1075 results found for 'seamade'

1075 results found for 'seamade'
Order results by

A list of search results

  • 20 March 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Aspiravi Offshore, part of the Aspiravi Group, will acquire all of Parkwind’s shares in the Northwind offshore wind farm in the Belgian North Sea, increasing its stake to 70 per cent in the 216 MW project. The new shareholder structure between Aspiravi Offshore and Sumitomo Corporation follows the sale of Parkwind to Japan’s JERA Green […]

  • 29 January 2024
    Cables, Fixed-Bottom, Grid Connection, Offshore Platforms

    The export cable of the Rentel offshore wind farm is reported to have been damaged. However, the offshore wind farm keeps feeding electricity into the Belgian grid as the offshore power hub, Modular Offshore Grid (MOG), has taken over. Elia, the operator of Belgium’s MOG, says that the cable from the Rentel platform to the […]

  • 12 July 2024
    Business & Finance, Collaboration, Energy Islands, Grid Connection, Outlook & Strategy

    Ocean Winds, a joint venture between EDP Renewables and ENGIE, Eneco, and Otary have entered into a strategic partnership to jointly compete in the tender for the offshore wind Princess Elisabeth concessions in Belgium. The consortium was formed to compete in the upcoming tenders for the Princess Elisabeth Zone, with the first one expected in […]

  • 2 February 2024
    Vessels

    Seaway7 is saying goodbye to Seaway Yudin, one of the company’s founding vessels and one of the first vessels of its size to serve the offshore wind industry, having entered the offshore wind construction market in 2009. In a social media post published on 2 February, Seaway7 said that the company said farewell to the […]

  • 14 May 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Seaway7’s vessels, Seaway Strashnov and Seaway Alfa Lift, have commenced the installation of monopile foundations and transition pieces (TPs) for Dogger Bank B, the second phase of the 3.6 GW Dogger Bank Wind Farm in the UK, which is set to become the world’s largest offshore wind farm once in operation. The monopiles and TPs, […]

  • 18 March 2024
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    Wind turbine installation is expected to start soon at Ørsted’s Borkum Riffgrund 3 and Gode Wind 3 offshore wind farms in Germany as Seaway7’s newbuild Seaway Ventus, which has been hired to do the work, arrived in Europe. Seaway Ventus was built by China Merchants Heavy Industry (CMHI) at its shipyard in Nantong, Jiangsu province, […]

  • 9 April 2024
    Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    The installation of the offshore substation topside and monopile foundations is about to commence at Dogger Bank B offshore wind farm, the second of the three 1.2 GW phases of the 3.6 GW Dogger Bank Wind Farm in the UK. Installation vessels Saipem 7000 and Seaway Strashnov are expected to arrive at the project site […]

  • 18 March 2024
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Boskalis has completed the work the company was contracted to perform on the Moray West offshore wind farm. While the Dutch offshore construction company has now wrapped up its part of the job, work on Ocean Winds’ 882 MW project offshore Scotland continues with the installation of foundations and inter-array cables underway. Boskalis says that […]

  • 1 April 2024
    Business development, Research & Development

    Iberdrola’s renewable energy development arm in Brazil, Neoenergia, has deployed a floating Light Detection and Ranging (LiDAR) sensor for wind measurement in an area on the north coast of Rio de Janeiro. The LiDAR system will collect data on wind and sea characteristics in an area located approximately 40 kilometres from the coast. Among other […]

  • 6 May 2024
    Business development, Fixed-Bottom, Project Updates, Research & Development, Wind Farm Update

    Denmark’s Copenhagen Offshore Partners (COP) and its compatriot NIRAS have teamed up on a project to kickstart the development of offshore wind farms in the Philippines. In April, COP started the Environmental Impact Assessment (EIA) and the Environment and Social Impact Assessment (ESIA) work for the future offshore wind farm sites, which NIRAS is leading. […]

  • 7 May 2024
    Cables, Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    ZTT Submarine Cable & System has finished the installation and termination of the 155 kV submarine cable connecting the Gode Wind 3 offshore wind farm to the DolWin kappa offshore converter platform in Germany. In 2020, TenneT contracted ZTT Submarine Cable & System to link the 253 MW offshore wind farm to the DolWin kappa […]

  • 3 July 2024
    Business development, Floating Wind, Green Hydrogen, Power-to-X, Research & Development

    After six years of development, sustainability consultancy ERM has launched offshore trials to test its Dolphyn Hydrogen process which combines electrolysis, desalination, and hydrogen production on a floating wind platform, marking the first time hydrogen has been produced from seawater in a marine environment in the UK. The trials conducted in Pembroke Port, South Wales, […]

  • 25 April 2024
    Business & Finance, Business development, Cables, Grid Connection, Outlook & Strategy, Transition, Vessels

    Subsea7 has reported a “robust” backlog of USD 10.4 billion in its financial results for the first quarter of 2024, with tendering activity high in both the subsea and offshore wind sectors. To remind, in the financial results for the full year of 2023, Subsea7 reported it had secured USD 7.4 billion of contract awards […]

  • 8 May 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first Siemens Gamesa’s SG 11.0-200 DD wind turbine has been installed at the Gode Wind 3 offshore wind farm in Germany. In addition, the 253 MW project has started producing electricity for the first time and delivering it to the transmission network. On 23 April, the first of 23 Siemens Gamesa turbines was installed […]

  • 27 March 2024
    Fixed-Bottom, Project Updates, Vessels, Wind Farm Update, Wind Turbines

    The jack-up vessel Voltaire has installed twelve wind turbines at the Dogger Bank A offshore wind farm in the UK so far and is currently in Vlissingen, the Netherlands, where it will undergo scheduled maintenance and return to the UK project in May. This is according to a Notice of Operations from the project issued […]

  • 12 March 2024
    Business development, Fixed-Bottom, Project Updates, Research & Development, Wind Farm Update

    The first geotechnical seabed surveys for TotalEnergies and SSE Renewables’ 500 MW Seagreen 1A offshore wind farm in Scotland have been completed. Phase two of the geotechnical works is expected to commence later this year and should take around two weeks to complete. Seagreen 1A lies adjacent to the existing 1,075 MW Seagreen project and […]

  • 17 April 2024
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Vessels, Wind Farm Update

    Saipem, using its vessel Saipem 7000, has completed the installation of the offshore substation (OSS) at Dogger Bank B, the second phase of the 3.6 GW Dogger Bank Wind Farm in the UK, which is set to become the world’s largest offshore wind farm once in operation. Saipem 7000 arrived this month at the Dogger Bank […]

  • 18 June 2024
    Authorities, Business development, Planning & Permitting, Research & Development

    The federal government of Australia has declared an area in the Pacific Ocean off Illawarra, New South Wales (NSW), as the country’s fourth offshore wind energy development zone, with the final area size reduced following community concerns. The Illawarra offshore wind zone stretches from Stanwell Park to Kiama and covers 1,022 square kilometres instead of […]

  • 20 June 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first Siemens Gamesa SG 11.0-200 DD wind turbine has been installed at the 913 MW Borkum Riffgrund 3 offshore wind farm in Germany. Located approximately 72 kilometres off the coast of Lower Saxony, the Borkum Riffgrund 3 offshore wind farm will feature a total of 83 Siemens Gamesa wind turbines, each with a rated […]

  • 12 July 2024
    Market Outlooks, Outlook & Strategy, Research & Development, Technology, Wind Turbines

    Researchers at the U.S. National Renewable Energy Laboratory (NREL) have found that using electricity generated by offshore wind turbines to split water to produce clean hydrogen may make economic sense.

  • 19 March 2024
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The installation of Siemens Gamesa’s 14 MW wind turbines at the Moray West offshore wind farm site in Scotland is scheduled to start in April. The vessel chartered to install the turbines, Cadeler’s Wind Orca, has just arrived in Esbjerg, Denmark, to mobilise for the project after completing a crane upgrade in the Netherlands. In […]

  • 18 January 2024
    Equipment, Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update

    NOTE: The article was amended on 23 January to include the parts of Dogger Bank Wind Farm’s Supporting Statement filed to the Marine Management Organisation (MMO) that concern the reasons for the delay of the monopile installation on Dogger Bank B. The installation of foundations on two UK offshore wind projects, the 1.4 GW Sofia […]

  • 18 December 2023
    Contracts & Tenders, Equipment, Supply Chain

    Norway-headquartered Glamox has won a contract from Dutch engineering company, Bakker Sliedrecht, to provide specialist marine LED lighting for the foundation platforms for 100 14 MW wind turbines for the Sofia offshore wind farm in the UK. For the Sofia offshore wind farm, Glamox will provide 800 marine-certified LED luminaires, which will illuminate the platforms […]

  • 14 November 2023
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Nexans has started the pull-in of the first of two export cables at the 882 MW Moray West offshore wind farm off the coast of Scotland. The offshore export cables were manufactured by Nexans at its factory in Halden under a contract signed with Ocean Winds in 2021. The Nexans Skaggerak and the Nexans Aurora […]

  • 20 July 2018
    Authorities, Business & Finance, Wind Farm Update

    Developers of the Mermaid and the Seastar wind farms in the Belgian North Sea have merged the two projects into one – the 487.2MW Seamade.

  • 3 December 2018
    Business & Finance, Contracts & Tenders, Operations & Maintenance, Wind Farm Update

    Siemens Gamesa has received the order for the 487MW SeaMade offshore wind power project in Belgium from Seamade NV.