220 results found for 'saint-brieuc'

220 results found for 'saint-brieuc'
Order results by

A list of search results

  • 11 March 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Ailes Marines, an Iberdrola subsidiary, has achieved a milestone by initiating power production from half of the wind turbines at the 496 MW Saint-Brieuc offshore wind farm in France. The commissioning of the project is gradual and will continue until spring 2024, said the developer. Located 16 kilometres off the northwest coast of France in […]

  • 28 May 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The 496 MW Saint-Brieuc offshore wind farm, developed by Ailes Marines, a subsidiary of Iberdrola, has been fully commissioned, making it the second fully operational offshore wind farm in France and the first in Brittany. As of 28 May, all 62 Siemens Gamesa’s SG 8.0-167 DD wind turbines are operational and feeding power into the […]

  • 2 July 2024
    Fixed-Bottom, Operations & Maintenance, Project Updates, Wind Farm Update

    Iberdrola has contracted DNV for power curve verification at the recently commissioned 496 MW Saint-Brieuc offshore wind farm in France so the developer could align actual energy production with initial projections and improve the accuracy of economic models for the wind farm. DNV will perform the work by employing advanced nacelle lidar technology, the global […]

  • 3 April 2024
    Vessels

    Offshore wind service vessel company, Edda Wind, has taken delivery of a newly built service operation vessel (SOV) from Spain’s Astilleros Balenciaga. The SOV C416, later to be renamed Edda Goelo, was delivered to Edda Wind on 26 March. C416 is of Salt 0358 design and the sister vessel of Edda Brint, delivered from Astilleros Balenciaga shipyard in […]

  • 26 March 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The 71st and final wind turbine was installed on 25 March at the Fécamp offshore wind farm in France, the first project of this kind to be built in Normandy. According to EDF Renouvelables, the last wind turbines that were installed are expected to produce electricity in the coming weeks, after testing is completed. The […]

  • 6 February 2024
    Business & Finance, Floating Wind, Ports & Logistics

    The shareholders of the Port of Brest in France, including the Brittany Region, Brest Métropole and the Western Brittany Metropolitan Chamber of Commerce and Industry (CCIMBO), have signed an agreement that will see EUR 900 million invested in developments heavily focusing on the energy transition, including establishing the port as a major player in floating wind. Under […]

  • 5 July 2024
    Contracts & Tenders, Energy Islands, Grid Connection, Offshore Platforms, Supply Chain

    France-headquartered Eiffage has unveiled details about its engineering, procurement, construction, installation, and commissioning (EPCIC) contract, which the company won last month to build four electrical substations for the world’s first artificial energy island, Princess Elisabeth Island. The contract was won through its Belgian arm Eiffage Métal subsidiary Smulders, in a consortium with HSM Offshore Energy […]

  • 16 May 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The 500 MW Fécamp offshore wind farm, owned by Eolien Maritime France (EMF), a joint venture between the French company EDF Renouvelables; EIH S.à.rl, owned by Enbridge Inc. and CPP Investments; and Skyborn Renewables (formerly wpd offshore), is now fully operational. The inauguration ceremony was held by the project partners and Roland Lescure, French delegated […]

  • 29 May 2024
    Business & Finance, Fixed-Bottom, Industry

    Beatrice Offshore Windfarm Limited (BOWL), the operator of an 85-turbine wind farm off northeast Scotland, has agreed to make a payment of GBP 33.14 million (approximately EUR 39 million) after admitting it breached energy market rules. BOWL, the operator of the 588 MW Beatrice offshore wind farm, admitted to breaching one of its licence conditions […]

  • 18 December 2023
    Fixed-Bottom, Project Updates, Wind Farm Update

    All 62 wind turbines have been installed at the Saint-Brieuc offshore wind farm in France, developed by Ailes Marines, a 100 per cent subsidiary of Iberdrola. The first wind turbine was installed in May on position number SB44, located in the northern part of the offshore construction site while the last SG 8.0-167 DD unit […]

  • 8 December 2023

    The French company, SPIE, has revealed the plan to take over UK-based offshore wind engineering, installation, and maintenance services company, Correll Group. Founded in 2014 and headquartered in Skelton, Correll Group stands out for its knowledge in the connection and testing of submarine high-voltage cables for the interconnection of wind farms, said SPIE. According to […]

  • 22 November 2023
    Business development, Innovation, Jobs & Recruitment, Operations & Maintenance

    Iberdrola France has launched its platform to identify and collaborate with companies committed to renewable energy and offshore wind for upcoming calls for tenders. According to Iberdrola, the company’s goal is to integrate new partners into the Iberdrola France network to facilitate collaboration on territories and future offshore wind projects. Iberdrola France is organising a […]

  • 9 October 2023
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The last jacket foundation has been installed at the Saint-Brieuc offshore wind farm in France, being built by Iberdrola through its wholly-owned subsidiary Ailes Marines. The Saint-Brieuc offshore wind farm features 62 jacket foundations that will support Siemens Gamesa SG 8.0-167DD wind turbines. All 62 1,150-tonne units for the 496 MW project have been produced […]

  • 19 September 2023
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The Navantia-Windar consortium has loaded out and shipped the last three jacket foundations for the Saint-Brieuc offshore wind farm from Navantia’s yard in Fene, Spain. In April 2021, the assembly of the first jacket foundation was completed at the Navantia Seanergies shipyard in Fene. Just over a year later, in June 2022, the first four […]

  • 19 September 2023
    Floating Wind, Project Updates, Wind Farm Update

    The first Siemens Gamesa 8 MW floating wind turbine has been installed at the Provence Grand Large offshore wind farm site off the coast of Port-Saint-Louis-du-Rhône in France. After assembling the turbine and its float, the first Provence Grand Large wind turbine left Quai Graveleau in Fos-sur-Mer to be towed 17 km from the coast […]

  • 28 August 2023
    Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    The installation of the jacket foundation piles at the Saint-Brieuc offshore wind farm in France has been completed and Van Oord’s vessel Aeolus, which was being used to perform the work, has now left the project site, Ailes Marines, the project development company wholly owned by Iberdrola, said on 28 August. All locations that (will) […]

  • 19 September 2023
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    UK-headquartered Octopus Energy has made an investment in the 731.5 MW Borssele III and IV offshore wind farm in the Dutch North Sea. Octopus Energy Generation acquired a 10 per cent stake in the fully operational 731.5 MW offshore wind farm, located 55 kilometres from the Port of Vlissingen in the Netherlands. The deal comes […]

  • 18 August 2023
    Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel Brave Tern has installed 31 out of 62 Siemens Gamesa SG 8.0-167 DD wind turbines at the Saint-Brieuc offshore wind farm in France. The first wind turbine was installed in May on position number SB44, located in the northern part of the offshore construction site. The wind turbines are manufactured […]

  • 6 July 2023
    Wind Farm Update

    The 496 MW Saint-Brieuc offshore wind farm, being built by Iberdrola through its wholly-owned subsidiary Ailes Marines in the Bay of Saint-Brieuc in Brittany, has produced its first green power. The project is Iberdrola’s first in France and only the second offshore wind farm to produce power in the country, according to the press release. […]

  • 19 June 2023
    Wind Farm Update

    The Navantia-Windar consortium has started shipping the remaining jacket foundations for the French Saint-Brieuc offshore wind farm, being built by Iberdrola through its wholly-owned subsidiary Ailes Marines in the Bay of Saint-Brieuc in Brittany. Each batch will comprise four jackets of the 38 that are still in the Navantia Seanergies Fene shipyard. All 62 foundations […]

  • 30 April 2021
    Wind Farm Update

    Navantia has completed the construction of the first jacket foundation for the French Saint-Brieuc offshore wind farm at its shipyard in Fene, Spain. The completion of the first jacket follows the reception of the first batch of components manufactured at the French port of Brest. The components have been assembled to the main blocks manufactured […]

  • 1 December 2022
    Contracts & Tenders, Wind Farm Update

    Global renewable energy company, RES, has signed a contract with Ailes Marines, a subsidiary of Iberdrola, for the maintenance and upkeep of the Saint-Brieuc offshore substation in France. This is RES’ first offshore O&M contract in France. The company is currently operating in eleven countries and provides large-scale renewable energy, energy storage, and transmission projects […]

  • 21 April 2021
    Wind Farm Update

    Construction works on the Saint-Brieuc offshore wind farm in France will begin on 3 May, Iberdrola announced on 21 April. The works, starting with pile installation for the project’s jacket foundations, are planned to take place from May to October in five zones located in the northern part of the wind farm to avoid interfering […]

  • 22 June 2021
    Business & Finance

    Navantia has manufactured the first node using robotic welding for the Saint-Brieuc offshore wind project. This is the first time automated welding of offshore nodes was carried out in commercial phase, according to the Spanish offshore wind foundation manufacturer. The robotised node welding cell, whose industrial property is shared by Navantia, INTAF, AIMEN and Electrorayma, […]

  • 7 July 2022
    Vessels, Wind Farm Update

    The installation vessel Saipem 7000 and the jacket foundation for the Saint-Brieuc wind farm’s offshore substation have arrived in the Bay of Saint-Brieuc ahead of installation work, which will begin once the topside – currently en route to the project site – also arrives in the French bay. After the load-outs in June, both the […]

  • 1 March 2023
    Operations & Maintenance, Wind Farm Update

    The technical base of the Saint-Brieuc offshore wind farm was inaugurated on 24 February, however, this solution remains temporary, pending the final realisation of the maintenance base in the port of Saint-Quay-Portrieux. The temporary technical base of the French offshore wind farm was inaugurated by Daniel Cueff, Vice President of the Brittany region, and Stéphane […]