2711 results found for 'Hywind Scotland'

2711 results found for 'Hywind Scotland'
Order results by

A list of search results

  • 15 July 2024
    Authorities, Floating Wind, Planning & Permitting

    The Scottish Government has received a consent application for the offshore array of the 3.6 GW Ossian floating wind project, being co-developed by SSE Renewables, Marubeni Corporation, and Copenhagen Infrastructure Partners (CIP). The scope of this application covers the generating assets and transmission platforms within the offshore array, with the offshore export cables and onshore […]

  • 20 February 2024
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The first Siemens Gamesa 108-metre-long wind turbine blades have left its manufacturing factory in Hull for the Moray West offshore wind project in Scotland. Nine of the 180 blades destined for the 882 MW offshore wind farm were loaded onto the Rotra Mare transporter ship at the Siemens Gamesa blade factory in Hull, and are […]

  • 29 January 2024
    Authorities, Business development, Floating Wind, Planning & Permitting, Project Updates, Research & Development, Wind Farm Update

    Stromar Offshore Wind Farm Limited, a joint venture between Ørsted, BlueFloat Energy, and Renantis, has submitted the environmental impact assessment (EIA) scoping and habitats regulations appraisal (HRA) screening reports for the 1 GW floating offshore wind farm in Scotland. The reports for the project, which is located approximately 50 kilometres from the Port of Wick, […]

  • 6 March 2024
    Floating Wind, Grid Connection, Planning & Permitting, Project Updates, Wind Farm Update

    The developers of the 1.4 GW Cenos floating offshore wind project in Scotland are set to run a nearshore survey campaign in March to revalidate data collected in 2017 by NorthConnect, an interconnector project whose infrastructure Cenos planned to use to connect to the grid. Starting on 11 March, the export cable corridor surveys will […]

  • 27 May 2024
    Fixed-Bottom, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Lamprell has completed the final delivery of transition pieces (TPs) for Ocean Winds’ Moray West offshore wind farm in Scotland. All 62 TPs, including the penultimate and final batch destined for Scotland, have been delivered and handed over to Lamprell’s client Ocean Winds. According to the UAE-based company, the project was completed on schedule and […]

  • 20 February 2024
    Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    DEME’s vessel Orion has installed its first XXL monopile foundation at the 882 MW Moray West offshore wind farm in Scotland. The company’s jack-up vessel Apollo is also joining the offshore work, taking care of installing the transition pieces at the construction site. Orion is performing monopile installation in addition to Bokalift 2, which kicked […]

  • 21 February 2024
    Business & Finance, Business development, Floating Wind, Research & Development

    BayWa r.e. AG has a development portfolio of over 9 GW in floating wind power projects in Italy, underlining its ambition to become an established player in the offshore wind industry, said the company. Integrated into a global offshore wind team, a dedicated offshore project development team has been set up in Rome which is […]

  • 10 July 2024
    Authorities, Floating Wind, Planning & Permitting

    Thistle Wind Partners (TWP), a consortium comprising DEME, Qair, and Aspiravi, has submitted the offshore scoping report for the Ayre floating offshore wind project to the Scottish Government’s Marine Directorate. The report was submitted to the Marine Directorate – Licensing & Operations Team to request a scoping opinion under the Environmental Impact Assessment (EIA) regulations. It provides […]

  • 24 June 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain, Wind Turbines

    Denmark’s Cadeler has signed a firm contract with Inch Cape Offshore Limited, a joint venture between Red Rock Power Limited and ESB, for the installation of 72 Vestas 15 MW wind turbines at the 1.1 GW offshore wind farm in Scotland. The contract value is projected to fall within the range of EUR 114 – […]

  • 26 March 2024
    Business & Finance, Contracts & Tenders, Supply Chain

    Thistle Wind Partners (TWP), a consortium involving DEME, Qair, and Aspiravi, has awarded Ramboll the contract for pre-FEED (Front-End Engineering Design) of the foundations for its 1 GW Bowdun offshore wind farm in Scotland. The scope of work includes the substructure design for the wind turbines consisting of a base-case jacket design concept for water […]

  • 25 July 2024
    Authorities, Fixed-Bottom, Floating Wind, Planning & Permitting

    The UK government will today (25 July) introduce a bill to establish Great British Energy, a publicly owned clean energy company. Ahead of issuing the bill, the government revealed a partnership between the new company and The Crown Estate which is estimated to lead to as much as 20-30 GW in new offshore wind seabed […]

  • 3 April 2024
    Fixed-Bottom, Manufacturing, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Dajin Heavy Industry has sent off the first batch of three wind turbine towers for the Moray West offshore wind farm, the company said on 3 April via social media. According to Dajin Heavy Industry, the company is the first Chinese supplier to deliver towers for 14 MW offshore wind turbines to the European wind […]

  • 23 February 2024
    Business & Finance, Fixed-Bottom, Planning & Permitting

    ScottishPower Renewables, Iberdrola’s company in the UK, is getting the East Anglia One North and East Anglia Two offshore wind projects ready for the upcoming auction round for Contracts for Difference (CfD). This is according to project updates Iberdrola published as part of its financial results for 2023. Iberdrola says “good progress is being made […]

  • 19 March 2024
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The installation of Siemens Gamesa’s 14 MW wind turbines at the Moray West offshore wind farm site in Scotland is scheduled to start in April. The vessel chartered to install the turbines, Cadeler’s Wind Orca, has just arrived in Esbjerg, Denmark, to mobilise for the project after completing a crane upgrade in the Netherlands. In […]

  • 13 February 2024
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The second offshore substation platform (OSP) has been installed at the Moray West offshore wind farm site in Scotland. The first OSP was installed in December 2023 by Boskalis’ DP installation vessel Bokalift 1 which also mounted the second OSP on its foundations on 10 January, according to a notice of operations from the project. […]

  • 15 April 2024
    Equipment, Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Belgian offshore construction company DEME, using its vessel Orion, has completed the installation of monopiles at the Moray West offshore wind farm site in Scotland.  Monopile installation at Moray West started in October 2023, with Boskalis’s vessel Bokalift 2 deployed for the work and Orion taking over in February. DEME’s Orion installed 29 monopiles for Ocean […]

  • 2 April 2024
    Business & Finance, Business development, R&D, Research & Development, Technology

    The Offshore Renewable Energy (ORE) Catapult and Vattenfall have signed a three-year extension on their testing and demonstration collaboration at the 96.8 MW Aberdeen Offshore Wind Farm, also known as the European Offshore Wind Deployment Centre (EOWDC) in Scotland. The partnership at the 96.8MW offshore wind test and demonstration facility first began in 2019. Since then, technologies that […]

  • 23 April 2024
    Contracts & Tenders, Project Updates, Supply Chain, Wind Farm Update

    Integrated energy services provider, Kent, has been awarded a contract by Spiorad na Mara Limited for the pre-front end engineering design (Pre-FEED) assessment of the proposed Spiorad na Mara offshore wind farm in Scotland. The project, formerly known as N4, will play a significant role in helping Scotland achieve its net zero emissions target by […]

  • 18 March 2024
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Boskalis has completed the work the company was contracted to perform on the Moray West offshore wind farm. While the Dutch offshore construction company has now wrapped up its part of the job, work on Ocean Winds’ 882 MW project offshore Scotland continues with the installation of foundations and inter-array cables underway. Boskalis says that […]

  • 4 April 2024
    Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The first 14 MW turbine nacelles have been loaded onto the roll-on/roll-off (Ro-Ro) vessel, Rotra Vente, at Siemens Gamesa’s Cuxhaven plant in Germany. They are destined for the Moray West offshore wind farm and are heading toward the Port of Nigg, Scotland, according to AIS data available online. The vessel left Cuxhaven on 3 April […]

  • 26 June 2024
    Business & Finance, Contracts & Tenders, Supply Chain

    UK-headquartered 2H has been awarded a four-year integrity management (IM) contract for the 882 MW Moray West offshore wind farm in Scotland. The contract’s scope covers IM for all balance of plant (BoP) equipment, including the wind turbine’s monopile foundations and tower structures, inter-array and export cables, and offshore and onshore substations. According to 2H, […]

  • 26 March 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first Siemens Gamesa wind turbine blades and tower components for Ocean Winds’ Moray West offshore wind farm have arrived at the Port of Nigg in Scotland. The 882 MW offshore wind farm, developed by Ocean Winds, will comprise 60 wind turbines and will be the first project to feature Siemens Gamesa’s SG 14-222 DD model. The turbines […]

  • 1 July 2024
    Floating Wind, Planning & Permitting

    Eolus has submitted an application to the Swedish government for permission to build a 2.2 GW floating offshore wind farm at a site located 20 kilometres north of Gotska Sandön and about 100 kilometres southeast of Stockholm. The project, named Skidbladner and developed by Simply Blue Group, is planned to comprise a maximum of 147 […]

  • 26 February 2024
    Manufacturing, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Siemens Gamesa has rolled out the first 14 MW wind turbine nacelles at its Cuxhaven plant in Germany as the production of wind turbine components for the Moray West offshore wind farm is currently underway. The first batch of nacelles is now awaiting shipment and installation at the Moray West project site offshore Scotland, Siemens […]

  • 12 February 2024
    Business development, Floating Wind, Industry, Jobs & Recruitment, R&D, Research & Development

    Three Welsh companies have been selected for Offshore Renewable Energy (ORE) Catapult’s first Fit 4 Offshore Renewables (F4OR) programme in Wales. The three companies that were selected to take part in the F4OR programme are Ledwood Mechanical Engineering, Mainstay Marine Solutions, and CELSA Steel UK. The 12-18 month programme will be delivered by ORE Catapult, […]

  • 21 May 2024
    Business & Finance, Ports & Logistics

    Haventus, the owner of the Ardersier Port in the Moray Firth, Scotland, has taken a final investment decision and kicked off construction work on redeveloping the port to serve both fixed-bottom and floating offshore wind projects. The revamped port is expected to open in the second half of 2025. This month, Haventus was granted a […]