Search results for: hornsea two

204 results

A list of search results

  • 14 September 2020
    Wind Farm Update

    Bladt Industries has loaded out the first six out of the 135 anode cages built for the 1.4 GW Hornsea Project Two offshore wind farm. The first six transition pieces will soon follow, Bladt Industries said. The Danish company is in charge of manufacturing and delivering 135 transition pieces for the project. The units are […]

  • 3 July 2020
    Vessels

    Spectrum Offshore has selected MHO-Co’s vessel MHO Grimsby to assist the construction survey support at the Hornsea Two offshore wind project. The vessel, which is equipped with special survey gear for the task, will be working on the project for the next two years, MHO-Co said. Last month, Spectrum secured a construction survey support contract […]

  • 15 June 2020
    Contracts & Tenders, Vessels

    Danish company MHO-Co has signed a contract with Afai Southern Shipyard in China for the construction of two crew transfer vessels with hybrid propulsion for the Hornsea Project Two offshore wind farm. The two vessels are scheduled for delivery in the summer of 2021, after which they will start working under a contract with Ørsted, […]

  • 31 March 2020
    Contracts & Tenders

    Ørsted has signed a contract with Trelleborg for the provision of four integrated cable protection systems for the 1.4GW Hornsea Two offshore wind farm.

  • 20 November 2019
    Contracts & Tenders

    EEW Group has contracted Hutchinson Engineering Ltd for the fabrication and on-site assembly of Suspended Internal Platforms (SIPs) for the Hornsea Two offshore wind project. The Cheshire-based company is in charge of providing 30 SIPs, each weighing 10t and towering 12m high, that will be suspended inside the transition pieces. In June, Ørsted, the developer […]

  • 29 April 2019
    Contracts & Tenders, Grid Connection

    Boskalis has won a contract for the offshore export cable installation at Ørsted’s Hornsea Project Two offshore wind farm in the UK. Under the contract worth more than EUR 100 million, Boskalis will install three export cable circuits with a total length of approximately 380km. The project scope includes the preparation of the offshore export cable route, […]

  • 16 April 2020
    Contracts & Tenders, Wind Farm Update

    FairWind has a won a contract by Bladt Industries to install the electrical scope on 135 transition pieces for the Hornsea Two offshore wind project in the UK. FairWind’s scope of work is full electrical installation, including light study design of cable support system, as well as installing all components and free issued items from […]

  • 16 August 2016

    RenewableUK has welcomed the news that DONG Energy’s Hornsea Two offshore wind farm has gained planning consent from the UK Business and Energy Secretary, Greg Clark.  Wind power is currently delivering over 12% of the UK’s electricity, which is expected to increase to 20% by 2020 with offshore wind alone providing 10%. Offshore wind’s costs have […]

  • 6 July 2020
    Contracts & Tenders

    Ørsted has awarded CHC Helicopter with a contract for aerial transportation during the construction and operations phases of the Hornsea Two offshore wind project in the UK. Leonardo AW139 and AW169 helicopters based at Humberside Airport in Lincolnshire will be used for crew transfers and cargo flights to the offshore accommodation jack-up barge and installation […]

  • 17 December 2015
    Authorities, Wind Farm Update

    The UK Planning Inspectorate closed the examination period for the Hornsea Two offshore wind project yesterday. The Examining Authority now has 3 months to consider the project and make a recommendation to the Secretary of State, who will then have further 3 months to make the decision. Hornsea Project Two, located approximately 89km off the Yorkshire coast, will […]

  • 8 September 2020
    Wind Farm Update

    The first six transition pieces for the Hornsea Two offshore wind project have arrived from the UK at the Buss Terminal in Eemshaven, Netherlands. Over the next months, Buss will receive a total of 165 foundation sets, which will be handled and stored at the terminal. The foundations will then be loaded onto DEME Group’s […]

  • 20 November 2018
    Business & Finance

    Ørsted has held a supply chain event for the Hornsea Project Two offshore wind farm allowing UK companies to find out how they can get involved in the project.

  • 21 April 2015
    Authorities, Wind Farm Update

    Registration to become an interested party on the application for the Hornsea Project Two offshore wind farm, developed by SMart Wind, will close tomorrow, April 22.  During this pre-examination stage at the Planning Inspectorate, all those who registered can have their say on the proposal and comment on the views that other people have provided. Also, they […]

  • 25 February 2020
    Contracts & Tenders, Grid Connection

    Siemens Energy has selected Fussey Engineering to supply and install steel framework and cladding at the National Grid 400kV substation site adjacent to the Hornsea Two offshore wind project.

  • 31 December 2019
    Vessels

    Louis Dreyfus Armateurs (LDA) has shared a video showing the construction of its service operations vessel (SOV) Wind of Hope. LDA placed an order with Salt Ship Design last year for the new wind farm SOV, which is being built at Turkey’s Cemre Shipyard. Wind of Hope will feature ABB technology, including the power distribution system […]

  • 2 August 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Ørsted and Prysmian Group have signed a contract to supply submarine inter–array cables for the world’s biggest offshore wind farm, the 1,386MW Hornsea Project Two.

  • 26 June 2019
    Wind Farm Update

    Ørsted has placed an order with the Rostock-based EEW Special Pipe Constructions GmbH for 30 transition pieces for the 1,386MW Hornsea Two offshore wind project in the UK. The transition pieces will be manufactured at EEW Offshore Structures Britain (EEW OSB) in Teesside, the UK. Production will start in September 2019. According to Sascha Hofmeister, Managing […]

  • 11 April 2018
    Contracts & Tenders, Grid Connection, Operations & Maintenance, Wind Farm Update

    Ørsted and Balfour Beatty have broken ground on the onshore substation for the Hornsea Project Two offshore wind farm. Balfour Beatty is in charge of enabling works for the wind farm’s onshore substation to ensure the site preparation is underway in good time, avoiding future schedule pressures, a spokesperson from Ørsted told OffshoreWIND. The main contract for […]

  • 18 May 2020
    Business & Finance

    Siemens Gamesa has signed a bank guarantee line for up to EUR 600 million to cover the construction of components for the 1.4 GW Hornsea Two offshore wind farm. Located in the North Sea and owned by Danish utility company Ørsted, the farm will consist of 165 Siemens Gamesa wind turbines. BNP Paribas lead managed […]

  • 10 July 2020
    Contracts & Tenders

    UK-based wireless telecommunications provider Vilicom has been appointed to provide a mobile network during the construction, development and deployment of Ørsted’s Hornsea Two offshore wind project in the UK. Vilicom’s communication infrastructure will be built and tested in the UK prior to installation on the 1.4 GW wind farm. According to the company, the fully […]

  • 4 December 2017
    Contracts & Tenders, Wind Farm Update

    Ørsted has hired Semco Maritime as Electrical Engineering Consultant (EEC) to develop electrical and mechanical basic engineering design of the 1.4GW offshore substation and the reactive compensation station for Hornsea Project Two.

  • 7 May 2019
    Business & Finance

    Ørsted A/S plans to issue green senior bonds in the UK-market to finance its green growth ambition towards 2025 including the investments in 1,386MW Hornsea Two offshore wind farm. With the bond issuance, Ørsted targets a multi-tranche senior unsecured GBP-Sterling green bond, subject to market conditions. Tranches may include benchmark 8-year and 14-year nominal fixed […]

  • 3 September 2019
    Ports & Logistics, Wind Farm Update

    Ørsted has officially opened the Hornsea Two Offshore Construction Base (HTOCB) at Humberside Airport in Lincolnshire. The building, formerly a police station at the airport, will now house around 30 Ørsted employees who will be working around the clock to construct the 1.4GW wind farm. Hornsea Two, located 89 kilometres off the Yorkshire Coast, will […]

  • 14 August 2020
    Wind Farm Update

    The jacket foundations for the Hornsea Two offshore substation and reactive compensation station (RCS) have set sail from Indonesia towards the project site in the UK. The structures weighing over 10,000 tons departed Batam on 13 August onboard heavy transport vessel (HTV) Big Lift Barentsz. The journey will take approximately 50 days via the Indian […]

  • 19 November 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    French cable maker Nexans has won a contract to provide a subsea export cable system for the nearshore section of Ørsted’s 1.4GW Hornsea Project Two offshore wind farm in the UK. The contract is worth over EUR 150 million and will see Nexans supplying 200 kilometres of the 245 kV high voltage alternating current (HVAC) subsea export […]

  • 28 June 2018
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Ørsted and Siemens Gamesa have signed a contract for the supply and service of 165 Siemens Gamesa 8MW wind turbines for Hornsea Project Two, world’s largest offshore wind project and the largest wind project in Siemens Gamesa’s history.