233 results found for 'thor'

233 results found for 'thor'
Order results by

A list of search results

  • 4 September 2013
    Wind Farm Update

    The jack-up platform Thor, owned by HOCHTIEF Solutions, is heading to the Global Tech I construction area, carrying three wind turbine towers and gondolas. The vessel will reach the North Sea wind farm in about one day and then start the installation. The towers come in three sections and are transported in an upright position. […]

  • 27 August 2019
    Contracts & Tenders, Wind Farm Update

    Danish transmission system operator Energinet has issued a tender for the procurement of services regarding an unexploded ordnance (UXO) Box survey for the Thor offshore wind farm. Energinet is performing the initial geophysical and geotechnical investigations in the Danish North Sea prior to the procurement of the new wind farm. In order to minimize the […]

  • 14 October 2022
    Contracts & Tenders, Grid Connection, Wind Farm Update

    RWE has selected Siemens Energy and HSM Offshore Energy as preferred suppliers for the electrical transmission system and entered into early works agreements in relation to the construction of the 1 GW Thor offshore wind farm in Denmark. Siemens Energy was selected as the preferred supplier for the design construction, and installation of the onshore […]

  • 15 August 2019
    Contracts & Tenders

    Energinet has contracted MMT Sweden AB to carry out site investigations at an offshore wind project in Denmark. MMT is in charge of carrying out a seabed survey at the site of the 800MW offshore wind farm and its export cable route in the North Sea and Baltic Sea, respectively. A geophysical survey will be performed at […]

  • 25 September 2019
    Contracts & Tenders

    Energinet has issued a tender seeking floating LiDAR measurement services for the Thor offshore wind project in the Danish North Sea. The tender seeks a floating LiDAR to be deployed at the project site more than 20km west of the coast of Jutland to measure wind speed and direction. Additionally, a third-party technical note on the expected […]

  • 24 May 2019
    Wind Farm Update

    Energinet has commenced the feasibility studies for the Thor offshore wind farm in the Danish North Sea. Preliminary investigations start immediately, while the first vessels will begin working on the project site after the summer holidays, the Danish transmission system operator said. Energinet’s Board of Directors decided that approximately DKK 180 million (some EUR 24 million) […]

  • 6 October 2020
    Contracts & Tenders, Grid Connection

    Rambøll will carry out cable route survey work for the Hesselø offshore wind farm in Denmark. According to a recently issued tender award notice, Rambøll signed a contract for the work with the Danish transmission system operator (TSO) Energinet on 18 September, following a tendering procedure. This summer, the Danish Energy Agency instructed Energinet to […]

  • 5 July 2019
    Contracts & Tenders

    Energinet has issued a tender seeking a consultant to provide a strategic environmental assessment (SEA) for the Thor offshore wind farm in Denmark. The work will include a number of surveys to be carried out, as well as technical reports of specific environmental and other themes, for the construction, operation and decommissioning phases of the […]

  • 4 March 2014

    CTruk will have two vessels on the Seawork pontoons this year. CWind Endurance, a 20m Small Waterplane Area Twin Hull (SWATH) OWSV for Dungeness-based Technical Marine Support and CWind, is due for delivery in March 2014 and it is planned that she will grace the pontoon at Seawork later in the year. CTruk has utilised […]

  • 25 September 2020
    Contracts & Tenders, Wind Farm Update

    Fugro Netherlands Marine B.V. has won the contract to carry out a geophysical survey at the proposed Hesselø wind site offshore Denmark. Located in Kattegatt, Hesselø is the second of the three offshore wind farms proposed in Denmark’s Energy Agreement 2018, the first being the Thor project. Both Hesselø and Thor will be commissioned in 2027. Denmark plans […]

  • 15 September 2014
    Business & Finance

    The large jack-up vessel Thor sailed from the North Sea to the Danish city Hirtshals in the beginning of September to be prepared for the ships next assignment in the Baltic Sea. During the stay, Blue Water acted as agent for the ship. “We have wide experience within port agency services and other harbor-related assignments, […]

  • 10 May 2012

    The BARD Group is intensifying its construction activities in the development site of BARD Offshore 1, the first commercial offshore wind farm in the North Sea located around 100 kilometres off the island coast of Borkum. From now on, the JB 117 belonging to the Dutch company Jack-Up Barge B.V. will be used for the […]

  • 23 December 2013
    Wind Farm Update

    From now on, the jack-up vessel Brave Tern from Fred. Olsen Windcarrier will work on the installation of wind turbines in the Global Tech I wind farm. This means, according to plan, a second vessel will supplement the installation work of towers and nacelles in addition to HOCHTIEF’s vessel Thor at the North Sea wind […]

  • 9 October 2019
    R&D

    Developing nearshore wind farms brings significant savings to the community compared to offshore wind projects located more than 20km from the coast, according to an analysis done by KPMG for the Danish HOFOR and European Energy A/S. According to the study, nearshore wind farms can help Denmark achieve a reduction of CO2 emissions by 70% […]

  • 14 June 2023
    Business development, Environment, Equipment, Industry, Infrastructure, Innovation, Outlook & Strategy, Research & Development, Technology, Transition, Wind Farm Update

    German energy company RWE said it will use the ”worldwide-first” recyclable rotor blades at its Thor offshore wind farm in the Danish North Sea. 40 of the 72 SG 14-236 DD wind turbines will be equipped with recyclable rotor blades manufactured by Siemens Gamesa. Installation at sea is expected in 2026. In addition, RWE is […]

  • 23 December 2021
    Business & Finance

    Offshore wind projects coming online in 2021 are getting revenues that are on a EUR per MWh basis on average 55 per cent lower than in 2014, according to Wood Mackenzie. And the most recent bids and WoodMac’s projection show that revenues in 2025 will be 25 per cent lower than in 2021, the energy […]

  • 11 September 2020
    Contracts & Tenders, Wind Farm Update

    Danish transmission system operator Energinet has issued a contract notice seeking environmental engineering consultancy services for the Hesselø offshore wind project. In June 2020, the Danish Parliament decided to commence the development of the Hesselø offshore wind farm. This is the second of the three offshore wind farms proposed in the Energy Agreement 2018, the first […]

  • 22 September 2015
    Vessels

    Njord Offshore have taken delivery of Njord Magni – the 3rd 26m Quad IPS Crew Transfer Vessel. Njord Magni is the third of four sister vessels to be delivered to Njord Offshore this year and is due to be shipped back to Europe from Singapore with Njord Thor in Mid October ’15. Sisters Njord Odin […]

  • 15 November 2019
    Authorities, Business & Finance

    The Danish government has agreed on a new subsidy scheme for the Thor offshore wind project. With the new scheme, the government said a stable settlement price is guaranteed for the power generated by the offshore wind farm and support is provided based on the difference between the agreed price and market price. This means […]

  • 12 December 2013
    R&D

    In the next few days, HOCHTIEF Solutions will commission a further powerful jack-up vessel for the construction of offshore wind farms. In the company of around 300 guests from the European offshore market the ship named VIDAR will officially be commissioned in Bremerhaven on December 12. The jack-up vessel was developed especially for construction and […]

  • 2 July 2020
    Authorities, Contracts & Tenders, Wind Farm Update

    Denmark is accelerating the tendering procedure for the Hesselø offshore wind farm to allow for the commissioning of the project one year earlier than initially planned. Located in Kattegatt, Hesselø is the second of the three offshore wind farms proposed in the Energy Agreement 2018, the first being the Thor project. Initially, Hesselø was scheduled […]

  • 6 December 2021
    Authorities, Contracts & Tenders

    The government of Denmark and several political parties have agreed to add up to 3 GW of new offshore wind capacity to be developed before 2030 as part of the Finance Act 2022. According to the green sub-agreement to the Finance Act 2022, 2 GW of offshore wind capacity must be offered for development before […]

  • 12 June 2023
    Contracts & Tenders, Infrastructure, Operations & Maintenance, Vessels, Wind Farm Update

    Jan De Nul Group has signed an agreement with RWE for the long-term chartering of two next-generation installation vessels for future offshore wind foundation and turbine construction. The charters are supported by a Service Agreement through which Jan De Nul will provide both in-house and market solutions and services, to support and perform installation campaigns […]

  • 17 November 2020
    Contracts & Tenders, Wind Farm Update

    Danish transmission system operator Energinet has selected EOLOS Floating Lidar Solutions SL to deploy a floating LiDAR buoy in the Hesselø offshore wind farm area. The floating LiDAR buoy will measure twelve months of wind speed and direction at the site located in Kattegatt more than 30 kilometers north of the coast of Zealand (Sealand). […]

  • 25 June 2021
    Authorities, Contracts & Tenders, Wind Farm Update

    The Danish Energy Agency has paused the tendering procedure for the Hesselø offshore wind farm to allow more time for the analysis of the results of preliminary seabed studies. The tender was paused after the analysis of Energinet’s preliminary seabed surveys identified soft clay bottoms in large parts of the designated area, especially in the […]

  • 29 March 2021
    Authorities, Business & Finance, Contracts & Tenders, Wind Farm Update

    The Danish government and the parties to the Climate Agreement have agreed on a subsidy scheme for the Hesselø offshore wind farm. To a large extent, the subsidy scheme for Hesselø is similar to the subsidy scheme decided for the Thor offshore wind farm which was based on the recommendations from The Danish Council on […]