

  • 24 October 2018
    Contracts & Tenders, Wind Farm Update

    Ørsted has signed a contract with CSBC Corporation for the manufacture of ”a significant number” of wind turbine foundation pin-piles for the first 900MW Greater Changhua projects in Taiwan.

  • 13 December 2018
    Business & Finance

    Ørsted has appointed the Bank of Taiwan, Cathay United Bank and BNP Paribas as lead arrangers for financing the Greater Changhua offshore wind projects in Taiwan.

  • 26 November 2020
    Technology, Wind Farm Update

    Ericsson and Chunghwa Telecom (CHT) will build a 5G-ready network for Ørsted’s Greater Changhua 1 & 2a offshore wind farms in Taiwan. The private network will enable Ørsted’s engineers to communicate through high-quality connectivity and to have optimised workplace communications for daily operations, according to the two telecommunication companies. “The Greater Changhua 1 & 2a […]

  • 25 April 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The Greater Changhua 1 and 2a offshore wind project was officially inaugurated at an event in the Port of Taichung, Taiwan, on 25 April 2024. With a total installed capacity of 900 MW, the project is in operation and fully connected to the grid, making it the largest in Taiwan and the Asia-Pacific region, said […]

  • 16 October 2023
    Business & Finance

    Ørsted has selected Cathay Life Insurance as the preferred bidder for a 50 per cent ownership share in the 583 MW Greater Changhua 4 offshore wind farm in Taiwan. Following a competitive divestment process, Ørsted signed an exclusivity agreement with Cathay Life Insurance, selecting the Taiwanese insurance company and its affiliate as preferred bidder for the […]

  • 3 August 2018

    Ørsted and the Taiwanese Century Wind Power (CWP) have cut the first steel for the jacket foundation transition piece mock-up.

  • 10 April 2024
    Operations & Maintenance

    In February 2024, Global Maritime completed its task of providing marine warranty services (MWS) for the installation of 111 wind turbines on Ørsted’s Greater Changhua 1 and 2a offshore wind farms in Taiwan. Ørsted awarded the MWS contract to Global Maritime Singapore in March 2021. The Greater Changhua 1 and 2a offshore wind project is […]

  • 31 March 2023
    Business & Finance, Wind Farm Update

    Ørsted has taken the final investment decision (FID) on the 920 MW Greater Changhua 2b and 4 offshore wind farms in Taiwan, moving them into the construction stage. Onshore work and fabrication of components will start this year and the project construction is scheduled to be completed by the end of 2025. The project is […]

  • 3 November 2022
    Contracts & Tenders, Operations & Maintenance, Wind Farm Update

    James Fisher Renewables (JF Renewables) has partnered with Ho Lung Power Engineering (HLPE) to provide technical support for cable termination and testing (T&T) of Ørsted’s Greater Changhua offshore wind farm in Taiwan. In the new collaboration, JF Renewables will provide planning, reporting, engineering support/technical review, and skilled labour to complete cable T&T for Greater Changhua. […]

  • 9 May 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    Ørsted has appointed energy and marine consultancy, ABL, to provide marine warranty survey services (MWS) for the offshore transportation and installation (T&I) of wind turbines and cables package for the 920 MW Greater Changhua 2b and 4 offshore wind farms in Taiwan. ABL’s scope of work includes reviewing, surveying, and approving all operations relating to the transportation […]

  • 15 August 2022
    Ports & Logistics, Wind Farm Update

    Ørsted and Sing Da Marine Structure (SDMS) have loaded out the first batch of jacket foundations fully manufactured in Taiwan out of the Port of Kaohsiung. The first six jacket foundations will be transported to the 900 MW Changhua 1 and 2a wind farm in two shipments this week, Ørsted said. There, they will be […]

  • 26 May 2022
    Contracts & Tenders, Vessels, Wind Farm Update

    Heerema Marine Contractors’ heavy lift vessel Aegir has completed the installation of jacket foundations at the Greater Changhua 2a wind farm site offshore Taiwan and will now move on to do the same work on Greater Changhua 1, the company said via social media. This brought the entire 900 MW Greater Changhua 1 & 2a […]

  • 20 June 2023
    Contracts & Tenders, Wind Farm Update

    The Netherlands-based Twentsche KabelFabriek (TKF) has been awarded a cable supply contract from Ørsted for the 920 MW Greater Changhua 2b and 4 offshore wind farms in Taiwan. The contract scope includes the supply and termination of close to 200 kilometres of inter-array cables and other cables including accessories and connectors, all operating 66 kV […]

  • 29 December 2021
    Contracts & Tenders, Wind Farm Update

    Taiwanese state-owned utility Taiwan Power Co. (Taipower) and Foxwell have selected the localised Vestas V174-9.5 MW wind turbines for the 300 MW Taipower Offshore Wind Project Phase II (TPC Changhua Phase II) in Taiwan. Vestas and Foxwell have now signed supply and service agreements for the project, Alex Robertson, Vestas’ General Manager for Taiwan, said […]

  • 16 July 2021
    Ports & Logistics, Vessels, Wind Farm Update

    Offshore construction is in full swing at Ørsted’s 900 MW Changhua 1 and 2a wind farm off Changhua County, Taiwan. The second of the two offshore substation jacket foundations has now been installed at the site. The first substation jacket was installed by Heerema Marine Contractors’ (HMC) vessel Aegir in early May. Ørsted has also […]

  • 1 November 2021
    Grid Connection, Ports & Logistics, Wind Farm Update

    The topsides for the Greater Changhua 1 & 2a offshore substations have set sail from Singapore to the installation site in the Taiwan Strait, Keppel Offshore & Marine Ltd said. Keppel O&M is in charge of the engineering, procurement, and construction of the two 600 MW unmanned offshore wind farm substations, which comprise the topside […]

  • 30 April 2018
    Authorities, Contracts & Tenders, Grid Connection, Wind Farm Update

    Taiwan’s Ministry of Economic Affairs has awarded Ørsted the right to connect 900MW offshore wind capacity to Taiwan’s power grid.