262 results found for 'Greater Changhua'

262 results found for 'Greater Changhua'
Order results by

A list of search results

  • 10 July 2025
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Ørsted has secured a finance package of approximately TWD 90 billion (about EUR 2.64 billion) for the 632 MW Greater Changhua 2 offshore wind project in Taiwan. The developer reached financial close on the project finance package with 25 banks and five Export Credit Agencies (ECAs). This is part of the financing structure for the […]

  • 27 June 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    The jacket foundation installation at Ørsted’s Greater Changhua 2b & 4 offshore wind farms is nearing completion, with 61 out of 66 foundations already installed at the site in Taiwan. Additionally, a third of the wind turbines for the project are now in place. Offshore construction of the 920 MW Greater Changhua 2b and 4 […]

  • 11 July 2025

    Heerema Marine Contractors’ heavy-lift vessel Aegir has installed the final suction bucket jacket foundation at Ørsted’s 920 MW Greater Changhua 2b and 4 offshore wind farms in Taiwan. According to the company’s latest social media post, the crew onboard Aegir installed a total of 66 foundations at the site located 35-60 kilometres off the coast […]

  • 23 July 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first turbine from the 920 MW Greater Changhua 2b and 4 offshore wind farms, owned by Ørsted, has delivered first power to the national grid of Taiwan. Being built 35-60 kilometres off the coast of Changhua County, the two offshore wind sites will together comprise 66 Siemens Gamesa 14-236 14 MW wind turbines, 32 […]

  • 8 September 2025
    Business & Finance, Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Ørsted’s Greater Changhua 2b offshore wind project in Taiwan will be commissioned in the third quarter of 2026 instead of later this year due to a damaged export cable. The 300 MW offshore wind farm is part of the 920 MW Greater Changhua 2b and 4 project, currently under construction 35-60 kilometres off the coast of Changhua […]

  • 21 May 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    All suction bucket jacket (SBJ) foundations have been installed at the Greater Changhua 2b offshore wind farm in Taiwan, being developed by Ørsted. All 24 SBJ foundations have been installed by heavy-lift vessel Aegir from Heerema Marine Contractors at the 337.1 MW Greater Changhua 2b offshore wind farm. Since installing the first foundation in early […]

  • 5 August 2025
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update

    Glamox has won contracts to light the turbine foundation transition pieces for the 495 MW Fengmiao 1 offshore wind farm in Taiwan, being developed by Copenhagen Offshore Partners (COP) on behalf of Copenhagen Infrastructure Partners (CIP). Glamox will provide approximately 920 marine-certified LED luminaires to illuminate the jacket foundation transition pieces for 33 turbines. The […]

  • 9 October 2025
    Cables, Contracts & Tenders, Fixed-Bottom, Grid Connection, Project Updates, Supply Chain, Wind Farm Update

    Jan De Nul has signed a contract with Synera Renewable Energy (SRE) for the installation of subsea export cables on the Formosa 4 offshore wind farm. SRE has also selected the Belgian offshore construction contractor for export cables on its Formosa 6 offshore wind project. Under the contract for Formosa 4, Jan De Nul will […]

  • 9 October 2025
    Business & Finance, Contracts & Tenders, Supply Chain, Vessels

    Global Maritime (GM) has signed a framework agreement with Van Oord, under which the marine and engineering consultancy company will provide a range of services to support Van Oord’s work in the offshore wind sector. The framework covers consultancy and technical support for operations and maintenance (O&M) campaigns, as well as wind turbine and foundation […]

  • 18 April 2025
    Fixed-Bottom, Grid Connection, Onshore Infrastructure, Project Updates, Wind Farm Update

    The first onshore substation of the 920 MW Greater Changhua 2b and 4 offshore wind project in Taiwan has been connected to the Taiwan Power Company (Taipower) onshore substation in the Changhua Coastal Industrial Park. The energisation of the onshore substation for the Greater Changhua 2b part of the project was delivered by Ørsted’s EPC contractor […]

  • 16 April 2025
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The first of 66 Siemens Gamesa 14 MW wind turbines that will make up the Greater Changhua 2b & 4 offshore wind farm in Taiwan has been installed. The major milestone for Ørsted’s 920 MW offshore wind project also marks a milestone for Siemens Gamesa, whose SG 14-236 DD wind turbine model is installed offshore […]

  • 11 April 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The first suction bucket jacket (SBJ) foundation has been installed at the Greater Changhua 2b and 4 offshore wind farm site in Taiwan, where wind turbine installation is also set to begin soon. The foundations are being installed by Heerema Marine Contractors’ heavy lift vessel Aegir, which was also used to install the project’s substation […]

  • 24 March 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The offshore substation (OSS) of the Greater Changhua 2b and 4 offshore wind project has been installed at its designated location 47 kilometres off the southwest coast of Taiwan. The OSS components were transported to the site by Boskalis’s vessels Mighty Servant 3 and Transshelf, and the installation of the substation was carried out by […]

  • 19 March 2025
    Vessels

    Cadeler’s recently delivered wind turbine installation vessel, Wind Maker, has arrived in Taichung, Taiwan, from where it will sail out to the Greater Changhua 2b and 4 offshore wind project sites. Wind Maker set sail from Singapore and has arrived in Taichung, marking an important milestone for the Greater Changhua 2b and 4 offshore wind […]

  • 19 March 2025
    Business & Finance, Contracts & Tenders, Grid Connection, Offshore Platforms, Supply Chain

    Bluestream Offshore, a subsidiary of OEG Energy, has been awarded a contract by transmission system operator (TSO) TenneT for the retrofit installation of a corrosion protection system on the SylWin alpha offshore converter station for the SylWin1 offshore grid connection in Germany. The award is for the subsea installation of an Impressed Current Cathodic Protection […]

  • 18 February 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    Ørsted has commenced the offshore construction for the 920 MW Greater Changhua 2b and 4 offshore wind farms, located 35-60 kilometres off the coast of Changhua County, Taiwan. Greater Changhua 2b and 4 were awarded in June 2018 as part of Taiwan’s first competitive price-based auction, which had no mandatory local content requirements. In July […]

  • 12 February 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The offshore substation topside for Ørsted’s Greater Changhua 2b and 4 wind farms has departed from Singapore and is en route to Taichung Port in Taiwan. The construction of the offshore substation that will be installed at the Greater Changhua 2b and 4 wind farm sites commenced in 2023 at Seatrium‘s Pioneer yard in Singapore. […]

  • 6 February 2025
    Business & Finance, Fixed-Bottom

    Ørsted has reported 2024 earnings from its operational offshore wind farms of DKK 23.8 billion (approximately EUR 3.2 billion), up by 20 per cent compared to 2023. The global offshore wind developer said on 6 February the increase was mainly due to the ramp-up of generation at Greater Changhua 1 and 2a offshore wind project […]

  • 3 February 2025
    Business & Finance, Contracts & Tenders, Operations & Maintenance, Supply Chain, Vessels

    The first of two M-class wind installation vessels, named Wind Maker, has been delivered to Denmark-headquartered Cadeler. The company has also signed the first contracts for its second M-class vessel, Wind Mover. Cadeler, a provider of offshore wind installation, operations and maintenance services, celebrated the naming of Wind Maker at the Hanwha Ocean shipyard in […]

  • 11 December 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Ørsted has sold a 50 per cent ownership share in the Greater Changhua 4 offshore wind farm to Taiwanese insurance company Cathay Life Insurance, and its affiliate Cathay Wind Power Holdings, for approximately DKK 11.6 billion (around EUR 1.55 billion). The 583 MW Greater Changhua 4 is part of the 920 MW offshore wind project […]

  • 2 December 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The first batch of four jacket foundations, manufactured by Petrovietnam Technical Services Corporation (PTSC), has set sail from Vietnam. The units will be installed at Ørsted’s Greater Changhua 2b & 4 offshore wind farms in Taiwan. To celebrate this milestone, PTSC and others held a special ceremony on 1 December, with Vietnam’s Prime Minister Phạm […]

  • 13 November 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first batch of suction bucket jacket foundations, which will be installed at the Greater Changhua 2b and 4 offshore wind farms, have arrived at the Port of Taichung in Taiwan. The initial batch of foundations has arrived from HSG Sungdong in South Korea, the supplier of 33 units for the 920 MW Greater Changhua […]

  • 15 November 2024
    Cables, Contracts & Tenders, Fixed-Bottom, Grid Connection, Project Updates, Supply Chain, Wind Farm Update

    Poseidon Cables, a UK-based company specialised in subsea cable installation, termination and testing, has secured a contract with Norwegian subsea services provider NCT Offshore for work on Ørsted’s 920 MW Greater Changhua 2b & 4 offshore wind farms in Taiwan. Last year, NCT Offshore was awarded the installation contract for the 66 kV inter-array cables […]

  • 25 April 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The Greater Changhua 1 and 2a offshore wind project was officially inaugurated at an event in the Port of Taichung, Taiwan, on 25 April 2024. With a total installed capacity of 900 MW, the project is in operation and fully connected to the grid, making it the largest in Taiwan and the Asia-Pacific region, said […]

  • 16 October 2023
    Business & Finance

    Ørsted has selected Cathay Life Insurance as the preferred bidder for a 50 per cent ownership share in the 583 MW Greater Changhua 4 offshore wind farm in Taiwan. Following a competitive divestment process, Ørsted signed an exclusivity agreement with Cathay Life Insurance, selecting the Taiwanese insurance company and its affiliate as preferred bidder for the […]

  • 13 December 2018
    Business & Finance

    Ørsted has appointed the Bank of Taiwan, Cathay United Bank and BNP Paribas as lead arrangers for financing the Greater Changhua offshore wind projects in Taiwan.