314 results found for 'GE Haliade-X '

314 results found for 'GE Haliade-X '
Order results by

A list of search results

  • 10 April 2023
    Business & Finance, Grid Connection, Wind Farm Update

    Prysmian’s cable-laying barge Ulisse has resumed cable-laying operations at the first U.S. large-scale offshore wind project, located off the coast of Massachusetts. According to the project’s latest mariner update, cable laying operations of the mid-section cable for the Vineyard Wind 1 project were set to kick off on or about 9 April and continue through […]

  • 17 April 2020
    Vessels

    Swire Blue Ocean (SBO) has commenced the installation of the new crane boom onboard its jack-up vessel Pacific Osprey. The 422-tonne boom was lifted onto the vessel in the Port of Esbjerg, Denmark, yesterday morning with the help of two shore cranes and locked to the base of the crane, SBO said. According to the […]

  • 7 April 2021
    Contracts & Tenders, Wind Farm Update

    Spanish manufacturer of rolled rings euskalforging has won a contract to deliver flanges for the 1.2 GW Dogger Bank A offshore wind farm. Under the contract, euskalforging will roll, heat treat, machine, and deliver flanges for all the 95 monopile foundations and transition pieces of the Dogger Bank A. According to the company, this will […]

  • 21 December 2022
    Contracts & Tenders, Wind Farm Update

    Spain-based manufacturer of rolled rings euskalforging has won a contract to produce flanges for the 1.2 GW Dogger Bank C offshore wind farm. Under the contract, the company will ring roll 87 rings for transition pieces and 87 rings for monopiles with an outside diameter larger than 8 metres. Dogger Bank Wind Farm is being built […]

  • 14 March 2022
    Vessels

    Jan De Nul’s next-generation jack-up installation vessel, the Voltaire, has been fitted with the main crane of more than 3,000 tonnes – the largest Leg Encircling Crane ever built. Featuring a crane house weighing 1,800 tonnes, a boom length of 140 metres, and weighing 800 tonnes, the Huisman crane will use a Universal Quick Connector […]

  • 26 August 2021
    Vessels, Wind Farm Update

    DEME Offshore’s DP2 jack-up installation vessel Sea Installer will undergo a crane replacement to increase the vessel’s lifting capacity from the current 900 tonnes to 1,600 tonnes. Being built by Huisman, the new crane will enable Sea Installer to handle the next generation of offshore wind turbines, DEME said. The upgraded Sea Installer will be […]

  • 29 March 2023
    Vessels

    Jan De Nul’s new jack-up vessel, Voltaire, has left Ras Al Khaimah in the United Arab Emirates (UAE), where it underwent further commissioning and project-specific adjustments ahead of its first assignment, and is now on its way to Europe. The vessel’s first deployment will be on the 3.6 GW Dogger Bank Wind Farm project offshore the UK, the world’s […]

  • 28 March 2022
    Contracts & Tenders

    Van Oord has won a contract to transport and install wind turbines at an undisclosed wind farm offshore the East Coast of the USA. The company will deploy the offshore installation vessel Aeolus on the project. The turbine installation work is scheduled to start in 2023. Van Oord said that this is the first contract […]

  • 30 March 2021
    Authorities, Business & Finance, Wind Farm Update

    The U.S. Bureau of Ocean Energy Management (BOEM) has released the Notice of Intent (NOI) to launch the formal environmental review for Ørsted’s Ocean Wind project offshore New Jersey. The NOI announces the preparation of the Environmental Impact Statement (EIS) for the Construction and Operations Plan (COP) submitted by Ocean Wind LLC. This opens a […]

  • 7 December 2022
    Grid Connection, Vessels, Wind Farm Update

    Vineyard Wind 1, America’s first large-scale offshore wind project, is moving forward with submarine cables being delivered by Prysmian Group. Prysmian’s cable laying vessels, Cable Enterprise and Ulisse, arrived in the US with submarine cables manufactured and tested at the company’s centres of technological excellence in Pikkala, Finland, and Arco Felice, Italy. In November, Cable […]

  • 2 June 2022
    Contracts & Tenders, Wind Farm Update

    Norway-based DeepOcean has been awarded a contract to provide subsea services to Vineyard Wind 1, the first utility-scale offshore wind project in the US. Under the contract, DeepOcean will provide a range of subsea services including project management, engineering, ROV, tooling, and survey activities. The company will lead the project out of its office in […]

  • 21 February 2020
    Ports & Logistics, Vessels

    SAL’s M/V Wiebke has transported the new crane boom of Swire Blue Ocean’s jack-up Pacific Osprey from China to the Port of Esbjerg in Denmark. The crane boom was loaded onto M/V Wiebke at NOV’s manufacturing yard in China on 21 January and the vessel left the yard a day later. The crane boom will […]

  • 30 October 2019
    Grid Connection, Wind Farm Update

    ABB has secured a contract to supply its high-voltage direct current (HVDC) Light® converter systems to connect the Dogger Bank offshore wind project to the UK transmission network. In the first-ever use of the HVDC technology in the UK’s offshore wind market, ABB will supply technology with one of the smallest environmental footprints, due to the […]

  • 14 October 2020
    Business & Finance

    The Netherlands-based Tetrahedron has developed a new crane for next-generation offshore wind turbines, said to be designed to fit on both existing and new jack-up vessels. Tetrahedron said that based on a different motion principle and a structural load transfer, the crane lifts higher than alternatives that can fit in the same footprint. According to […]

  • 1 October 2020
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Hellenic Cables has secured a contract with DEME Offshore to supply the inter-array cables and accessories for the Dogger Bank offshore wind farm in the UK. Hellenic Cables will design, manufacture, test and supply approximately 650 km of 66 kV XLPE-insulated inter-array cables and associated accessories for the project’s A & B phases. The contract […]

  • 13 September 2021
    Business & Finance

    GE Renewable Energy has received the official planning approval from local authorities for its manufacturing plant in Teesside, UK, where LM Wind Power will operate the facility which will be dedicated to the production of its 107-metre-long blades for GE’s Haliade-X offshore wind turbines. The construction of the blade manufacturing plant is planned to begin […]

  • 1 January 2020

    With 2019 now behind us, our editorial team looks back on what shaped the offshore wind industry in the last year of the decade. Below is a subjective list highlighting some of the most impactful events in the sector: UK Offshore Wind Strike Prices Slide Down to GBP 39.65/MWh Offshore wind projects selected in the […]

  • 3 July 2023
    Wind Farm Update

    The first monopile foundation has been completed at EEW American Offshore Structures‘ (EEW AOS) facility in Paulsboro, New Jersey, for the 1.1 GW Ocean Wind 1 offshore wind project. Ocean Wind 1 is the offshore wind project selected by the New Jersey Board of Public Utilities (NJBPU) through a solicitation held in 2019. The offshore wind farm […]

  • 29 October 2020
    Business & Finance

    Mitsubishi Heavy Industries (MHI) and Vestas Wind Systems have appointed Johnny Thomsen as the new CEO of MHI Vestas Offshore Wind. Thomsen is taking over from Philippe Kavafyan who has left the company after holding the CEO position for two and a half years. As of Thursday, 29 October, the executive management of MHI Vestas […]

  • 13 July 2020
    Grid Connection, Wind Farm Update

    Offshore wind developer Ørsted has decided against constructing the interconnection facility for the Skipjack wind farm at Fenwick Island State Park in Sussex County, Delaware, US. In July 2019, Ørsted entered into a non-binding memorandum of understanding with the Delaware Department of Natural Resources and Environmental Control (DNREC) to construct the interconnection facility on a […]

  • 23 April 2020
    Authorities, Wind Farm Update

    Ørsted is postponing the Skipjack Wind Farm project offshore Maryland, US by a year due to delays in the permitting procedure. The delays will push the project’s anticipated completion date from late 2022 to the end of 2023, the world’s leading offshore wind developer said. “As the federal permitting timeline evolves, Ørsted is now receiving […]

  • 28 September 2023
    Contracts & Tenders, Operations & Maintenance, Supply Chain

    Certex UK has secured a major framework to supply statutory inspection and maintenance services on the 3.6 GW Dogger Bank offshore wind farm in the UK. Under the 5-year framework contract, Certex UK’s Great Yarmouth-based Engineering Services division will be responsible for the inspection and maintenance of cranes, personnel lifts, general lifting, and safety equipment […]

  • 2 June 2023
    Business & Finance, Wind Farm Update

    Public Service Enterprise Group Inc. (PSEG) has completed the sale of its 25 per cent equity interest in 1.1 GW Ocean Wind 1 offshore wind project to Ørsted North America. With this executed agreement, Ørsted North America has reimbursed PSEG for all of its cumulative outlays in the Ocean Wind 1 project and Ørsted North […]

  • 16 September 2021
    Business & Finance, Wind Farm Update

    Vineyard Wind, a joint venture between Avangrid Renewables and Copenhagen Infrastructure Partners (CIP), has reached financial close on its 800 MW offshore wind farm in Massachusetts — the first large-scale offshore wind farm in the United States and the Americas region. The developer has raised USD 2.3 billion of senior debt through nine international and […]

  • 23 December 2020
    Authorities, Ports & Logistics

    The State of New Jersey is investing USD 250 million in a monopiles manufacturing facility that will serve the U.S. offshore wind industry. The facility will be located at the Paulsboro Marine Terminal in Gloucester County and is said to be the largest industrial offshore wind investment in the U.S. to date. EEW, Ørsted, as […]

  • 27 February 2020

    SSE Renewables and Equinor, the developers of the 3.6GW Dogger Bank Wind Farm, have changed the names of the project’s phases to recognise their link to the historic Doggerland area where the wind farm will be built. The location used to be home to a Mesolithic community who lived across the Doggerland area around 12,000 […]