9575 results found for 'Hesselø'

9575 results found for 'Hesselø'
Order results by

A list of search results

  • 26 May 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    ZTT’s flagship monopile installation vessel Zhongtian 39 has completed the foundation piling for China Resources Power’s Cangnan No.1 Phase II offshore wind farm expansion project. The 215-metre-long Zhongtian 39 has installed all 13 foundation piles for the 204 MW Cangnan No.1 Phase II offshore wind project in China. This was the first project undertaken and […]

  • 24 March 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The offshore substation (OSS) of the Greater Changhua 2b and 4 offshore wind project has been installed at its designated location 47 kilometres off the southwest coast of Taiwan. The OSS components were transported to the site by Boskalis’s vessels Mighty Servant 3 and Transshelf, and the installation of the substation was carried out by […]

  • 15 July 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    All 100 monopile foundations have been installed at RWE’s 1.4 GW Sofia offshore wind farm site, located 195 kilometres off the northeast coast of the UK. The achievement concludes a 14-month foundation installation campaign carried out by Van Oord as part of a joint engineering, procurement, construction and installation (EPCI) contract for both wind turbine […]

  • 15 July 2025
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Taihan Cable & Solution has completed the installation of export cables for the 364.8 MW Yeonggwang Nakwol offshore wind project in South Korea. The export cable installation, covering two 28-kilometre lines and carried out by Taihan’s cable-laying vessel (CLV) PALOS, was performed in two phases. The first phase took place over two weeks in mid-May, […]

  • 8 January 2025
    Business development, Collaboration, Outlook & Strategy

    Singapore-based shipbuilding player PaxOcean has landed a contract with Japan’s Penta-Ocean Construction to construct a 14,000 deadweight tonnage (DWT) cable laying vessel (CLV), seen as a “key project” in Japan’s offshore wind industry. According to PaxOcean, the vessel is expected to be delivered in February 2028. The deal was formalised on 3 December 2024, with the signing […]

  • 27 January 2025
    Business & Finance, Vessels

    UK-headquartered Tidal Transit has signed a memorandum of understanding (MoU) with Singapore’s Britoil Offshore Services and Sky Offshore to develop, fund, build, and operate offshore support vessels for the South Korean offshore wind industry. South Korea has set a nationwide goal of reaching 14.3 GW of offshore wind capacity by 2030. “South Korea is fast […]

  • 4 April 2025
    Project Updates, Wind Farm Update

    SSE Renewables is undertaking a benthic survey within a prospective offshore export cable route at the Berwick Bank offshore wind farm site in Scotland. The survey work is being carried out by Natural Power, utilising the Windcat 20 as the survey vessel. According to a Notice from Mariners from the project, the survey commenced on […]

  • 15 July 2025
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Vessels, Wind Farm Update

    The new cable-laying vessel (CLV) that joined Prysmian’s fleet earlier this year, Monna Lisa, has begun installing its first submarine cable at the Coastal Virginia Offshore Wind (CVOW) project site in the US, where Dominion Energy is building the country’s largest offshore wind farm. Dominion Energy selected the consortium of DEME Group and Prysmian as the Balance of Plant […]

  • 30 April 2025
    Business development, Collaboration, Innovation, Outlook & Strategy, Research & Development, Technology, Transition, Vessels

    Bureau Veritas Marine & Offshore (BV) has announced its participation in NavHyS, a new European research project aimed at advancing the use of liquid hydrogen (LH2) as marine fuel – specifically focusing on below-deck Type C LH2 tanks for service operation vessels (SOVs).

  • 6 June 2025
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Vessels, Wind Farm Update

    NKT, using its vessel NKT Victoria, is scheduled to start installing the export cable for the 1.4 GW East Anglia Three offshore wind farm in the UK this month. The vessel is expected to mobilise from the port of Karlskrona in Sweden on 14 June and work on the East Anglia Three site 24/7, conducting […]

  • 18 June 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The last three monopiles for RWE’s Sofia offshore wind farm in the UK have been loaded at the quay of EEW Special Pipe Constructions (EEW SPC) in Rostock, Germany. According to EEW SPC, a total of 100 monopiles, with weights of 1,143 to 1,521 tonnes and lengths of up to 91.8 metres, were loaded onto […]

  • 31 January 2025
    Business & Finance, Contracts & Tenders, Equipment, Foundations, Manufacturing, Supply Chain

    Vattenfall and BASF have signed contracts with EEW Special Pipe Constructions (EEW SPC) and CS Wind Offshore for component supply and with DEME and Jan De Nul for installation services for the Nordlicht 1 and Nordlicht 2 offshore wind farms in Germany. Germany’s EEW SPC will manufacture 112 monopile foundations, processing around 141,000 tonnes of […]

  • 19 March 2025
    Vessels

    Cadeler’s recently delivered wind turbine installation vessel, Wind Maker, has arrived in Taichung, Taiwan, from where it will sail out to the Greater Changhua 2b and 4 offshore wind project sites. Wind Maker set sail from Singapore and has arrived in Taichung, marking an important milestone for the Greater Changhua 2b and 4 offshore wind […]

  • 29 April 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    More than half of the wind turbines at Dogger Bank A, the first phase of the UK’s 3.6 GW Dogger Bank Wind Farm, have been installed. So far, 52 of the 95 GE Haliade-X 13 MW wind turbines that Dogger Bank A will feature are in place, according to a Notice to Mariners from the […]

  • 19 June 2025
    Business & Finance, Vessels

    Les Éoliennes en Mer Services, a consortium of Ocean Winds, Sumitomo Corporation, and Caisse des Dépôts, has signed contracts with TSM Windcat for the deployment of crew transfer vessels (CTVs) on two offshore wind farms. Two of TSM Windcat’s hydrogen-ready MK3.5 CTV models are going to be deployed at the Îles d’Yeu and Noirmoutier and Dieppe […]

  • 17 March 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Seaway7, using the jack-up vessel Seaway Ventus, is scheduled to start installing wind turbine foundations at the East Anglia Three offshore wind farm site at the beginning of April. Seaway Ventus is expected to mobilise at BOW Terminal in the Netherlands on 27 March and commence offshore work within the East Anglia Three array site […]

  • 22 April 2025
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    EEW Special Pipe Constructions (EEW SPC) has delivered the first monopiles for RWE’s Thor offshore wind farm in Denmark. In March 2025, the first of twelve shipments for the 1.1 GW Thor project was completed at Rostock Port. So far, 15 out of the total 36 monopiles being produced by EEW SPC have been collected, […]

  • 20 March 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    Seabed preparation activities are scheduled to begin at the Inch Cape offshore wind farm site in Scotland at the end of March. N-Sea, which has been contracted for the job, will start the work within the array site and the export cable corridor on or around 30 March and continue until November 2025. Seabed preparation […]

  • 14 January 2025
    Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    Wind turbine installation at the Borkum Riffgrund 3 offshore wind farm in Germany has been completed with the final Siemens Gamesa 11 MW turbine now installed. The final of the project’s 83 wind turbines was installed by Cadeler using its vessel Wind Osprey, which performed part of the installation work while the other part was […]

  • 30 January 2025
    Business & Finance, Business development, Contracts & Tenders, Fixed-Bottom, Research & Development, Supply Chain

    Norway-headquartered DeepOcean has been awarded a subsea survey contract for the Bałtyk 2 and Bałtyk 3 offshore wind projects in Poland, which are jointly developed by Equinor and Polenergia. Under the contract, DeepOcean will carry out geophysical seabed surveys of the export and inter-array cable corridors, utilising a dedicated survey remotely operated vehicle (SROV). The […]

  • 3 February 2025
    Operations & Maintenance, Ports & Logistics

    Iberdrola has inaugurated the operation and maintenance (O&M) base for the 496 MW Saint-Brieuc offshore wind farm in France. According to Iberdrola, 80 people will work in the O&M centre located in Binic-Établesm. The base controls and manages the electricity production and maintenance of the wind farm, playing a crucial role in its performance to […]

  • 21 January 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    Preparatory and trial operations for offshore construction are underway at the Baltic Power offshore wind farm site in the Polish sector of the Baltic Sea, with several vessels involved, including Van Oord’s heavy-lift ship Svanen, in advance of the upcoming monopile installation work. Van Oord’s heavy-lift vessel Svanen is currently situated at the Baltic Power […]

  • 28 March 2025
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The first wind turbine has been installed at the Sofia offshore wind farm in the UK. The 1.4 GW project, developed by RWE, will comprise 100 Siemens Gamesa 14 MW turbines, half of which will be fitted with recyclable blades. The wind turbine was installed by Cadeler’s wind turbine installation vessel (WTIV), Wind Peak, which […]

  • 24 June 2025
    Cables, Grid Connection, Project Updates, Wind Farm Update

    The final inter-array cable was installed at the 488 MW Îles d’Yeu and Noirmoutier (EMYN) offshore wind farm in France, developed by Les Éoliennes en Mer Services. The 61st and final inter-array cable was installed at the EMYN site located 11.7 kilometres from the island of Yeu and 16.5 kilometres from the island of Noirmoutier. […]

  • 19 February 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    Seabed investigations using a remotely operated vehicle (ROV) are scheduled to start at the site of Ørsted’s Hornsea Three offshore wind farm in the UK on 1 March. A work-class ROV will be deployed from a DP vessel to investigate discrete areas of the seabed, both in the array site and on the export cable […]

  • 7 February 2025
    Business & Finance, Vessels

    Ocean Winds and Cadeler have signed a vessel reservation agreement for the installation of the turbines at the BC-Wind offshore wind farm in the Polish Baltic Sea. The potential value of the contract to be negotiated during the pendency of the reservation agreement is estimated to be between EUR 48 million and EUR 56 million. […]