VIDEO: Load Out of DolWin Alpha Converter Platform The load out of DolWin alpha marks the start of a journey that the platform will make to its final offshore destination, the DolWin area in German North Sea. This operation was performed at the Heerema’s Zwijndrecht fabrication yard at the Drechthaven. The following is a video […]
-
Grid Connection, Technology
DolWin beta high‐voltage direct current (HVDC) platform will arrive at the yard in Haugesund tonight, subject to weather conditions, Aibel announced at its social network page today. The massive DolWin beta structure is being transported to Haugesund in Norway, where the platform will be commissioned prior to deployment in the German North Sea. With a […]
-
DolWin Beta’s topside was placed onto the substructure yesterday. The jacking up of DolWin Beta’s topsides started on December 5. Drydocks World lifted the 10,000-tonne topside of the platform structure to a height of 52.8 metres from the dock bottom. On Saturday, the substructure was moved in position under the topside. Aibel is designing and […]
-
On Thursday 5 December, the jacking up of Dolwin Beta’s topsides started. The topsides weighs 10,000 tons. It will be jacked up more than 50 meters to be fitter on the substructure by six gigantic jacking towers Drydocks commenced the construction of the June last year. The platform will be ready for sailaway from Dubai […]
-
On Sunday, 13 December, two 475-ton electric transformers for the onshore substation of the DolWin3 project will embark on the last stage of their journey to the Dörpen West converter station in Heede, Germany. The transport of the transformers started in late November from GE’s transformer factory in Mönchengladbach. In 2013, TenneT awarded a contract for the […]
-
Offshore WIND’s photo of the day: Aibel employees doing their job on the DolWin beta converter station. “Small people, great effort,” says Aibel AS in a description of the photo that shows work on the DolWin beta offshore converter station outside the company’s yard in Haugesund, Norway. With a capacity of more than 900 MW, the converter station will host […]
-
ABB, the leading power and automation technology group, has won a significant order from the Dutch-German transmission grid operator TenneT to supply an AC (alternating current) power transmission link connecting Nordergründe, an offshore North Sea wind farm, to the mainland grid in Germany. The order was booked in the first quarter. The link has a […]
-
Business & Finance, Contracts & Tenders, Grid Connection
London-based consultancy AqualisBraemar LOC has secured a contract to provide marine warranty services for the export cable installation of the DolWin5 offshore grid connection project in Germany. The scope of work covers all marine transportation and installation operations relating to the laying of export cables, as well as the suitability surveys of all construction and support […]
-
Nordic Yards held a dock laying ceremony of a steel element of the offshore converter platform DolWin gamma in Warnemünde on 30 January. The placing of a 200-tonne section marked another milestone in the production of the 900 MW HVDC platform. “With today´s dock-laying, we are happy to have completed one further important step in the construction […]
-
Contracts & Tenders, Grid Connection, Operations & Maintenance
A consortium of SeaRenergy and N-Sea has won a contract by TenneT for modification works to the jacket foundation of the HVDC platform DolWin alpha.
-
Transmission System Operator TenneT has awarded the DolWin3 offshore project in North Sea to Alstom. Windreich AG marks this contract for DolWin3, with a total investment of more than one billion euros, as another important component for the success of the energy transition. TenneT, together with the Windreich AG, is the most active investor in […]
-
Grid Connection, Technology
DolWin3 is the eighth grid connection project to be implemented by TenneT using direct current technology. Together with three projects based on AC current technology, TenneT TSO, which is responsible for the North Sea, will then deliver a total of around 6.2 GW of offshore wind energy to the mainland. Alstom has just been awarded […]
-
Grid Connection, Technology
Representatives of TenneT, Mitsubishi, ABB, Aibel and Dubai Dry Docks were present at a ceremony organized on the occasion of DolWin beta’s departure from Drydocks World. “DolWin beta is the first wind platform we have designed and built. Now that the giant is leaving its construction site, it is a milestone for Aibel,” says CEO Jan […]
-
Two almost identical jacket structures for DolWin gamma offshore converter platform are on their way to be installed in the North Sea. The structures will be positioned at sea with a spacer frame, accurately fitting them into the right place. Nine piles per jacket will anchor the support structure to the seabed, which had to be prepared prior to the […]
-
Recently, Norddeutsche Seekabelwerke GmbH (NSW) was awarded an order by TenneT TSO GmbH (TenneT), a German-based transmission network operator, to supply and install 2 x 8.5 kilometers of 155 kV AC submarine transmission cable system. The cable will provide the connection of the transformer platform of the future offshore wind park Gode Wind I to […]
-
Contracts & Tenders, Grid Connection, Wind Farm Update
Tekmar Energy has secured a contract by cable manufacturer ZTT to supply its cable protection system (CPS) for the Gode Wind 3 high-voltage grid connection in Germany. The 16 km long submarine cable is scheduled for installation in 2023 and will connect the 242 MW Gode Wind 3 offshore wind farm to TenneT’s extra-high-voltage grid […]
-
PFISTERER, an energy transmission and distribution specialist, has started the onshore work for equipping the DolWin gamma converter station. The 900MW DolWin gamma converter platform is currently being constructed as the third link within the DolWin wind farm cluster. PFISTERER is in charge of laying all high-voltage and medium-voltage cables, both within the platform and over the […]
-
Grid Connection, Technology
ABB has won a EUR 10.6 million order for ABB Ability™ digital products and services at TenneT’ DolWin5 (Epsilon) grid connection in the German North Sea. Under the order, ABB will provide a system for IT infrastructure, OT1 security, plant-wide condition monitoring, SCADA2, and remote access services to facilitate stable power transmission to the German […]
-
Grid Connection, Wind Farm Update
The on-schedule connection with the grid for the offshore wind park ‘Deutsche Bucht’ is now a good deal closer. At the hearing with the Federal Network Agency yesterday, it became clear in intensive negotiations over several hours that both sides – the wind park builder Windreich AG and the network operator TenneT – have a […]
-
The DolWin beta converter platform left Aibel’s yard in Haugesund, Norway on the night of August 1. Following a four-day transport stage, the platform will be installed in the DolWin wind cluster in the German North Sea. The platform concept is based on experience from the oil and gas sector, and has been developed and […]
-
VIDEO: DolWin Alpha Installation The DolWin alpha converter platform has been installed in the North Sea. Siemens Successfully Installs HelWin1 Platform (Germany) Siemens has installed the HelWin1 offshore platform in the North Sea, marking the successful completion of a significant stage in German grid connection projects. UK: Samsung’s 7MW Offshore Wind Turbine Reaches NAREC’s […]
-
Business & Finance, Grid Connection, Vessels
TenneT is on the market for a contractor for the provision of maritime consulting and support services for offshore installation projects in North Sea and Wadden Sea. The contract covers supervision of marine construction projects, primarily submarine cable laying, and provision of a vessel. Additionally, the contractor will be in charge of supervising the construction […]
-
Inocean AS has acquired all of the outstanding shares in ABB Inocean AB and has renamed the company Inocean AB.
-
Inocean, a leading Norwegian naval architect company, has signed an agreement with ABB, to set up an engineering services joint venture specializing in offshore wind integration projects. ABB will have a majority shareholding in the new entity, ABB Inocean AB which will be located in Gothenburg, Sweden, a region with a shipbuilding history and recognized […]
-
Grid Connection, Operations & Maintenance
During the test phase of the DolWin2 offshore grid connection, a cable component had failed repeatedly and TenneT decided to power off the system and has asked ABB to address the issue. The companies will now investigate whether an individual case or a systemic material error is in question, and then ABB will remove the cause of […]
-
Grid Connection, Wind Farm Update
Trianel has produced first power from its 200MW Borkum West offshore wind farm located in the North Sea. The first turbine was commissioned on Sunday and is now undergoing trial operation. “After the permanent power connection was successfully established by the substation DolWin Alpha in December, the first plant is now in trial operation,” said […]