  • 10 June 2026
    Ports & Logistics, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Towers, nacelles and blades for SG 14-236 DD wind turbines are arriving at Mukran Port on the German Baltic Sea coast, from where they will be installed at Iberdrola’s Windanker offshore wind farm. The 315 MW Windanker will comprise 21 turbines, equipped with Siemens Gamesa’s Power Boost, which will enable each turbine to deliver approximately […]

  • 4 June 2026
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Van Oord has completed the inter-array cable installation campaign at the Windanker offshore wind farm site in the Baltic Sea. According to the project owner and developer, Iberdrola, the campaign involved the installation and burial of 21 inter-array cables with a combined length of 28 kilometres. The works were completed on schedule and without any […]

  • 14 May 2026
    Project Updates, Supply Chain, Vessels, Wind Farm Update

    DEME’s new jack-up offshore installation vessel Norse Energi is preparing to begin work on offshore wind projects in the Baltic Sea and North Sea, with its first assignments lined up for Iberdrola’s Windanker offshore wind farm in Germany and Ørsted’s Hornsea 3 in the UK. The vessel, officially named on 12 May at DEME’s base […]

  • 3 February 2026
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Project Updates, Wind Farm Update

    Amazon has signed a Power Purchase Agreement (PPA) for 110 MW from Nordseecluster B offshore wind farm, the second phase of the Nordseecluster project in Germany, owned by RWE and Norges Bank Investment Management. The PPAbuilds on the Strategic Framework Agreement that RWE and Amazon signed in June 2025, under which RWE supports Amazon’s carbon-free […]

  • 11 February 2026
    Fixed-Bottom, Grid Connection, Wind Farm Update

    Germany’s total offshore wind power generation in 2025 amounted to 26.1 TWh, of which 20.8 TWh came from the North Sea and 5.38 TWh from the Baltic Sea, according to TenneT Germany, the transmission system operator (TSO) in charge of the country’s North Sea grid. In this article: With onshore wind farms contributing 106.5 TWh […]

  • 14 January 2026
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates

    HSI, a joint venture between HSM Offshore Energy, Smulders and Iv, has installed the Jasmund offshore substation (OSS), which will connect the Windanker offshore wind farm to the German electricity grid, at its designated location in the Baltic Sea. The Jasmund platform is part of the Ostwind 3 grid connection project, which will collect 300 MW […]

  • 12 May 2026
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    Navantia Seanergies and Windar Renovables have shipped the final monopiles for East Anglia Three directly to the offshore project site in the UK. The monopiles for the 95-turbine offshore wind farm are being supplied by Haizea Wind Group and the Navantia-Windar consortium, with Windar also delivering the transition pieces for the project. Navantia and Windar’s share of […]

  • 1 April 2026
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    Half of the 62 jacket foundations have been installed at the Dieppe-Le-Tréport offshore wind project site in France. The first wind turbine foundation was installed at the project site, located 15 kilometres off the city of Le Tréport and 17 kilometres off the city of Dieppe, by DEME’s installation vessel Innovation in September 2025. By February […]

  • 30 June 2026
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    DEME has completed the installation of the jacket foundations at the Dieppe-Le Tréport offshore wind farm in France, developed by Eoliennes en Mer Dieppe Le Tréport (EMDT), a joint venture between Ocean Winds, Sumitomo Corporation, and Banque des Territoires. The first of the 62 wind turbine foundations was installed at the project site, located 15 […]

  • 6 May 2026
    Fixed-Bottom, Manufacturing, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Haizea Wind Group has completed the manufacturing and assembly of 186 tower sections for 62 Siemens Gamesa wind turbines that will be installed at the Dieppe-Le Tréport offshore wind farm in France. The Spanish tower and foundation manufacturer produced the tower sections at its factory in Bilbao and has now shipped the last batch from […]

  • 15 June 2026
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The first wind turbine has been installed at the Dieppe-Le Tréport offshore wind farm, located 15 kilometres off the city of Le Tréport and 17 kilometres off the city of Dieppe in France. Ocean Winds, the project’s majority shareholder, said on 15 June that the wind farm, whose offshore substation was installed last year, would […]

  • 13 May 2026
    Business & Finance, Fixed-Bottom, Operations & Maintenance, Wind Farm Update

    Føn Energy Services has launched what it says will be its busiest offshore wind season to date, with inspection and repair campaigns underway across 14 offshore wind farms in the Netherlands, Scotland, Germany and Poland. The company has mobilised technicians, vessels, diving teams, remotely operated vehicle (ROV) spreads, and survey equipment to support above- and below-water […]

  • 1 July 2026
    Business & Finance, Fixed-Bottom, Operations & Maintenance, Supply Chain

    Føn Energy Services Poland has signed a long-term, multi-million-euro agreement with the joint venture between Orlen Group and Northland Power to provide integrated operations and maintenance (O&M) services for the 1.2 GW Baltic Power offshore wind farm in the Polish Baltic Sea. Under the agreement, Føn Energy Services will deliver a Balance of Plant (BoP) […]

  • 25 June 2026
    Authorities, Vessels

    NOTE: The article was updated on 31 July with information shared by Bunheur ASA, Fred. Olsen Windcarrier’s parent company. Fred. Olsen Windcarrier’s wind turbine installation vessel (WTIV) Brave Tern was out of operation for three weeks after the incident in the Port of Esbjerg on 10 June, which was caused by a lack of situational […]

  • 22 December 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The business alliance formed by Navantia Seanergies and Windar Renovables has completed the manufacturing of 45 monopiles for the East Anglia THREE offshore wind farm, developed by Iberdrola in the UK North Sea. The Navantia-Windar consortium is delivering 45 monopiles for the 1.4 GW East Anglia Three offshore wind farm under a contract with ScottishPower Renewables, […]

  • 4 December 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    All 21 monopile foundations at the Windanker offshore wind farm in the German Baltic Sea have been installed, according to a social media update posted by Iberdrola Deutschland. The work was carried out by Van Oord using the heavy-lift installation vessel Svanen, which installed the first monopile in September. According to Iberdrola, these are some […]

  • 5 December 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The HSI consortium, comprising HSM Offshore Energy, Smulders, and Iv, has sent off the Jasmund offshore substation (OSS), which will connect the Windanker offshore wind farm in the Baltic Sea to the German electricity grid. The 4,500-tonne OSS topside, measuring 48 metres in length, 33 metres in width, 17.5 metres in height, has sailed out […]

  • 9 January 2026
    Business & Finance, Foundations, Manufacturing, Supply Chain

    Navantia Seanergies and Windar Renovables have marked the production of the 200th jacket foundation for offshore wind at the Navantia Seanergies’ facilities in Spain, according to a social media update posted by Navantia on 9 January. The company did not name the project for which its 200th jacket was built. In July 2025, Navantia and […]

  • 18 November 2025
    Grid Connection, Offshore Platforms

    Both the topside and the jacket foundation of the 300 MW Jasmund offshore substation have been loaded out and are ready to set sail to the Baltic Sea for offshore installation. The topside, constructed at HSM Offshore Energy’s Stormpolder yard in the Netherlands, measures 48 metres long, 33 metres wide, and 17.5 metres high, and […]

  • 3 November 2025
    Business & Finance, Fixed-Bottom

    The European Investment Bank (EIB) has signed a EUR 500 million green loan with Iberdrola for the 315 MW Windanker offshore wind farm in Germany. The financing is guaranteed by the Spanish export credit agency, Cesce. This transaction with Iberdrola marks the inaugural use of a guarantee developed by the EIB and Cesce to support green […]

  • 31 October 2025
    Business & Finance, Collaboration, Outlook & Strategy

    Japan’s Kansai Electric Power (KEPCO) has signed a Share Subscription Agreement with Ireland-headquartered Simply Blue Group’s offshore wind development arm, Simply Blue Energy OSW (SBE OSW). This marks KEPCO’s first investment involving management participation in an offshore wind developer. SBE OSW is actively engaged in multiple offshore wind projects across Europe and elsewhere and possesses […]

  • 1 October 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    The first monopile has been installed at the Windanker offshore wind project site in the German Baltic Sea, marking the start of construction on Iberdrola’s third large-scale offshore wind project in the region, the company said via social media on 1 October. The monopiles are being installed by Van Oord using its heavy-lift installation vessel […]

  • 13 December 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Japan’s Kansai Electric Power Co., Inc. (Kansai) has signed a share purchase agreement with Iberdrola to participate in the 315 MW Windanker offshore wind farm in the German Baltic Sea. The operation values 100 per cent of the offshore wind farm at EUR 1.28 billion, which implies a multiple of EUR 4.1 million per MW […]

  • 17 July 2024
    Contracts & Tenders, Fixed-Bottom, Foundations, Manufacturing, Supply Chain

    The consortium of Navantia Seanergies and Windar Renovables has been awarded a contract to deliver 21 monopiles for Iberdrola’s Windanker offshore wind farm in Germany. The transition pieces (TPs) for the Windanker foundations will be delivered by Windar under a contract the Spanish manufacturer signed with Iberdrola in August last year. For the Navantia-Windar consortium, […]

  • 1 August 2024
    Fixed-Bottom, Operations & Maintenance, Project Updates, Wind Farm Update

    Rovco has completed a critical unexploded ordnance (UXO) clearance project for Iberdrola’s 315 MW Windanker offshore wind farm in the German Baltic Sea. The operation, which was Rovco’s first UXO project in Germany, was conducted using the company’s newly chartered multipurpose vessel MV Patriot, equipped with a spacious deck, active heave crane, DP Class 2 […]

  • 27 June 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Iberdrola has taken the final investment decision (FID) for its Windanker offshore wind farm in Germany, which has now advanced to the delivery phase. Windanker is the third offshore wind project for Iberdrola in the German Baltic Sea. The company already operates the 350 MW Wikinger and is developing the 467 MW Baltic Eagle project. […]