Search results for: hornsea two

9752 results

A list of search results

  • 2 August 2019
    Contracts & Tenders, Wind Farm Update

    Tekmar Energy has signed a contract with Ørsted to provide Cable Protection Systems for the 1.4GW Hornsea Two offshore wind farm. Tekmar will provide their patented Tekmar Cable Protection System (CPS) TekLink® Mechanical Latch for the wind farm, which when constructed will become the world’s largest offshore wind farm. The contract is valued in excess […]

  • 3 June 2019
    Contracts & Tenders

    Ørsted has contracted Bladt Industries to produce 135 transition pieces for the Hornsea Project Two offshore wind farm in the UK. The fabrication of the transition pieces is planned to begin this year at Bladt’s site in Aalborg, Denmark, with delivery expected to take place from mid-2020 to mid-2021. “We are proud that Ørsted have trusted Bladt Industries as […]

  • 3 March 2020
    Contracts & Tenders, Wind Farm Update

    Jumbo Shipping has secured a contract with DEME Offshore for the transport of foundations for the Hornsea Two offshore wind project. Jumbo will transport 165 monopiles from Rostock, Germany, and 135 transition pieces from Aalborg, Denmark, to Eemshaven, the Netherlands, with a K3000 class vessel. Additionally, the company will undertake the project management for the […]

  • 17 May 2019
    Contracts & Tenders, Wind Farm Update

    DEME Offshore has won contracts to transport and install foundations and wind turbines on Ørsted’s 1.4GW Hornsea Two offshore wind farm in the UK. The Hornsea Two offshore wind farm is located approximately 89 kilometres off the Yorkshire coast and will comprise 165  Siemens Gamesa 8.4MW wind turbines installed on monopile foundations. DEME Offshore will transport […]

  • 17 December 2015
    Authorities, Wind Farm Update

    The UK Planning Inspectorate closed the examination period for the Hornsea Two offshore wind project yesterday. The Examining Authority now has 3 months to consider the project and make a recommendation to the Secretary of State, who will then have further 3 months to make the decision. Hornsea Project Two, located approximately 89km off the Yorkshire coast, will […]

  • 16 April 2020
    Contracts & Tenders, Wind Farm Update

    FairWind has a won a contract by Bladt Industries to install the electrical scope on 135 transition pieces for the Hornsea Two offshore wind project in the UK. FairWind’s scope of work is full electrical installation, including light study design of cable support system, as well as installing all components and free issued items from […]

  • 16 August 2016

    RenewableUK has welcomed the news that DONG Energy’s Hornsea Two offshore wind farm has gained planning consent from the UK Business and Energy Secretary, Greg Clark.  Wind power is currently delivering over 12% of the UK’s electricity, which is expected to increase to 20% by 2020 with offshore wind alone providing 10%. Offshore wind’s costs have […]

  • 20 November 2018
    Business & Finance

    Ørsted has held a supply chain event for the Hornsea Project Two offshore wind farm allowing UK companies to find out how they can get involved in the project.

  • 21 April 2015
    Authorities, Wind Farm Update

    Registration to become an interested party on the application for the Hornsea Project Two offshore wind farm, developed by SMart Wind, will close tomorrow, April 22.  During this pre-examination stage at the Planning Inspectorate, all those who registered can have their say on the proposal and comment on the views that other people have provided. Also, they […]

  • 31 March 2020
    Contracts & Tenders

    Ørsted has signed a contract with Trelleborg for the provision of four integrated cable protection systems for the 1.4GW Hornsea Two offshore wind farm.

  • 20 November 2019
    Contracts & Tenders

    EEW Group has contracted Hutchinson Engineering Ltd for the fabrication and on-site assembly of Suspended Internal Platforms (SIPs) for the Hornsea Two offshore wind project. The Cheshire-based company is in charge of providing 30 SIPs, each weighing 10t and towering 12m high, that will be suspended inside the transition pieces. In June, Ørsted, the developer […]

  • 29 April 2019
    Contracts & Tenders, Grid Connection

    Boskalis has won a contract for the offshore export cable installation at Ørsted’s Hornsea Project Two offshore wind farm in the UK. Under the contract worth more than EUR 100 million, Boskalis will install three export cable circuits with a total length of approximately 380km. The project scope includes the preparation of the offshore export cable route, […]

  • 4 May 2018
    Authorities, Grid Connection, Wind Farm Update

    The UK Secretary of State for Business, Energy and Industrial Strategy (BEIS) has approved Ørsted’s application to reduce the number of offshore substations and increase the size of the topsides on the Hornsea Project Two offshore wind project.

  • 28 June 2018
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Ørsted and Siemens Gamesa have signed a contract for the supply and service of 165 Siemens Gamesa 8MW wind turbines for Hornsea Project Two, world’s largest offshore wind project and the largest wind project in Siemens Gamesa’s history.

  • 25 February 2020
    Contracts & Tenders, Grid Connection

    Siemens Energy has selected Fussey Engineering to supply and install steel framework and cladding at the National Grid 400kV substation site adjacent to the Hornsea Two offshore wind project.

  • 31 December 2019
    Vessels

    Louis Dreyfus Armateurs (LDA) has shared a video showing the construction of its service operations vessel (SOV) Wind of Hope. LDA placed an order with Salt Ship Design last year for the new wind farm SOV, which is being built at Turkey’s Cemre Shipyard. Wind of Hope will feature ABB technology, including the power distribution system […]

  • 26 June 2019
    Wind Farm Update

    Ørsted has placed an order with the Rostock-based EEW Special Pipe Constructions GmbH for 30 transition pieces for the 1,386MW Hornsea Two offshore wind project in the UK. The transition pieces will be manufactured at EEW Offshore Structures Britain (EEW OSB) in Teesside, the UK. Production will start in September 2019. According to Sascha Hofmeister, Managing […]

  • 11 April 2018
    Contracts & Tenders, Grid Connection, Operations & Maintenance, Wind Farm Update

    Ørsted and Balfour Beatty have broken ground on the onshore substation for the Hornsea Project Two offshore wind farm. Balfour Beatty is in charge of enabling works for the wind farm’s onshore substation to ensure the site preparation is underway in good time, avoiding future schedule pressures, a spokesperson from Ørsted told OffshoreWIND. The main contract for […]

  • 2 August 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Ørsted and Prysmian Group have signed a contract to supply submarine inter–array cables for the world’s biggest offshore wind farm, the 1,386MW Hornsea Project Two.

  • 19 November 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    French cable maker Nexans has won a contract to provide a subsea export cable system for the nearshore section of Ørsted’s 1.4GW Hornsea Project Two offshore wind farm in the UK. The contract is worth over EUR 150 million and will see Nexans supplying 200 kilometres of the 245 kV high voltage alternating current (HVAC) subsea export […]

  • 3 September 2019
    Ports & Logistics, Wind Farm Update

    Ørsted has officially opened the Hornsea Two Offshore Construction Base (HTOCB) at Humberside Airport in Lincolnshire. The building, formerly a police station at the airport, will now house around 30 Ørsted employees who will be working around the clock to construct the 1.4GW wind farm. Hornsea Two, located 89 kilometres off the Yorkshire Coast, will […]

  • 7 May 2019
    Business & Finance

    Ørsted A/S plans to issue green senior bonds in the UK-market to finance its green growth ambition towards 2025 including the investments in 1,386MW Hornsea Two offshore wind farm. With the bond issuance, Ørsted targets a multi-tranche senior unsecured GBP-Sterling green bond, subject to market conditions. Tranches may include benchmark 8-year and 14-year nominal fixed […]

  • 21 August 2015
    Business & Finance, Wind Farm Update

    Today, DONG Energy acquired the Hornsea Zone and the project rights to Hornsea Project Two and Three, which have the potential of 3 gigawatts (GW) of offshore wind capacity. This follows DONG Energy’s acquisition of Hornsea Project One, a 1,200 megawatt (MW) offshore wind project in the Round 3, which was announced in February 2015. […]

  • 18 May 2020
    Business & Finance

    Siemens Gamesa has signed a bank guarantee line for up to EUR 600 million to cover the construction of components for the 1.4 GW Hornsea Two offshore wind farm. Located in the North Sea and owned by Danish utility company Ørsted, the farm will consist of 165 Siemens Gamesa wind turbines. BNP Paribas lead managed […]

  • 10 August 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    The UK founded infrastructure group Balfour Beatty has secured a contract to build the onshore substation for Ørsted’s Hornsea Project Two offshore wind project on the East coast of England.

  • 31 December 2019
    Contracts & Tenders, Jobs & Recruitment

    EEW Offshore Structures Britain (EEW OSB) has appointed the UK-based professional personnel leasing specialist RTS Wind Recruitment as the main supplier. RTS has partnered with EEW-OSB for a number of years throughout the Hornsea Project One and has recruited for various different positions all working towards the completion of the transition pieces. The next project […]