Search results for: dogger bank

433 results

A list of search results

  • 23 June 2021
    Wind Farm Update

    Fugro is set to commence a geophysical survey at the Dogger Bank B offshore wind farm in the UK today, 23 June. Survey vessel Fugro Froneiter will be conducting the survey between 23 June and approximately 30 August. Operations will be continuous, 24 hours a day, with the vessel towing subsea sensors up to approximately […]

  • 9 June 2021
    Vessels, Wind Farm Update

    The Fugro Synergy survey vessel is currently conducting a geotechnical survey in the Dogger Bank C array area and export cable route, while the vessel Wind of Pride is performing inspection works in the Dogger Bank A array area and the export cable routes for Dogger Bank A & B. According to the latest update […]

  • 18 May 2021
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Dogger Bank Wind Farm and GE Renewable Energy have finalised contracts for the supply of 87 Haliade-X 14 MW turbines and a five-year service and warranty agreement for Dogger Bank C, the third and final phase of what will become the world’s largest offshore wind farm. GE Renewable Energy secured a preferred turbine supplier agreement […]

  • 3 June 2021
    Contracts & Tenders, Vessels, Wind Farm Update

    Dogger Bank Wind Farm has chartered two newbuild Commissioning Service Operation Vessels (CSOV) for the construction and commissioning work on Dogger Bank – the world’s largest offshore wind project. Dogger Bank Wind Farm signed charter agreements for one CSOV each with Edda Wind and Awind AS. Under the terms of the contract, Edda Wind will […]

  • 7 April 2021
    Contracts & Tenders, Wind Farm Update

    Spanish manufacturer of rolled rings euskalforging has won a contract to deliver flanges for the 1.2 GW Dogger Bank A offshore wind farm. Under the contract, euskalforging will roll, heat treat, machine, and deliver flanges for all the 95 monopile foundations and transition pieces of the Dogger Bank A. According to the company, this will […]

  • 17 May 2021
    Contracts & Tenders

    Axess Group has secured an Enterprise of Competence service contract with Aibel for the lifting equipment on the Dogger Bank A offshore substation. Under the contract, Axess will provide engineering review, inspection, testing and certification of the lifting appliances on the platform, to ensure statutory compliance and delivery of the asset to regional operational standards. […]

  • 30 June 2021
    Grid Connection, Wind Farm Update

    NKT has secured a contract to deliver and install the HVDC onshore and offshore export cables at the Dogger Bank C offshore wind farm in the UK. The scope of work includes the manufacture, delivery and installation of more than 2×250 kilometres total system length of 320 kV DC offshore export power cables and accessories. […]

  • 14 July 2021
    Contracts & Tenders, Wind Farm Update

    Granada Material Handling has secured three new contracts from Dogger Bank Tier 1 suppliers. Smulders will see 95 Granada cranes installed on the first phase of the wind farm, Dogger Bank A, and 95 cranes installed on the second phase of the wind farm, Dogger Bank B. One crane will be installed on each wind […]

  • 27 August 2021
    Operations & Maintenance, Wind Farm Update

    Ryder Geotechnical has completed site-specific assessment (SSA) at the turbine locations of the first two phases of the Dogger Bank offshore wind project. Ryder completed a geotechnical zonation assessment to classify the 190 turbine locations in terms of geotechnical risk to the upcoming jack-up operations at Dogger Bank A and B. According to the company, […]

  • 22 July 2021
    Contracts & Tenders, Vessels

    Red Rock has been awarded a contract by Vard for equipment supply for the three service operations vessels (SOVs) owned by North Star Renewables that have been chartered for the Dogger Bank Wind Farm in the UK. Red Rock will deliver two 2T 3D Motion Compensated cranes, a 5T 3D Motion Compensated crane, three 2T […]

  • 12 July 2021
    Contracts & Tenders, Vessels, Wind Farm Update

    After winning contracts to install GE Haliade-X 13 MW offshore wind turbines at Dogger Bank A & B last year, Jan De Nul has now signed an agreement with Dogger Bank Wind Farm for the transport and installation of 87 GE Haliade-X 14 MW units at the final phase of the project, Dogger Bank C. […]

  • 16 June 2021
    Contracts & Tenders

    Equinor has selected Vissim for the provision of digital support of the marine operations at the 3.6 GW Dogger Bank Wind Farm in the UK. Under a long-term framework agreement, the Norway-based company will provide digital marine optimisation solutions to the operator’s offshore wind projects, including an immediate call-off for Dogger Bank A, B and […]

  • 4 May 2021
    Grid Connection, R&D, Technology, Wind Farm Update

    Dogger Bank Wind Farm, the world’s largest offshore wind project, will use what the developers say is ”a revolutionary platform design, unveiling the world’s first unmanned High Voltage Direct Current (HVDC) offshore substation.” When complete in 2026, the 3.6 GW Dogger Bank wind farm will become the biggest in the world, able to produce enough […]

  • 25 March 2021
    Operations & Maintenance, Ports & Logistics, Wind Farm Update

    The developers of the Dogger Bank Wind Farm have revealed the design for the Operations and Maintenance (O&M) Base that will serve the world’s biggest offshore wind farm. Subject to planning approval, the base will be constructed in the Port of Tyne, the UK. It will serve as the main hub for operating the 3.6 […]

  • 9 July 2021
    Grid Connection, Wind Farm Update

    Delivery of onshore cables for Dogger Bank Wind Farm has started, according to Jones Bros Civil Engineering UK, the company responsible for installing the cables for the first two phases of the offshore wind project. The first drum with the cables has already arrived and Jones Bros are set to commence installation this month. In […]

  • 24 August 2021
    Contracts & Tenders, Vessels, Wind Farm Update

    North Star Renewables has secured a loan of GBP 96 million (approximately EUR 112 million) from Allianz Global Investors (AllianzGI) to build the three Service Operations Vessels (SOVs) that will serve the Dogger Bank offshore wind farm.  The vessel owner said the loan added to its own balance sheet and equity commitments from its 100 per cent shareholder, […]

  • 10 June 2021
    Contracts & Tenders, Technology, Wind Farm Update

    ABB will deliver 95 units of medium voltage converters for wind turbines to GE Renewable Energy for the first phase of the Dogger Bank offshore wind project. This is ABB’s first major order under its Long-Term Supply Agreement (LTSA) with GE Renewable Energy and the largest order of its kind to date. The 95 PCS6000 […]

  • 21 July 2021
    Operations & Maintenance, Wind Farm Update

    South Tyneside Council’s Planning Committee has granted permission for the construction of Dogger Bank Wind Farm’s operations and maintenance (O&M) base in the Port of Tyne. Equinor submitted an application with the accompanying planning documents to the Planning Committee in February, requesting permission to build the O&M base and warehouse with associated access, parking, landscaping […]

  • 13 September 2021
    Vessels

    Awind, a subsidiary of Integrated Wind Solutions, has ordered equipment packages for two Commissioning Service Operation Vessels (CSOVs) from MacGregor, part of Cargotec. MacGregor will deliver two equipment packages each consisting of a 3D motion compensated electrical gangway system, Colibri crane, and a remote control station located on the vessel bridge. The two vessels, scheduled […]

  • 13 April 2021
    Contracts & Tenders, Technology

    Bakker Magnetics is about to start the production of magnetic assemblies for the GE Haliade-X turbines that will be installed at the 3.6 GW Dogger Bank offshore wind project in the UK. Bakker Magnetics will fabricate and assemble magnetic assemblies for the turbines across all three phases of what is the world’s largest offshore wind […]

  • 28 May 2021
    R&D, Technology, Wind Farm Update

    The developers of the 3.6 GW Dogger Bank, the world’s largest offshore wind farm, will carry out the first large-scale pilot of a new process that is expected to reduce welding times by as much as 80 per cent. Ebflow Reduced Pressure Electron Beam (RPEB) welding is expected to be used at the 1.2 GW […]

  • 8 July 2021
    Wind Farm Update

    The 1.4 GW Sofia and the 1.2 GW Dogger Bank C offshore wind projects have marked the start of their onshore construction with an official ground-breaking in Teesside, the UK. The separate wind farm projects are sited on Dogger Bank in the middle of the North Sea, more than 190 kilometres from the North East […]

  • 14 September 2021
    Operations & Maintenance, Wind Farm Update

    Construction works on the operations and maintenance (O&M) base for what will become the world’s largest offshore wind farm, the 3.6 GW Dogger Bank project, are expected to start this month. Announcing that the O&M base will be constructed and operated in line with the UK Green Building Council’s Net Zero Carbon Buildings Framework on […]

  • 6 May 2021
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Six offshore wind projects under development in the UK, with a total installed capacity 5.5 GW, have passed their Milestone Requirement (MR), Low Carbon Contracts Company (LCCC) reported. The MR is the first significant milestone for projects awarded Contracts for Difference (CfDs), as it requires developers to demonstrate their commitment to delivering the project. The […]

  • 6 July 2021
    Vessels

    Uptime International AS has been awarded three contracts from Vard Singapore for the supply of three walk-to-work systems for North Star Renewables’ service operation vessels (SOVs). UPTIME’s scope of supply consists of three complete access systems for personnel and cargo, each consisting of a 30m autonomous gangway with artificial intelligence, mounted on elevator towers. One […]

  • 17 March 2021
    Business & Finance, Contracts & Tenders, Vessels, Wind Farm Update

    Aberdeen-based company North Star Renewables has won the tender for the delivery of three service operation vessels (SOVs) for the 3.6 GW Dogger Bank project, which is set to become the world’s biggest offshore wind farm. Under a contract worth approximately GBP 270 million (around EUR 316 million), the Scottish company is responsible for the […]