313 results found for 'GE Haliade-X '

313 results found for 'GE Haliade-X '
Order results by

A list of search results

  • 29 April 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    More than half of the wind turbines at Dogger Bank A, the first phase of the UK’s 3.6 GW Dogger Bank Wind Farm, have been installed. So far, 52 of the 95 GE Haliade-X 13 MW wind turbines that Dogger Bank A will feature are in place, according to a Notice to Mariners from the […]

  • 4 February 2025
    Business & Finance, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    Mitsubishi Corporation is reevaluating its offshore wind projects in Japan, planned to be built in the waters off the coasts of Akita Prefecture and Chiba Prefecture. The Japanese energy company said on 3 February it put the business plans for the projects under review “due to material changes in the macroeconomic environment.“ Mitsubishi Corporation, through […]

  • 4 March 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    On 27 February, a turbine at the Vineyard Wind offshore wind project was struck by lightning. The GE Vernova Haliade-X 13 MW turbine had previously experienced a blade failure in July 2024. In July 2024, a blade from one of the GE Vernova’s Haliade-X turbines detached, which resulted in debris washing up on beaches on […]

  • 3 January 2025
    Fixed-Bottom, Foundations, Project Updates, Vessels, Wind Farm Update

    The offshore installation vessel Seaway Strashnov has installed all but two monopile foundations at the Dogger Bank B offshore wind site in the UK and will return in the second quarter of 2025 to complete the installation. Five more transition pieces (TPs) are also left to be installed, according to the latest notices to mariners […]

  • 21 January 2025
    Authorities, Fixed-Bottom, Planning & Permitting

    The US Bureau of Ocean Energy Management (BOEM) and the Bureau of Safety and Environmental Enforcement (BSEE) have completed the review and approved the revised Construction and Operations Plan (COP) for the Vineyard Wind 1 offshore wind farm. Last week, the federal government lifted the suspension on Vineyard Wind’s installation of the remaining GE Vernova […]

  • 20 May 2025
    Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    All foundations, including the transition pieces (TPs), are now in place at Dogger Bank B, the second phase of the world’s largest offshore wind farm under construction, as the heavy-lift vessel (HLV) Seaway Alfa Lift recently installed the final TP. The vessel started installing the final five TPs earlier this month, after Seaway Strashnov installed the […]

  • 31 March 2025
    Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    The offshore installation vessel Seaway Strashnov will install the remaining two monopiles at the Dogger Bank B offshore wind farm site next month. According to a Notice to Mariners from the project, the work is planned to commence on 7 April and continue until approximately 30 April. The heavy lift vessel, owned by Seaway7, completed […]

  • 1 January 2025
    Business development, Equipment, Fixed-Bottom, Floating Wind, Operations & Maintenance, Project Updates, Supply Chain, Technology, Vessels, Wind Farm Update, Wind Turbines

    New wind turbine models, vessels and equipment, and project updates were the most read topics on offshoreWIND.biz in 2024. In this overview, we are bringing the ten most popular news in 2024. In January 2024, Siemens Gamesa received a EUR 30 million grant from the EU for a project called Highly Innovative Prototype of the […]

  • 3 June 2025
    Business & Finance, Project Updates, Wind Farm Update

    The French government and three offshore wind farms have signed amendments to their power purchase agreements (PPAs), allowing them to halt production during periods of negative electricity prices. The three wind farms that signed PPAs are the 500 MW Fécamp, the 480 MW Saint-Nazaire, and the 496 MW Saint-Brieuc. According to the Ministry of Economics, […]

  • 1 January 2025
    Business development, Industry, Supply Chain, Technology, Wind Turbines

    In offshoreWIND.biz‘s 2023 annual wind turbine overview from January 2024, you could have read about the first 16 MW model installed offshore and a 22 MW turbine about to enter development. Fast forward twelve months, a 21 MW prototype in Europe and 22 MW and 26 prototypes in China are expected to soon be installed […]

  • 12 December 2024
    Business & Finance, Contracts & Tenders, Supply Chain, Wind Turbines

    Dogger Bank Wind Farm, a joint venture between SSE Renewables, Equinor, and Vårgrønn, has signed a vessel reservation agreement with Seaway7 to charter a second turbine installation vessel to support the ongoing delivery of the offshore wind farm off the coast of England. Starting in 2026, the Seaway Ventus jack-up installation vessel is planned to […]

  • 17 December 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    Seaway7, part of the Subsea7 Group, has been awarded a contract by Inch Cape Offshore Limited (ICOL), a joint venture between ESB and Red Rock Renewables, for the transport and installation of pin-pile jacket foundations and transition pieces (TPs) for the 1.1 GW offshore wind project. The deal is worth between USD 150 million and […]

  • 16 December 2024
    Fixed-Bottom, Floating Wind, Planning & Permitting, Project Updates

    EDF Renewables has applied for environmental investigations for five offshore wind projects in Brazil, totalling over 10 GW in potential installed capacity. The developer also plans another 2 GW project in the country in partnership with the Brazilian company Internacional Energias Renováveis. According to documents from Brazil’s Institute for the Environment and Natural Resources (IBAMA), […]

  • 3 October 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    SSE has revealed that the completion of Dogger Bank A, the first of the three phases of the UK’s Dogger Bank Wind Farm, is projected for the second half of 2025, which is later than the previously expected first half of the year. In its interim earnings report released on 3 October, SSE said that […]

  • 28 October 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The DP3 installation vessel Orion, owned and operated by the Belgian offshore construction specialist DEME, is scheduled to begin installing the remaining monopile foundations at the Vineyard Wind 1 site in the US on or around 28 October, as disclosed in the project’s recent offshore wind mariner update. Prior to installation, the POLARIS and HOS RUGER […]

  • 24 October 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Following a July blade failure incident, GE Vernova plans to remove some blades and strengthen others at the Vineyard Wind 1 offshore wind farm in the US. The companies are implementing the incident and response action plan, which was announced in August. The plan outlined steps to safely remove the remainder of the damaged blade […]

  • 2 October 2024
    Business & Finance, Supply Chain, Wind Turbines

    Some 900 jobs in GE Vernova’s offshore wind business unit could be lost as the company plans to downsize the business. “On September 19, we submitted a proposal to the GE Vernova European Works Council related to proposed changes in our Offshore Wind business globally. The proposal reflects industry wide challenges for wind and aims […]

  • 23 August 2024
    Fixed-Bottom, Manufacturing, Supply Chain, Wind Farm Update, Wind Turbines

    This article was updated at 15:05 CET on 23 August 2024 with a statement from GE Vernova. One of the already installed wind turbine blades at Dogger Bank A offshore wind farm, currently under construction in the UK, has sustained damage and failed. The blade failure occurred on the morning of 22 August and, according […]

  • 26 July 2024
    Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    More than a quarter of wind turbines at Dogger Bank A, the first phase of the UK’s 3.6 GW Dogger Bank Wind Farm, have been installed. So far, 27 of the 95 GE Haliade-X 13 MW wind turbines that Dogger Bank A will comprise are in place, according to information in Equinor’s results for the […]

  • 14 August 2024
    Authorities, Fixed-Bottom, Project Updates, Wind Farm Update

    The US Bureau of Safety and Environmental Enforcement (BSEE) has allowed Vineyard Wind to resume certain limited additional activities at the Vineyard Wind 1 offshore wind farm site. These include the installation of towers and nacelles but not (yet) the installation of the wind turbine blades. BSEE issued an update to the Suspension Order the […]

  • 26 April 2019
    Business & Finance

    GE Renewable Energy is holding a series of supply chain engagement events in the UK for its Haliade-X 12MW offshore wind turbine. The events are part of GE’s supply chain plan for the world’s most powerful offshore wind turbine and will welcome potential suppliers that have suitable products or services that could support its production. GE […]

  • 13 November 2019
    Technology

    GE Renewable Energy has signed a cooperation agreement with State Power Investment Corp (SPIC) to bring the Haliade-X 12MW offshore wind turbine to China. GE announced in March last year that it will invest more than USD 400 million to develop and deploy Haliade-X 12MW, the world’s most powerful offshore wind turbine. The first unit was installed […]

  • 6 November 2019
    R&D, Technology

    The blade for GE’s Haliade-X 12MW offshore wind turbine has arrived at MassCEC’s Wind Technology Testing Center (WTTC) in Boston, U.S. The 107m long blade will undergo a series of fatigue tests that include moving it millions of times during a few months to validate that it can withstand more than 25 years of operation […]

  • 22 October 2020
    R&D, Technology

    GE Renewable Energy’s Haliade-X prototype, the world’s most powerful wind turbine operating to date, has been optimized and is now operating at a 13 MW power output. During the following months, the prototype operating in the Port of Rotterdam will undergo a series of tests to perform different types of measurements and obtain its type […]

  • 18 June 2020
    Technology

    GE’s Haliade-X 12 MW offshore wind turbine prototype has obtained a provisional type certificate by DNV GL. According to GE, this certification demonstrates that the Haliade-X prototype has the highest safety and quality standards. The company expects the full type certificate in the coming months. “This is a very important milestone for us as it confirms […]

  • 17 December 2019
    Business & Finance

    Dutch energy company Eneco is set to purchase all the electricity generated by GE’s Haliade-X 12MW offshore wind turbine prototype. This was announced during the inauguration ceremony for the prototype held today, 17 December, at the port of Maasvlakte-Rotterdam. According to GE, the Haliade-X 12MW prototype set a new world record the past weekend by […]