218 results found for 'thor'

218 results found for 'thor'
Order results by

A list of search results

  • 18 August 2020
    Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel Jill is nearing completion of the preliminary geotechnical surveys at the Thor offshore wind project in Denmark. According to Fred. Olsen Windcarrier, Jill is progressing on the borehole campaign at the site located west of Nissum Fjord, 20km from the shore. As reported in mid-April, the company secured a contract by Denmark’s Geo to […]

  • 21 December 2022
    Contracts & Tenders, Grid Connection

    Danish transmission system operator (TSO) Energinet has opened a tender for the installation of onshore cables for the connection of the Thor offshore wind farm to the national grid. The tender includes excavation and cable laying work for a cable connection consisting of two 29-kilometre-long 220 kV cables from the substation at Idomlund to the […]

  • 7 July 2020
    Contracts & Tenders, Environment

    Energinet has launched a tender searching for environmental engineering consultancy services for the Hesselø offshore wind project in Denmark. The tender concerns consultancy services for preparing environmental assessments, planning consents and marine environmental baseline investigations for the project that will have an installed capacity of between 800 MW and 1,200 MW. The duration of the […]

  • 14 August 2020
    Wind Farm Update

    The Danish Energy Agency and Energinet have made available the first results and data from site investigations carried out at the Thor offshore wind farm site. As part of the preliminary investigations for the site in the Danish North Sea, Energinet is conducting preliminary geotechnical, geophysical, and biological surveys, as well as collecting metocean data. […]

  • 1 July 2020
    Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel Jill has started the geotechnical investigations at the Thor offshore wind project in the Danish North Sea. Jill completed the first borehole drilling out of 20 in total at the site located west of Nissum Fjord, 20km from the shore. As reported in mid-April, Fred. Olsen Windcarrier secured a contract by Denmark’s […]

  • 19 June 2020
    Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel Jill has left the Port of Esbjerg to begin the preliminary geotechnical investigations for the Thor offshore wind project in the Danish North Sea. In mid-April, Fred. Olsen Windcarrier secured a contract by Denmark’s Geo to supply a vessel for the geotechnical work. The purpose of the assignment is to acquire geotechnical and […]

  • 24 April 2023
    Business development, Equipment, Infrastructure, R&D, Research & Development, Technology

    Siemens Gamesa has revealed its GreenerTower, a wind turbine tower made of more sustainable steel. The company already closed its first order with RWE to feature 36 of the GreenerTower units at the 1 GW Thor offshore wind project in Denmark. Today, tower production accounts for more than one-third of all wind-turbine-related CO2 emissions, according […]

  • 31 March 2020
    Contracts & Tenders, Wind Farm Update

    Danish Energy Agency (Energistyrelsen) plans to launch the tendering process for the Thor offshore wind farm in the third quarter of 2020 with the issuance of the contract notice and the tender documents. The deadline for final bids and the appointment of the concession winner is scheduled for the fourth quarter of 2021, the agency […]

  • 21 April 2021
    Contracts & Tenders, Wind Farm Update

    Denmark’s transmission system operator Energinet has selected the UK marine survey specialist Gardline Ltd to carry out preliminary geotechnical investigations at the Hesselø offshore wind farm. The Hesselø offshore wind farm is located north of Sealand in Kattegat, in Hesselø Bay, at a distance of 30 kilometres from Sealand and around 20 kilometres from the […]

  • 19 September 2013
    Authorities

    Bernard Jenkin, Member of Parliament for Harwich and North Essex, visited Brightlingsea-based designer and builder of multi-purpose composite marine craft, CTruk, in London last week as the defence and security event DSEI drew to a close.  CTruk launched its proof-of-concept Force Protection Craft, THOR – Twin Hulled Offshore Raider, at the show. After meeting the […]

  • 17 July 2017
    Grid Connection, Vessels

    The self-elevating platform JB-117 has been deployed on the DolWin 3 project  in Germany to provide crane support and accommodation services during the float over, installation, hook up and commission of the DolWin gamma converter station topside. Offshore Marine Contractors were appointed by Jack-Up Barge to provide assistance with the mobilisation of JB-117.

  • 27 August 2019
    Contracts & Tenders, Wind Farm Update

    Danish transmission system operator Energinet has issued a tender for the procurement of services regarding an unexploded ordnance (UXO) Box survey for the Thor offshore wind farm. Energinet is performing the initial geophysical and geotechnical investigations in the Danish North Sea prior to the procurement of the new wind farm. In order to minimize the […]

  • 6 July 2022
    Wind Farm Update

    Fugro has started soil investigations off the Danish west coast, where RWE will build the 1 GW Thor offshore wind farm, located approximately 22 kilometres from the port of Thorsminde. Up to three research vessels will be deployed to acquire geotechnical data from the seabed, which is necessary to inform the design, fabrication, and installation […]

  • 7 April 2022
    Contracts & Tenders, Grid Connection, Wind Farm Update

    German-based RWE has signed an agreement with the Danish grid operator Energinet to build two new electrical substations for its 1 GW Thor offshore wind farm. The agreement with Energinet regulates the technical set-up, the power quality, and the cooperation between RWE and Energinet, at the point of connection (POC) in Volder Mark. To connect […]

  • 17 April 2015
    Ports & Logistics, Vessels

    This week, the Port of Oostende welcomed the jack-up vessel Thor for the first time. For the next 3 months, Thor will conduct general maintenance on the C-Power (Thornton Bank) offshore wind farm from the Rebo terminal. A few weeks ago, the seasonal maintenance works started on three offshore wind farms: C-Power, Belwind and Northwind. Besides […]

  • 1 March 2019
    Authorities, Wind Farm Update

    The first of the three 800MW offshore wind farms to be constructed in Danish waters will be built off Nissum Fjord in the North Sea, the country’s Ministry of Energy, Utilities and Climate said. The Thor offshore wind site, to be located at least 20 kilometres offshore, was selected over the second proposed option at the […]

  • 15 August 2019
    Contracts & Tenders

    Energinet has contracted MMT Sweden AB to carry out site investigations at an offshore wind project in Denmark. MMT is in charge of carrying out a seabed survey at the site of the 800MW offshore wind farm and its export cable route in the North Sea and Baltic Sea, respectively. A geophysical survey will be performed at […]

  • 4 September 2013
    Wind Farm Update

    The jack-up platform Thor, owned by HOCHTIEF Solutions, is heading to the Global Tech I construction area, carrying three wind turbine towers and gondolas. The vessel will reach the North Sea wind farm in about one day and then start the installation. The towers come in three sections and are transported in an upright position. […]

  • 25 September 2020
    Contracts & Tenders, Wind Farm Update

    Fugro Netherlands Marine B.V. has won the contract to carry out a geophysical survey at the proposed Hesselø wind site offshore Denmark. Located in Kattegatt, Hesselø is the second of the three offshore wind farms proposed in Denmark’s Energy Agreement 2018, the first being the Thor project. Both Hesselø and Thor will be commissioned in 2027. Denmark plans […]

  • 14 October 2022
    Contracts & Tenders, Grid Connection, Wind Farm Update

    RWE has selected Siemens Energy and HSM Offshore Energy as preferred suppliers for the electrical transmission system and entered into early works agreements in relation to the construction of the 1 GW Thor offshore wind farm in Denmark. Siemens Energy was selected as the preferred supplier for the design construction, and installation of the onshore […]

  • 25 September 2019
    Contracts & Tenders

    Energinet has issued a tender seeking floating LiDAR measurement services for the Thor offshore wind project in the Danish North Sea. The tender seeks a floating LiDAR to be deployed at the project site more than 20km west of the coast of Jutland to measure wind speed and direction. Additionally, a third-party technical note on the expected […]

  • 24 May 2019
    Wind Farm Update

    Energinet has commenced the feasibility studies for the Thor offshore wind farm in the Danish North Sea. Preliminary investigations start immediately, while the first vessels will begin working on the project site after the summer holidays, the Danish transmission system operator said. Energinet’s Board of Directors decided that approximately DKK 180 million (some EUR 24 million) […]

  • 5 July 2019
    Contracts & Tenders

    Energinet has issued a tender seeking a consultant to provide a strategic environmental assessment (SEA) for the Thor offshore wind farm in Denmark. The work will include a number of surveys to be carried out, as well as technical reports of specific environmental and other themes, for the construction, operation and decommissioning phases of the […]

  • 6 October 2020
    Contracts & Tenders, Grid Connection

    Rambøll will carry out cable route survey work for the Hesselø offshore wind farm in Denmark. According to a recently issued tender award notice, Rambøll signed a contract for the work with the Danish transmission system operator (TSO) Energinet on 18 September, following a tendering procedure. This summer, the Danish Energy Agency instructed Energinet to […]

  • 4 March 2014

    CTruk will have two vessels on the Seawork pontoons this year. CWind Endurance, a 20m Small Waterplane Area Twin Hull (SWATH) OWSV for Dungeness-based Technical Marine Support and CWind, is due for delivery in March 2014 and it is planned that she will grace the pontoon at Seawork later in the year. CTruk has utilised […]

  • 15 September 2014
    Business & Finance

    The large jack-up vessel Thor sailed from the North Sea to the Danish city Hirtshals in the beginning of September to be prepared for the ships next assignment in the Baltic Sea. During the stay, Blue Water acted as agent for the ship. “We have wide experience within port agency services and other harbor-related assignments, […]