Search results for: hornsea two

427 results

A list of search results

  • 4 January 2021
    Grid Connection, Wind Farm Update

    VolkerInfra has completed the onshore cable installation for the Hornsea Two offshore wind project in the UK. VolkerInfra installed a total of 350 km of cable over 39 km of Lincolnshire land, reaching from the wind farm’s landfall point at Horseshoe Point to North Killingholme. Reinstatement works are expected to continue on the ground until […]

  • 16 August 2021
    Grid Connection, Wind Farm Update

    The Hornsea Two offshore substation (OSS) and the reactive compensation station (RCS) topsides have left the Sembcorp Marine Admiralty Yard in Singapore and are en route to the UK, Sembcorp Marine said. The two topsides departed on 15 August and are expected to reach their destination at the end of September for the integration with […]

  • 17 December 2015
    Authorities, Wind Farm Update

    The UK Planning Inspectorate closed the examination period for the Hornsea Two offshore wind project yesterday. The Examining Authority now has 3 months to consider the project and make a recommendation to the Secretary of State, who will then have further 3 months to make the decision. Hornsea Project Two, located approximately 89km off the Yorkshire coast, will […]

  • 20 November 2019
    Contracts & Tenders

    EEW Group has contracted Hutchinson Engineering Ltd for the fabrication and on-site assembly of Suspended Internal Platforms (SIPs) for the Hornsea Two offshore wind project. The Cheshire-based company is in charge of providing 30 SIPs, each weighing 10t and towering 12m high, that will be suspended inside the transition pieces. In June, Ørsted, the developer […]

  • 16 April 2020
    Contracts & Tenders, Wind Farm Update

    FairWind has a won a contract by Bladt Industries to install the electrical scope on 135 transition pieces for the Hornsea Two offshore wind project in the UK. FairWind’s scope of work is full electrical installation, including light study design of cable support system, as well as installing all components and free issued items from […]

  • 17 June 2021
    Vessels, Wind Farm Update

    Turkey’s Cemre Shipyard has bid farewell to the service operations vessel (SOV) Wind of Hope. Ordered by Louis Dreyfus Armateurs (LDA), Wind of Hope’s first assignment will be on Ørsted’s 1.4 GW Hornsea Two off the UK, which will be the world’s largest wind farm once completed. The vessel will operate from Ørsted’s operations and […]

  • 19 October 2020
    Grid Connection, Wind Farm Update

    Heerema Marine Contractors’ semi-submersible crane vessel Sleipnir has installed the jacket foundation for the reactive compensation station (RCS) at the Hornsea Two offshore wind project. Sleipnir installed the jacket foundation for the project’s offshore substation at the beginning of October. After the OSS foundation installation, the vessel moved to the shallow water to install the 1,500 metric […]

  • 11 April 2018
    Contracts & Tenders, Grid Connection, Operations & Maintenance, Wind Farm Update

    Ørsted and Balfour Beatty have broken ground on the onshore substation for the Hornsea Project Two offshore wind farm. Balfour Beatty is in charge of enabling works for the wind farm’s onshore substation to ensure the site preparation is underway in good time, avoiding future schedule pressures, a spokesperson from Ørsted told OffshoreWIND. The main contract for […]

  • 2 August 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Ørsted and Prysmian Group have signed a contract to supply submarine inter–array cables for the world’s biggest offshore wind farm, the 1,386MW Hornsea Project Two.

  • 6 August 2021
    Grid Connection, Ports & Logistics, Wind Farm Update

    The topsides for the Hornsea Two offshore substation and the reactive compensation station have been loaded onto Guangzhou Salvage’s vessel Hua Hai Long at Sembawang, Singapore. The topsides will soon be ready to start their journey to the UK, Guangzhou Salvage said. The topsides were manufactured by Sembcorp Marine. The jacket foundations for the offshore […]

  • 21 April 2015
    Authorities, Wind Farm Update

    Registration to become an interested party on the application for the Hornsea Project Two offshore wind farm, developed by SMart Wind, will close tomorrow, April 22.  During this pre-examination stage at the Planning Inspectorate, all those who registered can have their say on the proposal and comment on the views that other people have provided. Also, they […]

  • 5 February 2021
    Vessels

    C-bed has signed a contract with Ørsted for the deployment of its Service Operation Vessel (SOV) Wind Innovation on the Hornsea Two offshore wind farm in the UK. The vessel, which has also been hired for Ørsted’s Hornsea One offshore wind farm and is currently in full operation there, will start working at the Hornsea […]

  • 23 June 2021

    World’s leading offshore wind developer Ørsted has installed its 1,000th offshore wind turbine in UK waters. The company’s 1,000th turbine was a Siemens Gamesa 8.4 MW unit installed at the 1,386 MW Hornsea Two offshore wind farm, the 16th wind turbine to be erected at the wind farm. Ørsted currently has 12 operational offshore wind […]

  • 31 March 2020
    Contracts & Tenders

    Ørsted has signed a contract with Trelleborg for the provision of four integrated cable protection systems for the 1.4GW Hornsea Two offshore wind farm.

  • 3 November 2020
    Contracts & Tenders, Vessels

    Solstad Offshore has been awarded a contract by Ørsted to deploy its offshore support vessel (OSV) Normand Jarstein on the Hornsea Two offshore wind farm in the UK. The contract has been signed for a period of four months, starting in the third quarter of 2021, when the vessel will support operations at the 1.4 […]

  • 31 December 2019
    Vessels

    Louis Dreyfus Armateurs (LDA) has shared a video showing the construction of its service operations vessel (SOV) Wind of Hope. LDA placed an order with Salt Ship Design last year for the new wind farm SOV, which is being built at Turkey’s Cemre Shipyard. Wind of Hope will feature ABB technology, including the power distribution system […]

  • 27 August 2021
    Vessels, Wind Farm Update

    AFAI Southern Shipyard has delivered two 35m hybrid Incat Crowther crew transfer vessels (CTVs) to MHO-Co for the Hornsea Two offshore wind farm.  The two CTVs, MHO Asgard and MHO Apollo, that were developed in collaboration with Danfoss and Volvo Penta, will be powered by an advanced propulsion system that comprises a pair of diesel drivetrains and a pair of diesel-electric drivetrains, each driving Volvo Penta […]

  • 29 September 2020
    Wind Farm Update

    Bladt Industries has completed the load out of the first transition pieces (TPs) for the Hornsea Two offshore wind farm at its facilities in Aalborg. In mid-September, the company carried out the load-out of the first six anode cages built for the 1.4 GW offshore wind project, saying the first six transition pieces would soon […]

  • 15 June 2020
    Contracts & Tenders, Vessels

    Danish company MHO-Co has signed a contract with Afai Southern Shipyard in China for the construction of two crew transfer vessels with hybrid propulsion for the Hornsea Project Two offshore wind farm. The two vessels are scheduled for delivery in the summer of 2021, after which they will start working under a contract with Ørsted, […]

  • 9 August 2021
    Ports & Logistics, Wind Farm Update

    The Rostock-based EEW Special Pipe Constructions GmbH has loaded out the last five monopiles for Ørsted’s Hornsea Two offshore wind farm. The final five monopiles were loaded out at EEW SPC’s quay on 30 July. In the past eleven months, a total of 165 monopiles was loaded for the project by two self-geared vessels. The […]

  • 20 November 2018
    Business & Finance

    Ørsted has held a supply chain event for the Hornsea Project Two offshore wind farm allowing UK companies to find out how they can get involved in the project.

  • 29 April 2019
    Contracts & Tenders, Grid Connection

    Boskalis has won a contract for the offshore export cable installation at Ørsted’s Hornsea Project Two offshore wind farm in the UK. Under the contract worth more than EUR 100 million, Boskalis will install three export cable circuits with a total length of approximately 380km. The project scope includes the preparation of the offshore export cable route, […]

  • 2 September 2020
    Vessels

    MHO-Co and AFAI Southern Shipyard have held a keel-laying ceremony for the two hybrid crew transfer vessels (CTVs) that will service the Hornsea Two offshore wind project. MHO-Co signed a contract with the Chinese shipyard in mid-June for the construction of the two CTVs. The 35m vessels will have hybrid propulsion packages designed to be adapted […]

  • 6 July 2020
    Contracts & Tenders

    Ørsted has awarded CHC Helicopter with a contract for aerial transportation during the construction and operations phases of the Hornsea Two offshore wind project in the UK. Leonardo AW139 and AW169 helicopters based at Humberside Airport in Lincolnshire will be used for crew transfers and cargo flights to the offshore accommodation jack-up barge and installation […]

  • 9 August 2021
    Operations & Maintenance, Ports & Logistics, Vessels, Wind Farm Update

    Ørsted’s new service operations vessel (SOV) Wind of Hope has arrived in the Port of Grimsby in the UK to prepare for working out at sea on the world’s largest offshore wind farms. Up to 60 of Ørsted’s wind turbine technicians will call the 84-metre vessel home for two weeks at a time, whilst they […]

  • 28 June 2018
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Ørsted and Siemens Gamesa have signed a contract for the supply and service of 165 Siemens Gamesa 8MW wind turbines for Hornsea Project Two, world’s largest offshore wind project and the largest wind project in Siemens Gamesa’s history.