Search results for: hornsea two

492 results

A list of search results

  • 19 July 2023
    Environment

    Ørsted has commissioned three nearshore artificial nesting structures (ANS) designed to house Black-legged kittiwake off the East Suffolk coastline as part of plans to compensate for the potential impacts of the Hornsea 3 offshore wind farm on the species. The structures, fabricated by Suffolk-based Red7Marine and Four Tees Engineering, are located approximately one kilometre offshore, […]

  • 12 June 2023
    Infrastructure, Vessels

    Norway-based Norwind Offshore has taken delivery of the first of four Commissioning Service Operation Vessels (CSOVs) built by Vard. The delivery ceremony took place in Ålesund, on the west coast of Norway. The naming ceremony was attended by representatives of Norwind Offshore, as well as from Vard, various suppliers, and business partners. “The Norwind Gale […]

  • 26 August 2020
    Grid Connection

    Cable pull-in for the Hornsea Two offshore wind farm’s export line has been completed at the project’s landfall site at Lincolnshire’s Horseshoe Point beach. The operation, carried out by Boskalis’ cable laying vessel Ndurance, involved installing 2.4 kilometres of cable under water and toward the connection point. “Thanks to the dedication of our contracted staff, […]

  • 5 July 2021
    Wind Farm Update

    DEME Offshore has installed the 100th monopile foundation at the 165-turbine Hornsea Two wind farm offshore the UK. DEME installed the first foundation at the site some 89 kilometres north-east of Grimsby in early October 2020. The monopile foundations are being loaded at and transported from the Buss Terminal Eemshaven in the Netherlands and installed at the […]

  • 29 March 2021
    Wind Farm Update

    Sembcorp Marine has contracted Palfinger to provide cranes for the offshore substation and the reactive compensation station to be installed at Ørsted’s 1.4 GW Hornsea Two wind farm offshore the UK. Palfinger will equip the offshore substation with one telescopic crane (DKT400), two davit cranes (PF17000), and the reactive compensation station with one stiff-boom crane […]

  • 3 March 2020
    Contracts & Tenders, Wind Farm Update

    Jumbo Shipping has secured a contract with DEME Offshore for the transport of foundations for the Hornsea Two offshore wind project. Jumbo will transport 165 monopiles from Rostock, Germany, and 135 transition pieces from Aalborg, Denmark, to Eemshaven, the Netherlands, with a K3000 class vessel. Additionally, the company will undertake the project management for the […]

  • 3 June 2019
    Contracts & Tenders

    Ørsted has contracted Bladt Industries to produce 135 transition pieces for the Hornsea Project Two offshore wind farm in the UK. The fabrication of the transition pieces is planned to begin this year at Bladt’s site in Aalborg, Denmark, with delivery expected to take place from mid-2020 to mid-2021. “We are proud that Ørsted have trusted Bladt Industries as […]

  • 2 August 2019
    Contracts & Tenders, Wind Farm Update

    Tekmar Energy has signed a contract with Ørsted to provide Cable Protection Systems for the 1.4GW Hornsea Two offshore wind farm. Tekmar will provide their patented Tekmar Cable Protection System (CPS) TekLink® Mechanical Latch for the wind farm, which when constructed will become the world’s largest offshore wind farm. The contract is valued in excess […]

  • 2 October 2020
    Wind Farm Update

    The jacket foundation for the offshore substation at the Hornsea Two offshore wind project in the UK has been installed. The installation of the 4,800-tonne jacket marks the start of the project’s offshore construction. Six weeks ago, 10,000 tonnes of steel framework for the pin piles, reactor compensation and offshore substation jackets sailed from Batam, Indonesia, towards […]

  • 9 October 2020
    Wind Farm Update

    The first out of the total of 165 monopile foundations has been installed at the Hornsea Two offshore wind farm site in the UK, according to social media updates from Ørsted. The milestone comes around a week after the jacket foundation for the wind farm’s offshore substation was installed. DEME’s jack-up vessel Innovation has been […]

  • 17 May 2019
    Contracts & Tenders, Wind Farm Update

    DEME Offshore has won contracts to transport and install foundations and wind turbines on Ørsted’s 1.4GW Hornsea Two offshore wind farm in the UK. The Hornsea Two offshore wind farm is located approximately 89 kilometres off the Yorkshire coast and will comprise 165  Siemens Gamesa 8.4MW wind turbines installed on monopile foundations. DEME Offshore will transport […]

  • 4 March 2021
    Contracts & Tenders, Wind Farm Update

    Manor Renewable Energy (MRE) has signed a major contract with Ørsted to supply power to the Hornsea Two offshore wind project in the UK. MRE will provide the full temporary power solution, service technicians, and both crew transfer and walk-to-work vessels, during the construction phase of the 1.4 GW offshore wind farm. “When the company […]

  • 10 September 2021
    Contracts & Tenders, Operations & Maintenance

    Manor Renewable Energy (MRE) has signed a contract to charter a new build crew transfer vessel from WEM Marine LTD to support its work supplying temporary power solution at the 1.4 GW Hornsea Two offshore wind farm. WEM Marine LTD’s vessel, the WEM3, joined MRE on Hornsea Two in July 2021. The WEM3 is a […]

  • 4 January 2021
    Grid Connection, Wind Farm Update

    VolkerInfra has completed the onshore cable installation for the Hornsea Two offshore wind project in the UK. VolkerInfra installed a total of 350 km of cable over 39 km of Lincolnshire land, reaching from the wind farm’s landfall point at Horseshoe Point to North Killingholme. Reinstatement works are expected to continue on the ground until […]

  • 21 September 2020
    Vessels

    Louis Dreyfus Armateurs’ (LDA’s) new service operations vessel (SOV), which will be working at Ørsted’s Hornsea Two offshore wind farm, was launched on 21 September at Cemre Shipyard in Turkey. The Wind of Hope SOV, ordered in 2018, is expected to arrive at Ørsted’s operations and maintenance (O&M) facility at the port of Grimsby in […]

  • 20 November 2019
    Contracts & Tenders

    EEW Group has contracted Hutchinson Engineering Ltd for the fabrication and on-site assembly of Suspended Internal Platforms (SIPs) for the Hornsea Two offshore wind project. The Cheshire-based company is in charge of providing 30 SIPs, each weighing 10t and towering 12m high, that will be suspended inside the transition pieces. In June, Ørsted, the developer […]

  • 17 December 2015
    Authorities, Wind Farm Update

    The UK Planning Inspectorate closed the examination period for the Hornsea Two offshore wind project yesterday. The Examining Authority now has 3 months to consider the project and make a recommendation to the Secretary of State, who will then have further 3 months to make the decision. Hornsea Project Two, located approximately 89km off the Yorkshire coast, will […]

  • 16 April 2020
    Contracts & Tenders, Wind Farm Update

    FairWind has a won a contract by Bladt Industries to install the electrical scope on 135 transition pieces for the Hornsea Two offshore wind project in the UK. FairWind’s scope of work is full electrical installation, including light study design of cable support system, as well as installing all components and free issued items from […]

  • 29 September 2020
    Wind Farm Update

    Bladt Industries has completed the load out of the first transition pieces (TPs) for the Hornsea Two offshore wind farm at its facilities in Aalborg. In mid-September, the company carried out the load-out of the first six anode cages built for the 1.4 GW offshore wind project, saying the first six transition pieces would soon […]

  • 23 June 2021

    World’s leading offshore wind developer Ørsted has installed its 1,000th offshore wind turbine in UK waters. The company’s 1,000th turbine was a Siemens Gamesa 8.4 MW unit installed at the 1,386 MW Hornsea Two offshore wind farm, the 16th wind turbine to be erected at the wind farm. Ørsted currently has 12 operational offshore wind […]

  • 19 October 2020
    Grid Connection, Wind Farm Update

    Heerema Marine Contractors’ semi-submersible crane vessel Sleipnir has installed the jacket foundation for the reactive compensation station (RCS) at the Hornsea Two offshore wind project. Sleipnir installed the jacket foundation for the project’s offshore substation at the beginning of October. After the OSS foundation installation, the vessel moved to the shallow water to install the 1,500 metric […]

  • 11 April 2018
    Contracts & Tenders, Grid Connection, Operations & Maintenance, Wind Farm Update

    Ørsted and Balfour Beatty have broken ground on the onshore substation for the Hornsea Project Two offshore wind farm. Balfour Beatty is in charge of enabling works for the wind farm’s onshore substation to ensure the site preparation is underway in good time, avoiding future schedule pressures, a spokesperson from Ørsted told OffshoreWIND. The main contract for […]

  • 2 August 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Ørsted and Prysmian Group have signed a contract to supply submarine inter–array cables for the world’s biggest offshore wind farm, the 1,386MW Hornsea Project Two.

  • 17 June 2021
    Vessels, Wind Farm Update

    Turkey’s Cemre Shipyard has bid farewell to the service operations vessel (SOV) Wind of Hope. Ordered by Louis Dreyfus Armateurs (LDA), Wind of Hope’s first assignment will be on Ørsted’s 1.4 GW Hornsea Two off the UK, which will be the world’s largest wind farm once completed. The vessel will operate from Ørsted’s operations and […]

  • 21 April 2015
    Authorities, Wind Farm Update

    Registration to become an interested party on the application for the Hornsea Project Two offshore wind farm, developed by SMart Wind, will close tomorrow, April 22.  During this pre-examination stage at the Planning Inspectorate, all those who registered can have their say on the proposal and comment on the views that other people have provided. Also, they […]

  • 5 February 2021
    Vessels

    C-bed has signed a contract with Ørsted for the deployment of its Service Operation Vessel (SOV) Wind Innovation on the Hornsea Two offshore wind farm in the UK. The vessel, which has also been hired for Ørsted’s Hornsea One offshore wind farm and is currently in full operation there, will start working at the Hornsea […]