1123 results found for 'seamade'

1123 results found for 'seamade'
Order results by

A list of search results

  • 30 December 2025
    Cables, Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    Cable-laying vessel (CLV) Seaway Aimery is en route from the US to Europe for work that the vessel has scheduled on the East Anglia Three offshore wind farm in the UK. According to a Notice to Mariners from the East Anglia Three project, inter-array cable installation is set to commence around 12 January 2026, with […]

  • 18 February 2026
    Cables, Fixed-Bottom, Project Updates, Wind Farm Update

    The vessel Seaway Aimery is laying inter‑array cables between wind turbines and the offshore converter platform at the East Anglia Three offshore wind site in the UK. The cable-laying vessel (CLV), which started the installation work in January, is supported by Seaway Moxie and will be joined by two additional vessels around 27 February. Windea […]

  • 27 November 2025
    Fixed-Bottom, Foundations, Project Updates, Vessels, Wind Farm Update

    Seaway7 has installed the last of the total of 277 transition pieces (TPs) on Dogger Bank Wind Farm, the 3.6 GW offshore wind project in the UK North Sea, marking the completion of all foundation installation work. The company’s heavy-lift vessel, Seaway Alfa Lift, started TP transport and installation work on Dogger Bank C, the […]

  • 20 May 2026
    Fixed-Bottom, Ports & Logistics, Project Updates, Supply Chain, Wind Farm Update

    Global Port Services Shipping (GPSS) is providing marine logistics and vessel support services to Seaway7 for work on the Inch Cape offshore wind farm in Scotland, GPSS said on 20 May. The Port of Cromarty Firth in Invergordon is serving as an intermediate port for Seaway7’s heavy lift vessel Seaway Alfa Lift during multiple port […]

  • 11 March 2026
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    Seaway7 is scheduled to start installing monopile transition pieces (TPs) at the Inch Cape offshore wind farm site in Scotland this month. At the beginning of March, the first jacket foundations for the project, which will comprise a combination of monopile and jacket foundations, arrived in the Port of Leith. Heavy-lift vessel Seaway Alfa Lift […]

  • 1 May 2026
    Cables, Grid Connection, Outlook & Strategy, Vessels

    Norwegian shipbuilder Ulstein has held the naming ceremony for Nexans’ new 155-metre-long cable-laying vessel (CLV) Nexans Electra. Based on the ST-297 CLV design by Skipsteknisk, Nexans Electra, ordered as the second vessel by Nexans at Norway’s Ulstein Verft, is an updated version of the sister vessel Nexans Aurora, delivered in 2021. Following the launch of the […]

  • 12 May 2026
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    Navantia Seanergies and Windar Renovables have shipped the final monopiles for East Anglia Three directly to the offshore project site in the UK. The monopiles for the 95-turbine offshore wind farm are being supplied by Haizea Wind Group and the Navantia-Windar consortium, with Windar also delivering the transition pieces for the project. Navantia and Windar’s share of […]

  • 8 January 2026
    Business development, Fixed-Bottom, Foundations, Innovation, Research & Development, Supply Chain

    A consortium comprising AF Gruppen, Multiconsult, DOF, Semar, and the Norwegian University of Science and Technology (NTNU) is set to launch a new project to develop and test technology for the industrial-scale production of gravity-based concrete foundations (GBS). The BetongVIND project, scheduled to commence this month, has a total budget exceeding NOK 20 million (approximately […]

  • 21 April 2026
    Business development, Fixed-Bottom, Foundations, Innovation, Research & Development, Supply Chain, Technology

    IQIP, in partnership with EnBW and Vattenfall, is preparing to carry out the first full-scale offshore installation of its EQ-Piling technology at the Dreekant offshore wind farm site in German waters. The demonstration monopile will be installed by DEME using its installation vessel Orion. The offshore campaign is expected to take place in the coming […]

  • 18 May 2026
    Cables, Grid Connection, Outlook & Strategy, Vessels

    Norway’s Ulstein Verft has delivered the cable-laying vessel (CLV) Nexans Electra to French cable systems designer and manufacturer Nexans, purpose‑built for the transport, laying, protection, repair and jointing of subsea power cables. Nexans Electra was ordered as the second vessel by Nexans at Norway’s Ulstein Verft and is an updated version of sister vessel Nexans Aurora, delivered […]

  • 19 November 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    Ørsted has completed the 2025 foundation installation campaign at the Sunrise Wind offshore project site in the US and is now commencing cable installation works on both its projects under construction in the Northeast US, Revolution Wind and Sunrise Wind. According to the latest Notice to Mariners from the developer, Bokalift 2 and Bokalift 1 […]

  • 18 May 2026
    Business development, Fixed-Bottom, Grid Connection, Infrastructure, Innovation, Power-to-X, Research & Development, Technology

    An underwater data centre (UDC) connected directly to an offshore wind farm has been put into operation off the coast of China’s Lingang Special Area of China (Shanghai) Pilot Free Trade Zone, Chinese media reports. The project, said to be the world’s first of this kind, was officially launched in June 2025 with the signing of […]

  • 6 November 2025
    Business & Finance, Fixed-Bottom, Industry, Jobs & Recruitment, Supply Chain

    The 3.6 GW Dogger Bank Wind Farm, which will become the world’s largest offshore wind farm once fully operational, will boost the UK economy by GBP 6.1 billion (approximately EUR 6.9 billion) during its lifetime and support thousands of UK jobs over the next decade, according to a report written by BVG Associates. The economic […]

  • 12 September 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    Seaway7’s Seaway Strashnov has installed the final monopile at Dogger Bank C, the third phase of the 3.6 GW Dogger Bank Wind Farm, the world’s biggest offshore wind farm under construction, in the UK. This marks the completion of 277 monopile foundations installed by Seaway7 across Dogger Bank A, B, and C throughout the project’s […]

  • 3 September 2025
    Cables, Project Updates, Vessels, Wind Farm Update

    DEME’s cable-laying vessel (CLV) Viking Neptun is scheduled to start installing the first inter-array cables at the Dogger Bank C offshore wind farm site in the UK on or around 7 September. The vessel will lay the inter-array cable onto the seabed, where the cable will remain exposed until trenching is performed, which is scheduled […]

  • 20 July 2018
    Authorities, Business & Finance, Wind Farm Update

    Developers of the Mermaid and the Seastar wind farms in the Belgian North Sea have merged the two projects into one – the 487.2MW Seamade.

  • 3 December 2018
    Business & Finance, Contracts & Tenders, Operations & Maintenance, Wind Farm Update

    Siemens Gamesa has received the order for the 487MW SeaMade offshore wind power project in Belgium from Seamade NV.

  • 3 December 2018
    Business & Finance, Wind Farm Update

    The 487MW SeaMade offshore wind farm in the Belgian North Sea has reached financial close.

  • 20 May 2020
    Grid Connection, Wind Farm Update

    DEME Offshore and Hellenic Cables have completed the testing and energization of the export cable connections at the SeaMade offshore wind project in Belgium. DEME said it is currently carrying out the inter-array cable installation and preparing for the turbine installation campaign, set to begin in mid-June. “Another important milestone for the SeaMade offshore wind […]

  • 15 November 2019
    Grid Connection, Wind Farm Update

    DEME’s cable laying vessel Living Stone has departed Greece carrying the export cables for the 487MW SeaMade offshore wind farm in the Belgian North Sea. Living Stone loaded the export cables with a combined length of around 28 kilometres at Hellenic Cables’ facility in Soussaki. The vessel is currently en route to Vlissingen, the Netherlands. […]

  • 26 November 2020
    Wind Farm Update

    The SeaMade offshore wind farm is nearing completion with only three wind turbines left to be installed. Located 50 kilometres off the Belgian coast in the North Sea, the offshore wind farm will comprise 58 Siemens Gamesa 8.4 MW turbines, 55 of which are now in place. This is according to social media posts from […]

  • 9 July 2020
    Wind Farm Update

    A blade from one of SeaMade’s wind turbines collided with the gangway on DEME Group’s jack-up Apollo, after which the gangway detached from the vessel and fell into the sea. The accident happened on 2 July in the morning and no injuries were reported as there were no employees on the gangway at the time of […]

  • 18 October 2019
    Wind Farm Update

    The first offshore substation transition piece and J-tube cage for the SeaMade offshore wind farm are on their way from Belgium to the Sif terminal in Rotterdam, the Netherlands, DEME Group said. The transition piece was loaded out at Smulders’ yard in Hoboken. Together with the foundation, which is already in Rotterdam, the transition piece and […]

  • 20 March 2020
    Wind Farm Update

    Tekmar Energy Limited has completed the delivery of TekLink® cable protection systems to DEME Offshore for the SeaMade offshore wind farm in Belgium. SeaMade is a 487MW offshore wind farm currently under construction off the coast of Belgium and integrates two wind farm sites known as Mermaid and Seastar. Tekmar Energy was awarded a contract […]

  • 5 March 2020
    Grid Connection, Wind Farm Update

    The first of two offshore substations for the SeaMade offshore wind farm has been installed at the project site in the Belgian North Sea. The 487MW SeaMade wind farm is a combination of the 235MW Mermaid and the 252MW Seastar offshore wind projects. The 1,200t topside, which has four decks and is 14m tall, has been installed […]

  • 22 June 2020
    Wind Farm Update

    DEME Offshore has installed the first wind turbine at the SeaMade offshore wind farm in Belgium, using its jack-up installation vessel Apollo. The vessel will install 57 wind turbines more at the site located 35-50 kilometres off Oostende, where the 487 MW offshore wind farm is scheduled to be fully up and running by the […]