1073 results found for 'dogger bank'

1073 results found for 'dogger bank'
Order results by

A list of search results

  • 8 November 2024
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Production of the last transition piece (TP) for the 3.6 GW Dogger Bank Wind Farm, the world’s largest offshore wind farm under construction, is underway at Smulders facility in Hoboken, Belgium. The consortium comprising Sif and Smulders was awarded contracts for the manufacture of all monopiles and transition pieces for the three-phased Dogger Bank Wind […]

  • 3 January 2025
    Fixed-Bottom, Foundations, Project Updates, Vessels, Wind Farm Update

    The offshore installation vessel Seaway Strashnov has installed all but two monopile foundations at the Dogger Bank B offshore wind site in the UK and will return in the second quarter of 2025 to complete the installation. Five more transition pieces (TPs) are also left to be installed, according to the latest notices to mariners […]

  • 12 December 2024
    Business & Finance, Contracts & Tenders, Supply Chain, Wind Turbines

    Dogger Bank Wind Farm, a joint venture between SSE Renewables, Equinor, and Vårgrønn, has signed a vessel reservation agreement with Seaway7 to charter a second turbine installation vessel to support the ongoing delivery of the offshore wind farm off the coast of England. Starting in 2026, the Seaway Ventus jack-up installation vessel is planned to […]

  • 31 January 2025
    Business & Finance, Vessels

    UK-headquartered North Star has named and delivered its latest service operation vessel (SOV), completing its fleet of vessels chartered for long-term service at the 3.6 GW Dogger Bank offshore wind farm. The Grampian Tweed is the fourth SOV introduced ahead of schedule to support the Dogger Bank offshore wind farm, owned by a consortium of […]

  • 9 December 2024
    Business & Finance, Cables, Contracts & Tenders, Fixed-Bottom, Grid Connection, Supply Chain

    Proserv has been awarded a contract by DEME Offshore to de-risk offshore wind operations at Dogger Bank C, the third phase of the 3.6 GW Dogger Bank Wind Farm project in the UK. According to Proserv, the company will utilise its Electro Cable Guard (ECG) system to identify signs of transmission cable failure far earlier, […]

  • 3 October 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    SSE has revealed that the completion of Dogger Bank A, the first of the three phases of the UK’s Dogger Bank Wind Farm, is projected for the second half of 2025, which is later than the previously expected first half of the year. In its interim earnings report released on 3 October, SSE said that […]

  • 4 November 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Van Oord, using its jack-up vessel Aeolus, has installed 34 of the total 100 monopiles at the Sofia offshore wind farm site in the UK, according to a Notice to Mariners issued on 29 October. Aeolus installed the first monopile at the Sofia project site, located on Dogger Bank in the central North Sea, in […]

  • 21 March 2025
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    Cadeler’s wind turbine installation vessel (WTIV) Wind Peak is en route to the site of the Sofia offshore wind farm with the first set of Siemens Gamesa’s SG 14-222 DD turbine components. The vessel departed the port of Hull on 20 March, according to the available AIS data, and is heading towards the project site […]

  • 27 February 2025
    Authorities, Business & Finance, Fixed-Bottom, Grid Connection, Planning & Permitting

    Ofgem is inviting tenders to own and operate electricity transmission links worth GBP 4 billion (about EUR 4.8 billion), connecting the Sofia offshore wind farm to Great Britain’s mainland energy network. Ofgem has opened the Offshore Transmission Owner (OFTO) regime Tender Round 12, which invites investors to bid to own and operate infrastructure connecting RWE’s […]

  • 17 December 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    Seaway7, part of the Subsea7 Group, has been awarded a contract by Inch Cape Offshore Limited (ICOL), a joint venture between ESB and Red Rock Renewables, for the transport and installation of pin-pile jacket foundations and transition pieces (TPs) for the 1.1 GW offshore wind project. The deal is worth between USD 150 million and […]

  • 3 October 2024
    Fixed-Bottom, Manufacturing, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    RWE has unveiled the first 108-metre turbine blade made at the Siemens Gamesa factory in Hull, which will be part of 100 wind turbines to be installed at the 1.4 GW Sofia offshore wind farm in the UK. Each of the 100 wind turbines, rated at 14 MW, will be equipped with 108-metre-long blades that […]

  • 7 November 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Vårgrønn has agreed to acquire a 27.4 per cent stake in the 288 MW Baltic 2 offshore wind farm from PGGM Infrastructure Fund, marking its entry into the German market. Following the deal closing, Vårgrønn and EnBW will own 27.4 per cent and 50.1 per cent, respectively, with EnBW responsible for operations and maintenance activities. […]

  • 5 December 2024
    Business & Finance, Fixed-Bottom, Floating Wind

    Shell has decided to cease investments in new offshore wind developments as part of a review of the Shell Energy business. The oil and gas major, which has built a significant portfolio of renewable energy and clean fuel projects, will not abandon its existing offshore wind projects, but investing in new offshore wind farms is […]

  • 21 January 2025
    Authorities, Fixed-Bottom, Planning & Permitting

    The US Bureau of Ocean Energy Management (BOEM) and the Bureau of Safety and Environmental Enforcement (BSEE) have completed the review and approved the revised Construction and Operations Plan (COP) for the Vineyard Wind 1 offshore wind farm. Last week, the federal government lifted the suspension on Vineyard Wind’s installation of the remaining GE Vernova […]

  • 24 October 2024
    Cables, Grid Connection, Project Updates, Vessels, Wind Farm Update

    Van Oord’s new, next-generation cable-laying vessel (CLV) Calypso has begun installing cables at its first offshore wind project, marking its official debut. Calypso’s first project is RWE’s Sofia offshore wind farm, being constructed on Dogger Bank in the central North Sea, 195 kilometres from the North East coast of the UK, which, with a capacity […]

  • 17 March 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    RWE’s Sofia offshore wind farm in the UK has reached several major milestones in the construction of foundations and onshore and offshore electrical systems and is now preparing for the first turbine installation expected in the coming weeks. Last week, Cadeler’s wind turbine installation vessel (WTIV) Wind Peak arrived, ready to transport the first set […]

  • 1 January 2025
    Business development, Equipment, Fixed-Bottom, Floating Wind, Operations & Maintenance, Project Updates, Supply Chain, Technology, Vessels, Wind Farm Update, Wind Turbines

    New wind turbine models, vessels and equipment, and project updates were the most read topics on offshoreWIND.biz in 2024. In this overview, we are bringing the ten most popular news in 2024. In January 2024, Siemens Gamesa received a EUR 30 million grant from the EU for a project called Highly Innovative Prototype of the […]

  • 25 February 2025
    Business development, Innovation, Technology, Vessels

    Dutch company Next Ocean is looking at a global reach for its technology that predicts waves and vessel motions minutes beforehand. Following a period of demonstration deployments of WavePredictor and the first vessels using it commercially, Next Ocean says it is witnessing the technology becoming standard equipment onboard vessels working in offshore wind and other […]

  • 2 September 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The blade failure event at the Dogger Bank A offshore wind farm last month was not caused by an installation or manufacturing issue but happened during the commissioning process, according to an analysis conducted by GE Vernova. The blade failure occurred on the morning of 22 August and, according to an update from the Dogger […]

  • 23 August 2024
    Fixed-Bottom, Manufacturing, Supply Chain, Wind Farm Update, Wind Turbines

    This article was updated at 15:05 CET on 23 August 2024 with a statement from GE Vernova. One of the already installed wind turbine blades at Dogger Bank A offshore wind farm, currently under construction in the UK, has sustained damage and failed. The blade failure occurred on the morning of 22 August and, according […]

  • 29 August 2024
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The high-voltage direct current (HVDC) offshore converter platform (OCP) has been installed at the Sofia offshore wind farm site in the UK. The installation was carried out by Heerema Marine Contractors, using its Sleipnir heavy-lift vessel as a subcontractor to the GE Vernova/Seatrium consortium responsible for the OCP. The platform, equivalent in height to an […]

  • 12 August 2024
    Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    A multibeam echosounder (MBES) geophysical survey of the Dogger Bank D offshore wind site, using several uncrewed surface vessels (USVs), is scheduled to start on 13 August. According to information in the project’s Notice to Mariners, XOCEAN will deploy multiple USVs to survey the wind turbine array site and the export cable route. The USVs will […]

  • 23 August 2024
    Vessels

    Norway’s Integrated Wind Solutions has taken delivery of its third Commissioning Service Operation Vessel (CSOV) in the Skywalker class series, named IWS Seawalker. IWS Fleet, a fully owned subsidiary of IWS, signed newbuild contracts with China Merchants Heavy Industry (CMHI) for two purpose-built, walk-to-work CSOVs in March 2021 through IWS’s then subsidiary Awind. In March 2022, IWS […]

  • 10 February 2025
    Authorities, Floating Wind, Planning & Permitting, Ports & Logistics

    A new bill has been introduced in California’s state legislature that would add an assessment of funding opportunities for offshore wind port infrastructure to the Governor’s Five-Year Infrastructure Plan. Introduced on 6 February, Assembly Bill 472 would amend the definition of “infrastructure” in the California Infrastructure Planning Act to include offshore wind port infrastructure as […]

  • 28 February 2025
    Authorities, Market Outlooks, Outlook & Strategy, Planning & Permitting, Transition

    The European Union has unveiled the Clean Industrial Deal, a transformational business plan outlining concrete actions to turn decarbonisation into ‘a driver of growth‘ for European industries by supporting renewable energy sources. Specifically, the plan aims to lower energy prices, create ‘quality’ jobs and the ‘right’ conditions for companies to thrive, accelerating decarbonisation while at […]

  • 25 September 2024
    Contracts & Tenders, Supply Chain, Vessels

    Havfram has signed a contract with Luxcara, an independent German asset manager specialized in clean energy infrastructure projects, for the transport and installation support of wind turbines for the Waterkant offshore wind farm in the German North Sea. The agreement covers the vessel charter for transport and installation of 16 of the foreseen 18.5 MW […]