308 results found for 'dolwin6'

308 results found for 'dolwin6'
Order results by

A list of search results

  • 15 December 2025
    Cables, Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    Jan De Nul has installed three HVAC subsea cables, delivered by Hellenic Cables, between TenneT’s offshore converter station DolWin kappa and Nordseecluster 1 and 2 sites in the German North Sea. The two locations make up the 660 MW Nordseecluster A offshore wind farm, which itself is part of a bigger, two-phased Nordseecluster project. With […]

  • 23 January 2026
    Business & Finance, Grid Connection, Offshore Platforms

    Seatrium’s wholly owned subsidiary, Seatrium New Energy, and its consortium partner Aibel have filed for arbitration proceedings in connection with DolWin epsilon, the offshore converter platform of TenneT’s DolWin5 grid connection. The arbitration was initiated under the consortium agreement and filed with the Arbitration Institute of the Stockholm Chamber of Commerce, Seatrium said on 22 […]

  • 17 October 2025
    Grid Connection, Offshore Platforms

    The Dutch/German transmission system operator (TSO) TenneT Germany has commenced the commissioning of the 900 MW DolWin5 offshore grid connection system. Following the completion of the installation campaign in the summer, the consortium of Aibel and Seatrium, together with Hitachi Energy and TenneT, started commissioning as planned in the autumn, said the TSO. In addition […]

  • 4 December 2025
    Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    The Borkum Riffgrund 3 offshore wind farm fed its first power into the German grid on 3 December, according to Ørsted, which owns the project together with Nuveen Infrastructure. Once fully commissioned, which is expected in the first quarter of 2026, the 913 MW offshore wind farm will become the largest in Ørsted’s German portfolio. […]

  • 17 November 2025
    Business & Finance

    Germany has earmarked a budget ceiling of EUR 7.6 billion for the possible purchase of a minority stake in the German arm of transmission system operator (TSO) TenneT, subject to parliamentary approval. Reuters reported on 12 November 2025 that Germany intends to spend over multiple years to acquire a stake in the unit, starting with […]

  • 23 July 2025
    Cables, Grid Connection, Offshore Platforms

    The laying of the subsea cable that connects the DolWin epsilon platform to land has been completed. The platform and the cables, part of TenneT’s DolWin5 grid connection, will transmit the electricity generated by Ørsted’s Borkum Riffgrund 3 offshore wind farm to the German grid on land. The DolWin epsilon platform was installed this June. […]

  • 6 January 2026
    Business development, Fixed-Bottom, Grid Connection, Innovation, Offshore Platforms, Technology

    ABS has issued an Approval in Principle (AIP) to Seatrium for the company’s offshore substation (OSS) design, described as a next-generation offshore HVAC platform engineered for scalability. Seatrium has built several offshore converter platforms for offshore wind farms and grid connections over the years, including the now-operational DolWin epsilon in Germany and the OSS for […]

  • 8 September 2025
    Business & Finance, Grid Connection

    RWE and the global asset manager and infrastructure investor, Apollo Global Management, have signed an agreement under which Apollo will pay EUR 3.2 billion to RWE in exchange for an equity stake in a to-be-established joint venture (JV), which will hold RWE’s existing 25.1 per cent stake in the German transmission system operator (TSO) Amprion. […]

  • 25 July 2025
    Authorities, Business & Finance, Grid Connection

    TenneT Holding is exploring two options to meet TenneT Germany’s equity requirements: a private placement of shares and an initial public offering (IPO), and expects to decide on which option to proceed with in September. The German government has not yet excluded the possibility of buying into the German transmission system operator (TSO). On 15 […]

  • 10 June 2025
    Grid Connection, Offshore Platforms

    The DolWin epsilon converter platform, part of the DolWin5 offshore grid connection, has been installed in the German North Sea. After three years of construction at Seatrium’s shipyard in Singapore, the 82-metre-long platform has covered approximately 13,000 nautical miles to Norway in 60 days. There, Aibel and Hitachi Energy installed the final technical equipment, including […]

  • 29 May 2025
    Grid Connection, Offshore Platforms

    The 900 MW DolWin epsilon platform is getting ready to sail into the German North Sea, the transmission system operator (TSO) TenneT announced on 28 May. After three years of construction at Seatrium’s shipyard in Singapore, the 82-metre-long platform has covered approximately 13,000 nautical miles to Norway in 60 days. There, the structure received its […]

  • 16 June 2025
    Grid Connection, Offshore Platforms

    The first steel has been cut for the BalWin1 and BalWin2 grid connection systems that will be installed in the German North Sea. Last week, Meyer Werft, together with the German transmission system operator (TSO) Amprion, Dragados Offshore, and Siemens Energy, celebrated the start of production of the converter platforms for the BalWin1 and BalWin2 […]

  • 4 March 2021
    Contracts & Tenders, Grid Connection

    MENCK, part of Acteon, has signed a contract with Allseas to deliver pile-driving and handling equipment for the installation of TenneT’s DolWin kappa offshore converter platform, the centerpiece of the DolWin6 offshore grid project in the German North Sea. A submersible MHU 3500S hydraulic hammer, capable of driving monopiles and smaller sized piles, will be […]

  • 17 January 2020
    Grid Connection

    Spanish steel fabricator Tecade has shipped off the final leg extensions manufactured for the DolWin6 offshore platform. The leg extensions were delivered to Dragados Offshore in Puerto Real where they will be integrated into the substation for further shipment to the German North Sea, Tecade said. Tecade’s scope of work includes the manufacture and delivery […]

  • 8 August 2022
    Business & Finance, Grid Connection, Vessels, Wind Farm Update

    The DolWin kappa offshore platform, part of the DolWin6 grid connection project, has sailed out from the Dragados shipyard in Cádiz, Spain, and is en route to the Port of Rotterdam in the Netherlands. After three years of construction, the platform was loaded on the transport barge Iron Lady on 5 August and headed to […]

  • 29 June 2021
    Grid Connection

    Offshore cable-laying work to link the DolWin6 grid connection in the North Sea to the German grid has started, TenneT said. The cable-laying work follows an unexploded ordnance removal campaign where a total of twelve UXOs identified along the sea cable route were removed in May 2021. The 39-kilometre export cable section is expected to […]

  • 17 July 2019
    Grid Connection

    Transmission system operator TenneT has cut the first steel for the DolWin kappa offshore converter platform, the centerpiece of the 900MW DolWin6 HVDC connection. Spain’s Dragados Offshore is responsible for the design, supply, construction, transportation and installation of the DolWin kappa platform and the accompanying jacket foundation. Siemens will supply the entire technology for the […]

  • 24 October 2019
    Grid Connection

    Transmission system operator TenneT has started construction work in Emden, Germany at the site of the onshore converter station which will be part of the DolWin6 grid connection. The foundation work for the converter station in Emden will continue over the next six months with one thousand piles up to 24 metres long being drilled into the […]

  • 28 March 2022
    Contracts & Tenders, Grid Connection

    VCE Vienna Consulting Engineers ZT has been awarded a contract to install Structural Health Monitoring (SHM) systems on twelve TenneT’s HVDC platforms in Germany. On nine platforms, which are in operation, the installation of the SHM systems will be carried out offshore during operation, while for the three platforms which are under construction or in […]

  • 21 September 2021
    Contracts & Tenders, Grid Connection

    TenneT has issued a call for tenders for Structural Health Monitoring systems (SHM systems) and their installation on twelve offshore HVDC platforms, including both existing and platforms yet to be installed offshore. Under a five-year, EUR 3.25 million contract, the tender winner will develop and install a monitoring concept for the support structures of the […]

  • 22 August 2022
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Allseas’ installation vessel Pioneering Spirit has installed the foundation structure for the DolWin kappa offshore platform in the German North Sea, according to TenneT’s latest social media post. After three years of construction, the platform sailed out from the Dragados shipyard in Spain on 5 August and was en route to the Port of Rotterdam […]

  • 31 May 2019
    Contracts & Tenders, Grid Connection

    Gaditana de Chorro y Limpieza has won a contract to carry out coating works on the DolWin6 grid connection in the German North Sea. The Spanish company is in charge of the surface preparation and coating application of the offshore substation, jacket foundation, bridge connection, and offshore hook-ups and touch-ups after transport and installation. The […]

  • 16 October 2023

    The 900 MW DolWin Epsilon offshore converter platform has left Seatrium’s shipyard in Singapore and is heading towards Aibel’s yard in Haugesund, Norway, where it is expected to arrive in the second half of December. After three years of construction and with more than ten million manhours, the heavy transport vessel Mighty Servant 1 has […]

  • 26 October 2022
    Contracts & Tenders, Grid Connection

    SeaRenergy has been awarded a contract by Siemens Energy to provide integrated onshore and offshore logistics services during the commissioning of DolWin6 converter platform in the German Bight. The contract consists of various packages. Besides marine coordination and management of all personnel transfers, SeaRenergy is responsible for the onshore logistics and warehousing in Emden using […]

  • 13 July 2021
    Grid Connection, Vessels

    DEME has completed the laying of the HVDC cable for the DolWin6 offshore grid connection in the German sector of the North Sea, using its LNG-powered, DP3 vessel Living Stone. According to the company, this was the first time a cable laying vessel installed cables while running on LNG. The 900 MW transmission link DolWin6, […]

  • 4 November 2020
    Contracts & Tenders, Grid Connection

    TenneT has invited tenders for services related to cable repair and maintenance in both Germany and the Netherlands, which include locating cable faults. The services will be delivered across several grid connections and interconnectors. The transmission system operator (TSO) is looking to conclude a contract for a service-level agreement with a provider of cable fault […]