Search results for: hornsea two

478 results

A list of search results

  • 20 November 2019
    Contracts & Tenders

    EEW Group has contracted Hutchinson Engineering Ltd for the fabrication and on-site assembly of Suspended Internal Platforms (SIPs) for the Hornsea Two offshore wind project. The Cheshire-based company is in charge of providing 30 SIPs, each weighing 10t and towering 12m high, that will be suspended inside the transition pieces. In June, Ørsted, the developer […]

  • 16 April 2020
    Contracts & Tenders, Wind Farm Update

    FairWind has a won a contract by Bladt Industries to install the electrical scope on 135 transition pieces for the Hornsea Two offshore wind project in the UK. FairWind’s scope of work is full electrical installation, including light study design of cable support system, as well as installing all components and free issued items from […]

  • 30 September 2022
    Business & Finance, Wind Farm Update

    Ørsted has completed the divestment of 50 per cent of its 1.3 GW Hornsea Two project, the world’s largest offshore wind farm in operation. The developer sold half of the project to a consortium comprising AXA IM Alts, acting on behalf of clients, and Crédit Agricole Assurances. Ørsted announced the Hornsea Two offshore farm-down in […]

  • 19 October 2020
    Grid Connection, Wind Farm Update

    Heerema Marine Contractors’ semi-submersible crane vessel Sleipnir has installed the jacket foundation for the reactive compensation station (RCS) at the Hornsea Two offshore wind project. Sleipnir installed the jacket foundation for the project’s offshore substation at the beginning of October. After the OSS foundation installation, the vessel moved to the shallow water to install the 1,500 metric […]

  • 2 February 2022
    Business & Finance, Wind Farm Update

    Ørsted will sell 50 per cent of its Hornsea Two offshore wind farm in the UK and expects to close the 1.3 GW project farm-down this year, the company said in its 2021 annual results. Putting the project in full operation will be slightly delayed due to the impact of the Omicron variant of SARS-CoV-2 on […]

  • 11 April 2018
    Contracts & Tenders, Grid Connection, Operations & Maintenance, Wind Farm Update

    Ørsted and Balfour Beatty have broken ground on the onshore substation for the Hornsea Project Two offshore wind farm. Balfour Beatty is in charge of enabling works for the wind farm’s onshore substation to ensure the site preparation is underway in good time, avoiding future schedule pressures, a spokesperson from Ørsted told OffshoreWIND. The main contract for […]

  • 2 August 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Ørsted and Prysmian Group have signed a contract to supply submarine inter–array cables for the world’s biggest offshore wind farm, the 1,386MW Hornsea Project Two.

  • 17 June 2021
    Vessels, Wind Farm Update

    Turkey’s Cemre Shipyard has bid farewell to the service operations vessel (SOV) Wind of Hope. Ordered by Louis Dreyfus Armateurs (LDA), Wind of Hope’s first assignment will be on Ørsted’s 1.4 GW Hornsea Two off the UK, which will be the world’s largest wind farm once completed. The vessel will operate from Ørsted’s operations and […]

  • 21 April 2015
    Authorities, Wind Farm Update

    Registration to become an interested party on the application for the Hornsea Project Two offshore wind farm, developed by SMart Wind, will close tomorrow, April 22.  During this pre-examination stage at the Planning Inspectorate, all those who registered can have their say on the proposal and comment on the views that other people have provided. Also, they […]

  • 20 November 2018
    Business & Finance

    Ørsted has held a supply chain event for the Hornsea Project Two offshore wind farm allowing UK companies to find out how they can get involved in the project.

  • 29 April 2019
    Contracts & Tenders, Grid Connection

    Boskalis has won a contract for the offshore export cable installation at Ørsted’s Hornsea Project Two offshore wind farm in the UK. Under the contract worth more than EUR 100 million, Boskalis will install three export cable circuits with a total length of approximately 380km. The project scope includes the preparation of the offshore export cable route, […]

  • 2 September 2020
    Vessels

    MHO-Co and AFAI Southern Shipyard have held a keel-laying ceremony for the two hybrid crew transfer vessels (CTVs) that will service the Hornsea Two offshore wind project. MHO-Co signed a contract with the Chinese shipyard in mid-June for the construction of the two CTVs. The 35m vessels will have hybrid propulsion packages designed to be adapted […]

  • 5 February 2021
    Vessels

    C-bed has signed a contract with Ørsted for the deployment of its Service Operation Vessel (SOV) Wind Innovation on the Hornsea Two offshore wind farm in the UK. The vessel, which has also been hired for Ørsted’s Hornsea One offshore wind farm and is currently in full operation there, will start working at the Hornsea […]

  • 31 March 2020
    Contracts & Tenders

    Ørsted has signed a contract with Trelleborg for the provision of four integrated cable protection systems for the 1.4GW Hornsea Two offshore wind farm.

  • 3 November 2020
    Contracts & Tenders, Vessels

    Solstad Offshore has been awarded a contract by Ørsted to deploy its offshore support vessel (OSV) Normand Jarstein on the Hornsea Two offshore wind farm in the UK. The contract has been signed for a period of four months, starting in the third quarter of 2021, when the vessel will support operations at the 1.4 […]

  • 31 December 2019
    Vessels

    Louis Dreyfus Armateurs (LDA) has shared a video showing the construction of its service operations vessel (SOV) Wind of Hope. LDA placed an order with Salt Ship Design last year for the new wind farm SOV, which is being built at Turkey’s Cemre Shipyard. Wind of Hope will feature ABB technology, including the power distribution system […]

  • 15 June 2020
    Contracts & Tenders, Vessels

    Danish company MHO-Co has signed a contract with Afai Southern Shipyard in China for the construction of two crew transfer vessels with hybrid propulsion for the Hornsea Project Two offshore wind farm. The two vessels are scheduled for delivery in the summer of 2021, after which they will start working under a contract with Ørsted, […]

  • 29 September 2020
    Wind Farm Update

    Bladt Industries has completed the load out of the first transition pieces (TPs) for the Hornsea Two offshore wind farm at its facilities in Aalborg. In mid-September, the company carried out the load-out of the first six anode cages built for the 1.4 GW offshore wind project, saying the first six transition pieces would soon […]

  • 23 June 2021

    World’s leading offshore wind developer Ørsted has installed its 1,000th offshore wind turbine in UK waters. The company’s 1,000th turbine was a Siemens Gamesa 8.4 MW unit installed at the 1,386 MW Hornsea Two offshore wind farm, the 16th wind turbine to be erected at the wind farm. Ørsted currently has 12 operational offshore wind […]

  • 7 November 2022
    Contracts & Tenders

    Iberdrola and AXA IM Alts have signed a memorandum of understanding (MoU) to explore collaboration in the offshore wind sector in France. With the agreement signed between the two companies, both parties will negotiate terms where AXA IM Alts on behalf of clients would join Iberdrola’s project as a minority shareholder if awarded in the […]

  • 5 September 2022
    Business & Finance, Contracts & Tenders, Grid Connection, Wind Farm Update

    Ofgem has selected Diamond Transmission Partners as the preferred bidder for the offshore transmission of the Hornsea Two offshore wind farm in the UK. The company now has to resolve certain matters before being granted the Offshore Transmission Owner (OFTO) license for the 1.3 GW project. Diamond Transmission Partners has to establish the necessary arrangements […]

  • 6 July 2020
    Contracts & Tenders

    Ørsted has awarded CHC Helicopter with a contract for aerial transportation during the construction and operations phases of the Hornsea Two offshore wind project in the UK. Leonardo AW139 and AW169 helicopters based at Humberside Airport in Lincolnshire will be used for crew transfers and cargo flights to the offshore accommodation jack-up barge and installation […]

  • 28 June 2018
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Ørsted and Siemens Gamesa have signed a contract for the supply and service of 165 Siemens Gamesa 8MW wind turbines for Hornsea Project Two, world’s largest offshore wind project and the largest wind project in Siemens Gamesa’s history.

  • 16 April 2018
    Operations & Maintenance, Vessels, Wind Farm Update

    Louis Dreyfus Armateurs’ (LDA) new service operations vessel (SOV) will service Ørsted’s Hornsea Project Two offshore wind farm once delivered in 2021.

  • 19 November 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    French cable maker Nexans has won a contract to provide a subsea export cable system for the nearshore section of Ørsted’s 1.4GW Hornsea Project Two offshore wind farm in the UK. The contract is worth over EUR 150 million and will see Nexans supplying 200 kilometres of the 245 kV high voltage alternating current (HVAC) subsea export […]

  • 5 November 2020
    Environment, Wind Farm Update

    Seiche Ltd. has mobilized onboard two vessels at the Hornsea Two offshore wind farm to support marine mammal safety during project construction. The Seiche team is in charge of ensuring compliance with procedures that seek to minimize the effects of construction noise on the local marine population. Key species known to occur in the project […]