Search results for: hornsea two

491 results

A list of search results

  • 29 April 2019
    Contracts & Tenders, Grid Connection

    Boskalis has won a contract for the offshore export cable installation at Ørsted’s Hornsea Project Two offshore wind farm in the UK. Under the contract worth more than EUR 100 million, Boskalis will install three export cable circuits with a total length of approximately 380km. The project scope includes the preparation of the offshore export cable route, […]

  • 2 September 2020
    Vessels

    MHO-Co and AFAI Southern Shipyard have held a keel-laying ceremony for the two hybrid crew transfer vessels (CTVs) that will service the Hornsea Two offshore wind project. MHO-Co signed a contract with the Chinese shipyard in mid-June for the construction of the two CTVs. The 35m vessels will have hybrid propulsion packages designed to be adapted […]

  • 28 June 2018
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Ørsted and Siemens Gamesa have signed a contract for the supply and service of 165 Siemens Gamesa 8MW wind turbines for Hornsea Project Two, world’s largest offshore wind project and the largest wind project in Siemens Gamesa’s history.

  • 16 April 2018
    Operations & Maintenance, Vessels, Wind Farm Update

    Louis Dreyfus Armateurs’ (LDA) new service operations vessel (SOV) will service Ørsted’s Hornsea Project Two offshore wind farm once delivered in 2021.

  • 5 November 2020
    Environment, Wind Farm Update

    Seiche Ltd. has mobilized onboard two vessels at the Hornsea Two offshore wind farm to support marine mammal safety during project construction. The Seiche team is in charge of ensuring compliance with procedures that seek to minimize the effects of construction noise on the local marine population. Key species known to occur in the project […]

  • 19 November 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    French cable maker Nexans has won a contract to provide a subsea export cable system for the nearshore section of Ørsted’s 1.4GW Hornsea Project Two offshore wind farm in the UK. The contract is worth over EUR 150 million and will see Nexans supplying 200 kilometres of the 245 kV high voltage alternating current (HVAC) subsea export […]

  • 2 August 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Ørsted and Prysmian Group have signed a contract to supply submarine inter–array cables for the world’s biggest offshore wind farm, the 1,386MW Hornsea Project Two.

  • 11 April 2018
    Contracts & Tenders, Grid Connection, Operations & Maintenance, Wind Farm Update

    Ørsted and Balfour Beatty have broken ground on the onshore substation for the Hornsea Project Two offshore wind farm. Balfour Beatty is in charge of enabling works for the wind farm’s onshore substation to ensure the site preparation is underway in good time, avoiding future schedule pressures, a spokesperson from Ørsted told OffshoreWIND. The main contract for […]

  • 17 June 2021
    Vessels, Wind Farm Update

    Turkey’s Cemre Shipyard has bid farewell to the service operations vessel (SOV) Wind of Hope. Ordered by Louis Dreyfus Armateurs (LDA), Wind of Hope’s first assignment will be on Ørsted’s 1.4 GW Hornsea Two off the UK, which will be the world’s largest wind farm once completed. The vessel will operate from Ørsted’s operations and […]

  • 21 April 2015
    Authorities, Wind Farm Update

    Registration to become an interested party on the application for the Hornsea Project Two offshore wind farm, developed by SMart Wind, will close tomorrow, April 22.  During this pre-examination stage at the Planning Inspectorate, all those who registered can have their say on the proposal and comment on the views that other people have provided. Also, they […]

  • 15 June 2020
    Contracts & Tenders, Vessels

    Danish company MHO-Co has signed a contract with Afai Southern Shipyard in China for the construction of two crew transfer vessels with hybrid propulsion for the Hornsea Project Two offshore wind farm. The two vessels are scheduled for delivery in the summer of 2021, after which they will start working under a contract with Ørsted, […]

  • 14 July 2023
    Authorities

    NOTE: The original article “Irish Government Designates 700 MW Area for Next Offshore Wind Auction, Work on Tender Design Underway”, published on the 14th of July, has been updated following information from the Irish Department of the Environment, Climate and Communications (DECC) that the grid capacity available for auction in ORESS 2.1 has been upgraded from […]

  • 12 August 2021
    Ports & Logistics, Vessels, Wind Farm Update

    50 of the 165 Siemens Gamesa 8.4 MW wind turbines have been installed at the 1,386 MW Hornsea Two, soon to be the largest offshore wind farm in the world. DEME Offshore’s jack-ups Sea Installer and Sea Challenger are transporting the turbines from Siemens Gamesa’s facilities in the Port of Hull and installing them at […]

  • 29 September 2020
    Wind Farm Update

    Bladt Industries has completed the load out of the first transition pieces (TPs) for the Hornsea Two offshore wind farm at its facilities in Aalborg. In mid-September, the company carried out the load-out of the first six anode cages built for the 1.4 GW offshore wind project, saying the first six transition pieces would soon […]

  • 23 June 2021

    World’s leading offshore wind developer Ørsted has installed its 1,000th offshore wind turbine in UK waters. The company’s 1,000th turbine was a Siemens Gamesa 8.4 MW unit installed at the 1,386 MW Hornsea Two offshore wind farm, the 16th wind turbine to be erected at the wind farm. Ørsted currently has 12 operational offshore wind […]

  • 18 May 2020
    Business & Finance

    Siemens Gamesa has signed a bank guarantee line for up to EUR 600 million to cover the construction of components for the 1.4 GW Hornsea Two offshore wind farm. Located in the North Sea and owned by Danish utility company Ørsted, the farm will consist of 165 Siemens Gamesa wind turbines. BNP Paribas lead managed […]

  • 14 August 2020
    Wind Farm Update

    The jacket foundations for the Hornsea Two offshore substation and reactive compensation station (RCS) have set sail from Indonesia towards the project site in the UK. The structures weighing over 10,000 tons departed Batam on 13 August onboard heavy transport vessel (HTV) Big Lift Barentsz. The journey will take approximately 50 days via the Indian […]

  • 16 August 2021
    Grid Connection, Wind Farm Update

    The Hornsea Two offshore substation (OSS) and the reactive compensation station (RCS) topsides have left the Sembcorp Marine Admiralty Yard in Singapore and are en route to the UK, Sembcorp Marine said. The two topsides departed on 15 August and are expected to reach their destination at the end of September for the integration with […]

  • 7 May 2019
    Business & Finance

    Ørsted A/S plans to issue green senior bonds in the UK-market to finance its green growth ambition towards 2025 including the investments in 1,386MW Hornsea Two offshore wind farm. With the bond issuance, Ørsted targets a multi-tranche senior unsecured GBP-Sterling green bond, subject to market conditions. Tranches may include benchmark 8-year and 14-year nominal fixed […]

  • 21 October 2020
    Business & Finance, Vessels, Wind Farm Update

    Cadeler, formerly known as Swire Blue Ocean, is ready to send its Pacific Orca vessel in early 2021 to support foundation installation at the Hornsea Two offshore wind farm in the UK. The company has been subcontracted by DEME to deliver a vessel which will support the installation of the wind farm’s 165 monopile foundations, and Pacific […]

  • 4 May 2018
    Authorities, Grid Connection, Wind Farm Update

    The UK Secretary of State for Business, Energy and Industrial Strategy (BEIS) has approved Ørsted’s application to reduce the number of offshore substations and increase the size of the topsides on the Hornsea Project Two offshore wind project.

  • 6 July 2020
    Contracts & Tenders

    Ørsted has awarded CHC Helicopter with a contract for aerial transportation during the construction and operations phases of the Hornsea Two offshore wind project in the UK. Leonardo AW139 and AW169 helicopters based at Humberside Airport in Lincolnshire will be used for crew transfers and cargo flights to the offshore accommodation jack-up barge and installation […]

  • 30 September 2022
    Business & Finance, Wind Farm Update

    Ørsted has completed the divestment of 50 per cent of its 1.3 GW Hornsea Two project, the world’s largest offshore wind farm in operation. The developer sold half of the project to a consortium comprising AXA IM Alts, acting on behalf of clients, and Crédit Agricole Assurances. Ørsted announced the Hornsea Two offshore farm-down in […]

  • 31 December 2019
    Contracts & Tenders, Jobs & Recruitment

    EEW Offshore Structures Britain (EEW OSB) has appointed the UK-based professional personnel leasing specialist RTS Wind Recruitment as the main supplier. RTS has partnered with EEW-OSB for a number of years throughout the Hornsea Project One and has recruited for various different positions all working towards the completion of the transition pieces. The next project […]

  • 28 March 2022
    Business & Finance, Wind Farm Update

    Ørsted has signed an agreement to divest 50 per cent of its 1.3 GW Hornsea Two offshore wind farm in the UK to a consortium comprising AXA IM Alts and Crédit Agricole Assurances for GBP 3 billion (approximately EUR 3.6 billion). The transaction is expected to close in the second half of 2022, once the […]

  • 15 March 2018
    Authorities, Environment, Grid Connection, Wind Farm Update

    UK’s Secretary of State for Business, Energy and Industrial Strategy (BEIS) has approved an increase in the total works area for the Hornsea Project Two onshore substation site.