427 results found for 'formosa'

427 results found for 'formosa'
Order results by

A list of search results

  • 23 March 2026
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    The Formosa 2 consortium, consisting of Synera Renewable Energy (SRE) and JERA Nex BP, has reached financial close on what the project shareholders say is the first offshore wind refinancing in both Taiwan and the broader Asia-Pacific region. Supported by SMBC Group as the financial advisor, the consortium finalised a TWD 58.9 billion (approximately EUR […]

  • 29 January 2026
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The consortium between Semco Maritime and PTSC Mechanical & Construction has cut the first steel for the Formosa 4 offshore substation (OSS) at PTSC M&C’s fabrication yard in Vung Tau, Vietnam. Under a contract awarded in late August 2025, the consortium is responsible for the design, procurement, construction, and commissioning of the offshore substation’s jacket […]

  • 5 March 2026
    Contracts & Tenders, Equipment, Project Updates, Supply Chain, Wind Farm Update

    Palfinger has secured a contract to supply PF 200 fully electric offshore cranes for the Formosa 4 offshore wind farm in Taiwan. As part of the contract for Synera Renewables Taiwan (SRE), Palfinger will supply 35 units of PF 200 fully electric offshore cranes, each with a 7-meter outreach. They will be installed on jacket […]

  • 30 December 2025
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    The output of the 495 MW Formosa 4 offshore wind farm in Taiwan has been fully subscribed, according to its developer Synera Renewable Energy (SRE) Group, which signed three corporate power purchase agreements (CPPAs) this month. “With this milestone, the ready-to-build Formosa 4 now calls for support from the government and local financial institutions to […]

  • 9 October 2025
    Cables, Contracts & Tenders, Fixed-Bottom, Grid Connection, Project Updates, Supply Chain, Wind Farm Update

    Jan De Nul has signed a contract with Synera Renewable Energy (SRE) for the installation of subsea export cables on the Formosa 4 offshore wind farm. SRE has also selected the Belgian offshore construction contractor for export cables on its Formosa 6 offshore wind project. Under the contract for Formosa 4, Jan De Nul will […]

  • 29 September 2025
    Contracts & Tenders, Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Supply Chain, Wind Farm Update

    The consortium between Denmark’s Semco Maritime and Vietnam’s PTSC Mechanical & Construction (PTSC M&C) has secured an Engineering, Procurement, and Construction (EPC) contract with Synera Renewable Energy (SRE) for the offshore substation of the Formosa 4 offshore wind farm in Taiwan. Following extensive negotiation rounds, the consortium was awarded the EPC contract in late August […]

  • 25 September 2025
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    Synera Renewable Energy has signed a contract with CSBC-DEME Wind Engineering (CDWE) for the transportation and installation of 35 turbine foundations and the offshore substation, as well as scour protection works for the Formosa 4 offshore wind farm in Taiwan. Among the fleet to be deployed by CDWE to support the project’s grid connection target, […]

  • 16 September 2025
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Synera Renewable Energy (SRE) has partnered with Siemens Gamesa for the third time, selecting the company to supply 35 14 MW turbines for the Formosa 4 offshore wind farm in Taiwan. The turbines will be provided by Siemens Gamesa’s industrial nacelle factory in Taichung, Taiwan. The wind turbine foundations will be supplied by the local […]

  • 2 September 2025
    Cables, Contracts & Tenders, Project Updates, Supply Chain, Wind Farm Update

    Synera Renewable Energy (SRE) has awarded a contract to Seaway7, part of the Subsea7 Group, for the transport and installation of 35 inter-array cables at the Formosa 4 offshore wind farm in Taiwan, with offshore work expected to commence in 2028. Announcing the contract award, Subsea7 said this was a “substantial contract”, which the company […]

  • 25 August 2025
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Foundations, Supply Chain

    Synera Renewable Energy (SRE) has contracted Taiwan-based Century Group to supply wind turbine foundations for the 800 MW Formosa 6 offshore wind farm. Under the contract, Century Wind Power (CWP) will supply 57 jackets for Formosa 6, Taiwan’s single largest offshore wind farm by capacity. Additionally, Century Huaxin Wind Energy, newly appointed as a Tier […]

  • 22 August 2025
    Contracts & Tenders, Fixed-Bottom, Supply Chain, Vessels

    Cadeler has signed a firm contract with Synera Renewable Energy (SRE) for the transportation and installation of turbines at the 495 MW Formosa 4 offshore wind farm in Taiwan. The transportation and installation of 35 Siemens Gamesa 14 MW turbines will be executed by one of Cadeler’s next-generation M-class wind turbine installation vessels (WTIVs). The […]

  • 8 August 2025
    Business & Finance, Vessels

    Synera Renewable Energy (SRE) has awarded a 15-year contract to Dong Fang Offshore (DFO) to support the operations and maintenance (O&M) of SRE’s fleet of assets, starting with the Formosa 4 offshore wind project in Taiwan. Under the contract, which is the longest of its type in Taiwan’s offshore wind sector to date, DFO will […]

  • 9 March 2020
    Wind Farm Update

    JERA has reached an agreement with Macquarie’s Green Investment Group (GIG) and EnBW Energie Baden-Württemberg AG (EnBW) to join the development of the Formosa 3 offshore wind farm in Taiwan. JERA now holds 43.75% of the project, with GIG holding 31.25% and EnBW 25%, retaining material stakes and remaining committed to the ongoing development. The […]

  • 15 October 2020
    Business & Finance, Contracts & Tenders, Operations & Maintenance

    CWind Taiwan has been awarded a balance of plant (BOP) contract for the Formosa 1 offshore wind farm. The company is providing inspection and maintenance services to the 22 turbines at Formosa 1 Phase 1 and Formosa 1 Phase 2 sites, including internal and external inspections and painting. Under the contract, signed with Formosa 1 […]

  • 12 November 2019
    Wind Farm Update

    Ørsted and project partners have held an inauguration ceremony for the Formosa 1 Phase 2 offshore wind project in Taiwan. Formosa 1 Phase 2 is an extension of the existing two-turbine Formosa 1 Phase 1 project, which was officially commissioned in April 2017. The 120MW project comprises 20 Siemens Gamesa 6MW turbines installed approximately 2 […]

  • 7 January 2020
    Wind Farm Update

    The Formosa 1 offshore wind project in Taiwan started commercial operation on 27 December, according to JERA. The 128MW wind farm consists of the 8MW Formosa 1 Phase 1, inaugurated in May 2017, and the 120MW Formosa 1 Phase 2 which was officially commissioned in November. Formosa 1 comprises two Siemens Gamesa 4MW turbines from the first phase […]

  • 29 November 2019
    Business & Finance

    SeaPlanner, SeaRoc Group’s marine management system, has been selected to support the operations and maintenance phase of the Formosa 1 offshore wind farm in Taiwan. Under the 10-year contract, SeaPlanner will be deployed by the O&M team to coordinate all personnel and marine logistics for the 128MW wind farm. SeaPlanner also supported the construction of […]

  • 8 September 2023
    Wind Farm Update

    The Formosa 2 offshore wind farm has officially entered commercial operation, becoming the first Round 2 offshore wind project in Taiwan to achieve commercial operation date (COD). This project, owned by JERA, Green Investment Group (supported by its portfolio company Corio Generation) and Synera Renewable Energy (SRE), has entered the operations & maintenance (O&M) phase […]

  • 30 June 2022
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Japanese utility JERA and Corio Generation, the new specialist offshore wind business of Macquarie’s Green Investment Group (GIG), announced on 30 June that they were ready to bid for the third phase of Taiwan’s offshore wind zonal development with their Formosa 3 project. JERA and Corio (GIG at the time) have already partnered in Taiwan […]

  • 17 June 2019
    Contracts & Tenders

    Jan De Nul has secured the engineering, procurement, construction and installation contract (EPCI) for foundations and subsea cables at the Formosa 2 offshore wind project in Taiwan. Jan De Nul Group is responsible for the design, fabrication and installation of the jacket foundations, as well as for the design, supply and installation of subsea cables […]

  • 12 December 2018
    Authorities, Business & Finance, Wind Farm Update

    Swancor has signed a power purchase agreement (PPA) with Taipower for the Formosa 2 offshore wind farm.

  • 22 September 2020
    Business & Finance, Wind Farm Update

    Swancor Renewable Energy has revealed plans to develop the 4.4 GW Formosa 4 offshore wind project off the Miaoli County in Taiwan. The portfolio would consist of three sites, including Formosa 4-1, Formosa 4-2 and Formosa 4-3, which would cover a large maritime area located 18 to 20km offshore. Swancor Renewable Energy said it had […]

  • 29 October 2019
    Wind Farm Update

    Taiwan’s Formosa 2 offshore wind farm has reached financial close, Macquarie’s Green Investment Group (GIG) said. Formosa 2 has been jointly developed by Macquarie Capital (75%) and Swancor Renewable Energy (25%). GIG will now play a role in delivering the project through its construction phase. The 376MW offshore wind project located off the coast of Miaoli […]

  • 17 May 2018
    Contracts & Tenders, Wind Farm Update

    Jan De Nul has won a contract for the design, procurement and installation of the wind turbine foundations for the 120MW Formosa 1 Phase 2 wind farm offshore Taiwan.

  • 15 September 2014
    Business & Finance, Wind Farm Update

    K2 Management has announced its role as the general consultant to Formosa Wind Power Co. Ltd. in helping Formosa 1 Offshore Wind Farm.  Formosa 1 Offshore Wind Farm (128 MW) will be Taiwan’s first utility-size offshore wind farm planned for commissioning by 2018. K2 Management has performed wind modelling and wind data analysis and will now […]

  • 23 April 2020
    Operations & Maintenance, Vessels

    Siemens Gamesa has inaugurated the world’s first Service Accommodation Transfer Vessel (SATV) in Taiwan. The 35-metre Ventus Formosa will operate from Taichung. The vessel will support Siemens Gamesa’s full service agreement for the Formosa 1 offshore wind project. Penguin International built the SATV at its shipyard in Singapore and delivered it at the beginning of […]