Search results for: Hollandse Kust Zuid Alpha

4846 results

A list of search results

  • 28 November 2019
    Contracts & Tenders, Grid Connection

    Van Oord-Cablel Hellenic Cables consortium has awarded First Subsea with a contract to supply a cable protection system (CPS) for the Hollandse Kust (zuid) export cables, and a cross over protection for TenneT’s Net op zee Hollandse Kust (zuid). Under the contract, First Subsea will engineer, test, and supply a CPS for the protection of […]

  • 26 September 2018
    Contracts & Tenders, Grid Connection

    DNV GL has been contracted by Transmission System Operator TenneT to deliver the complete project certification for two offshore substations (OSS) for the Hollandse Kust Zuid offshore wind farms in the Dutch North Sea.

  • 7 July 2020
    Grid Connection

    The export cables for TenneT’s Hollandse Kust Zuid grid connection have been sent off from Greece to the Netherlands, according to the Dutch cable logistics company WIND, which handled the load-out. The company has been hired by Van Oord to provide subsea cable logistics for the grid connection project, for which Van Oord has been […]

  • 31 August 2020
    Contracts & Tenders, Grid Connection

    Mech-Tool Engineering (MTE) has won a contract from DryDocks World to provide fire and blast solutions for the Hollandse Kust Zuid Beta offshore substation. The contract award follows MTE completing a similar contract for the Hollandse Kust Zuid Alpha offshore platform. Under the contract, MTE designed, engineered, fabricated, and supplied its A0 fire-rated and Non-Rated […]

  • 24 December 2019

    DryDocks World has awarded Mech-Tool Engineering (MTE) with a contract to deliver fire and blast solutions to the Hollandse Kust Zuid Alpha project. MTE will design, engineer, fabricate, and supply its A0 fire-rated and Non-Rated (NR) external and internal profiled wall panels for the offshore platform. MTE has recently started the fabrication of the walls […]

  • 1 June 2020
    Grid Connection

    The project team working on the jacket foundation for the Hollandse Kust Zuid Alpha offshore substation has completed all the major lifts for the jacket, Petrofac said. The jacket is now getting ready to depart the United Arab Emirates and head to the Dutch North Sea. In September 2019, Eversendai Offshore cut the first steel […]

  • 28 May 2020
    Grid Connection

    Dubai-based Drydocks World has held a steel-cutting ceremony for the Hollandse Kust Zuid Beta offshore substation topside. This is the third topside that Drydocks World will be constructing for Petrofac and end-client TenneT, and the second project for the Hollandse Kust Zuid zone. The 700 MW High Voltage Alternating Current (HVAC) platform will, together with […]

  • 22 September 2015
    Contracts & Tenders, Grid Connection

    Transmission system operator (TSO) Tennet has developed a procurement strategy aiming to involve all future suppliers in connecting future Dutch offshore wind farms to the grid. Under the document, the companies will be able to qualify to take part in future tenders for five wind connection projects offshore Dutch coast. The strategy is based upon […]

  • 29 July 2019
    Grid Connection

    Drydocks World has signed a contract with Petrofac and end-client TenneT to construct the topside for the Alpha platform at the Hollandse Kust Zuid offshore wind farm zone. Drydocks will provide production engineering, construction, mechanical completion, pre-commissioning, commissioning assistance, load-out, sea fastening and HVAC (EPC) for the 700MW topside. This is the first time such a […]

  • 7 September 2020
    Grid Connection, Vessels, Wind Farm Update

    Heerema Marine Contractors’ semi-submersible crane vessel Sleipnir has installed the six-legged jacket foundation for TenneT’s Hollandse Kust Zuid Alpha offshore substation. Sleipnir transported the jacket to the installation site in the Dutch North Sea and lowered it into position over the weekend. Built by Eversendai Offshore, the jacket foundation will support the 700 MW topside […]

  • 17 September 2019
    Grid Connection

    Eversendai Offshore has cut the first steel for the jacket foundation destined for the Alpha platform at the Hollandse Kust Zuid offshore wind farm zone in the Netherlands. The wholly-owned subsidiary of Eversendai Corporation Berhad is in charge of the engineering and fabrication of the six-legged jacket at its fabrication yard in RAK Maritime City, Ras Al Khaimah in […]

  • 8 November 2016
    Grid Connection

    TenneT has signed framework agreements with Royal Smit Transformers and Siemens for the delivery of components for the Dutch offshore grid in the North Sea. Under the contracts, Royal Smit Transformers will supply reactive current compensation coils for the transformer station on land and Siemens will deliver reactive current compensation coils for the offshore transformer station as well […]

  • 9 December 2016
    Authorities, Contracts & Tenders, Wind Farm Update

    The Dutch government has designated two additional strips of sea area for offshore wind infrastructure to allow for the realisation of offshore wind projects at Hollandse Kust Zuid (1,400MW) and Hollandse Kust Noord (700MW). The aim of this move is to cut the offshore wind cost by enabling construction closer to the coast. Namely, the newly designated […]

  • 25 February 2020
    Grid Connection, Wind Farm Update

    Fugro has completed a marine unexploded ordnance (UXO) risk mitigation project for TenneT as part of the construction of the Hollandse Kust (zuid) offshore wind farm. The 13-month project involved surveying the cable route for explosive remnants of war (ERW), including munitions dumped at sea after conflict, and investigating potential targets. TenneT received their final […]

  • 15 January 2019
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Grid operator TenneT and wind farm developer Vattenfall have signed agreements for the offshore grid connection for the Hollandse Kust Zuid I and II wind farms in the Dutch North Sea. The agreements relate to the realisation of the connection and the transmission of electricity between Vattenfall’s wind farm and the TenneT Hollandse Kust Zuid Alpha offshore […]

  • 17 July 2020
    Grid Connection, Wind Farm Update

    The jacket foundation for the Hollandse Kust Zuid (HKZ) Alpha offshore platform has left the Eversendai Offshore shipyard in Ras al Khaimah, the United Arab Emirates. The Hua Xing Long vessel is transporting the jacket foundation to the Dutch North Sea and is expected to arrive at its destination mid-August, TenneT said. There, the jacket […]

  • 15 May 2019
    Contracts & Tenders, Grid Connection

    Heerema Marine Contractors has won a contract by Petrofac for the transport and installation of the Alpha platform at the Hollandse Kust Zuid offshore wind farm zone. Heerema will perform the installation by one of its newest vessels, the semi-submersible crane vessel Sleipnir. According to the company, during the tender preparations the feasibility of the […]

  • 28 August 2020
    Grid Connection

    The jacket foundation and pin piles for the Hollandse Kust Zuid (HKZ) Alpha platform have arrived from the United Arab Emirates to the Netherlands. According to Petrofac’s post on social media, the 3,200-tonne jacket is currently off the coast of Scheveningen, waiting for Heerema Marine Contractors’ semi-submersible crane vessel (SSCV) Sleipnir to place it at […]

  • 27 June 2019
    Grid Connection

    Petrofac and TenneT have confirmed the award of the contract to build the Hollandse Kust Zuid (HKZ) offshore grid connection Beta HVAC substation in the Dutch North Sea. This follows the award of the contract for HKZ platform Alpha in July 2018 and subsequent confirmation of HKZ platform Beta option. A total of eight 700MW […]

  • 9 June 2020
    Grid Connection, Wind Farm Update

    Eversendai Offshore cut the first steel for the Hollandse Kust Zuid (HKZ) Beta offshore substation platform on 28 May. The United Arab Emirates-based company, and a wholly-owned subsidiary of Malaysia’s Eversendai Corporation Berhad, is in charge of manufacturing athe jacket foundation and accompanying piles for the platform to be installed at the Hollandse Kust Zuid […]

  • 10 July 2018
    Contracts & Tenders, Grid Connection

    Petrofac has won a contract by TenneT for the offshore grid connection at the Hollandse Kust Zuid wind farm zone.

  • 8 February 2018
    Business & Finance, Contracts & Tenders, Grid Connection

    Dutch transmission system operator TenneT TSO has invited certifying authorities to submit their bids for the certification for the execution phase of the Alpha and the Beta offshore substation projects in the Hollandse Kust (zuid) zone, and the pre-contract award phase of the Hollandse Kust (noord) project.

  • 28 July 2020
    Grid Connection

    More than 8,000 tonnes of high voltage cables for the connection of the Hollandse Kust Zuid (HKZ) Alpha offshore platform to the onshore grid arrived at the Port Rotterdam on 19 July. The cables, which Hellenic Cables sent from Greece at the beginning of July, were transported by Acta Marine’s CC Atlantique barge, chartered by […]

  • 1 June 2020
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Petrofac has awarded the Dubai-based Eversendai Offshore with two substantial contracts for the offshore wind-related projects in the Netherlands and in Scotland, UK. Eversendai Offshore, a wholly-owned subsidiary of Malaysia’s Eversendai Corporation Berhad, will fabricate and construct a jacket foundation and the accompanying piles for the Hollandse Kust Zuid (HKZ) Beta substation platform to be […]

  • 12 May 2017
    Contracts & Tenders, Grid Connection, Wind Farm Update

    TenneT has launched a qualification process for candidates interested in tendering for the delivery of offshore platforms that will connect wind farms at Hollandse Kust Zuid and Hollandse Kust Noord offshore areas to the Dutch grid on the mainland.

  • 4 June 2019

    The Offshore WIND team brings you the ten most read offshore wind news in the month of May. Vietnamese Offshore Wind Farm Breaks Ground Vietnam’s Tra Vinh Wind Power has held a groundbreaking ceremony to mark the start of construction of the 48MW Korea- Tra Vinh wind farm (Phase 1). Offshore Construction Starts on Moray East The […]