Search results for: dogger bank

4898 results

A list of search results

  • 6 May 2015
    Authorities, Wind Farm Update

    The UK Planning Inspectorate submitted a report of recommendation for Forewind’s Dogger Bank Teesside A&B offshore wind project to the Secretary of State on May 5. The Secretary of State will issue a decision in the following three months. Dogger Bank Teesside is Forewind’s second stage of development of the Dogger Bank Zone. Originally planned to be four separate wind […]

  • 26 November 2020
    Business & Finance, Contracts & Tenders

    Norwegian state-backed Export Credit Guarantee Agency GIEK is providing loan guarantees for contracts awarded to Aibel and OHT for the UK’s Dogger Bank A and B offshore wind project, for which Equinor and SSE have now reached financial close. Aibel has won a contract to deliver two converter platforms for the 2.4 GW Dogger Bank […]

  • 3 August 2015
    Authorities, Wind Farm Update

    The UK Energy Secretary is expected to decide on the Dogger Bank Teesside A&B offshore wind project on August 5.  The UK Planning Inspectorate issued a report of recommendation to the Secretary of State on 5 May 2015. The Secretary of State then issues a decision within the following 3 months. The decision letter and report of […]

  • 14 September 2020
    Contracts & Tenders, Wind Farm Update

    Dogger Bank Wind Farm has signed the contract with OHT to transport and install foundations for the second phase of the world’s largest wind farm – the 3.6 GW Dogger Bank. Dogger Bank Wind Farm and OHT signed the contract for the 1.2 GW Dogger Bank A phase in July. The new contract covers the […]

  • 17 November 2020
    Contracts & Tenders, Wind Farm Update

    The consortium of Sif Netherlands and Smulders Projects Belgium will manufacture all the monopiles and transition pieces for the Dogger Bank A & B offshore wind farm project. Dogger Bank Wind Farm, a joint venture between SSE Renewables and Equinor, awarded the consortium with the contract to manufacture and deliver 190 monopiles and transition pieces […]

  • 16 December 2015
    Wind Farm Update

    Assigning operators for four Dogger Bank offshore wind projects is the next major step that needs to be taken so that the projects could enter the pre-construction phase.  Forewind, the consortium behind the Dogger Bank development, said that the initial aim will be to assign operators for the two projects that make up Dogger Bank Creyke Beck, which is expected […]

  • 18 November 2020
    Business & Finance, Wind Farm Update

    Financial close on the first two phases of the world’s largest offshore wind farm at Dogger Bank is expected in the coming days, SSE said. SSE Renewables and Equinor are jointly developing the 3.6 GW Dogger Bank offshore wind project through a 50:50 joint venture company – Dogger Bank Wind Farm. The project is divided […]

  • 7 August 2015
    Wind Farm Update

    Forewind, together with its owners and in agreement with The Crown Estate, has ceased work on its remaining development consent application to focus efforts on the four consented Dogger Bank projects, the consortium reported today. With the consent award earlier this week, the Dogger Bank development now totals 4.8GW and includes four 1.2GW projects – […]

  • 22 March 2018
    Business & Finance

    Dogger Bank Joint Venture, developing three out of four 1.2GW Dogger Bank offshore wind farms, will hold a Meet the Buyer event on 23 May at the Hardwick Hall Hotel in Sedgefield, North East England, to present business opportunities to UK companies. Besides presentations by the Dogger Bank JV team, the visitors will be able to […]

  • 7 August 2020
    Vessels, Wind Farm Update

    Dogger Bank Wind Farm has signed a contract with Jan De Nul Group for the transport and installation of GE Haliade-X offshore wind turbines at Dogger Bank A and Dogger Bank B. The installation of the 12 MW units at the site some 130 kilometres off the Yorkshire coast will start in 2023. Turbine transport […]

  • 20 August 2020
    Contracts & Tenders, Wind Farm Update

    DEME Offshore has signed a contract with Dogger Bank Wind Farm to provide the inter-array cables for Dogger Bank A and Dogger Bank B offshore UK. Under the EPCI contract, DEME will in total supply, install and protect 650km of 66kV inter-array cables and all related accessories. Production will start in 2021 and the company’s […]

  • 1 October 2019
    Contracts & Tenders, Wind Farm Update

    Dogger Bank Wind Farms, which is developing what will become the world’s largest offshore wind farm when built, has unveiled GE Renewable Energy as its preferred turbine supplier. Under the new deal, GE Renewable Energy will supply Dogger Bank with the Haliade-X turbine, bringing the world’s most powerful wind turbine to the world’s largest wind […]

  • 5 May 2016
    Operations & Maintenance, Technology, Vessels, Wind Farm Update

    Forewind has used its latest operations and maintenance trip to the meteorological masts on Dogger Bank to trial new technology and methodology. The trip enabled aerial inspection and survey contractor Cyberhawk to utilise a new advanced camera technology to inspect the overall status of the met masts and condition of bolts along with the structure of the lattice […]

  • 22 October 2019
    Contracts & Tenders, Vessels, Wind Farm Update

    Jan De Nul’s new offshore jack-up installation vessel Voltaire will have its debut on the 3.6GW Dogger Bank offshore wind farm in the UK. With a lifting capacity of over 3,000 tonnes and standing taller than the Eiffel tower, Voltaire is the largest of its kind in the world, Jan De Nul said. The Voltaire […]

  • 30 April 2015
    Wind Farm Update

    Through the undertaken surveys as part of its environmental impact assessment process, Forewind has extended the depth of knowledge about the geology of Dogger Bank. Geological maps used prior to Forewind’s work in the area were based on sparse data, gathered tens of kilometres apart in the late 1960s and 1970s. But since a far greater […]

  • 8 May 2012

    Forewind, development partner for the Dogger Bank Zone, potentially the world’s largest wind energy project, announces its first community consultation events in relation to its second stage of development: Dogger Bank Teesside. Dogger Bank Teesside is planned to comprise up to four offshore wind farm projects located at least 156 kilometres off the Teesside coast […]

  • 22 July 2020
    Contracts & Tenders

    Saipem revealed on 22 July that it won three contracts for offshore wind farms in Europe – Dogger Bank A and B, Seagreen, and Saint Brieuc – valued at more than EUR 90 million in total. With the Equinor-SSE Renewables join venture Dogger Bank Offshore Wind Farms, Saipem inked a deal for the transportation and […]

  • 4 September 2017
    Business & Finance, Wind Farm Update

    Scotland’s energy company SSE has confirmed the formation of a 50:50 joint venture (JV) partnership with Norway’s Statoil to progress three of the four consented Dogger Bank offshore wind projects towards financial investment decisions.

  • 1 April 2016
    Business & Finance, Operations & Maintenance, Vessels

    Forewind has awarded a combined Fred. Olsen Windcarrier and SeaRoc team with the contract for the 2016 operations and maintenance (O&M) work on the two meteorological masts collecting data at Dogger Bank. The two masts were installed in 2013 and are located in the North Sea approximately 100 and 150 kilometres from the UK coast. The […]

  • 18 December 2012
    Wind Farm Update

    Forewind’s second stage of offshore wind development, Dogger Bank Teesside will be divided into two separate Development Consent Order (DCO) applications, each for two offshore wind projects. Dogger Bank Teesside will comprise four wind farms, which could have a total installed capacity of up to 4.8GW which means it would have the potential to generate […]

  • 26 November 2020
    Business & Finance, Wind Farm Update

    Equinor and SSE have reached financial close on the first two phases of the Dogger Bank wind farm project, representing in aggregate the largest offshore wind project financing to date globally. The 3.6 GW Dogger Bank offshore wind project is divided into three 1.2 GW phases, Dogger Bank A, Dogger Bank B, and Dogger Bank C. The […]

  • 19 February 2015

    HiDef Aerial Surveying Limited (HiDef) has congratulated Forewind on the consent for Dogger Bank Creyke Beck, the largest offshore wind consent award worldwide to date and one in which HiDef has played an important role. Dogger Bank Creyke Beck is the first stage of development in the Dogger Bank Zone and will have an installed […]

  • 22 September 2020
    Jobs & Recruitment

    Dogger Bank Wind Farm has announced 320 jobs to be created in the UK’s North East so far, with the recruitment set to start in early 2021. In May, Dogger Bank Wind Farm said Equinor, which will operate the 3.6 GW wind farm for its expected life of more than 25 years, will construct an […]

  • 22 September 2020
    Contracts & Tenders, Wind Farm Update

    Dogger Bank Wind Farm, a 50:50 joint venture between SSE Renewables and Equinor, has signed a contract with GE Renewable Energy for 190 wind turbines for the Dogger Bank A & B offshore wind project. Dogger Bank A & B will be the world’s first offshore wind farm to use GE’s Haliade-X 13 MW turbines, […]

  • 28 September 2015
    Operations & Maintenance

    The SeaRoc Group has completed a maintenance visit to the two Forewind meteorological masts, installed at the Dogger Bank offshore wind farm site in 2013. SeaRoc team of 9 personnel included an operations manager, rope access riggers and engineers to undertake inspections and scheduled maintenance on both Dogger Bank Met Mast East, located approximately 100 […]

  • 27 February 2020

    SSE Renewables and Equinor, the developers of the 3.6GW Dogger Bank Wind Farm, have changed the names of the project’s phases to recognise their link to the historic Doggerland area where the wind farm will be built. The location used to be home to a Mesolithic community who lived across the Doggerland area around 12,000 […]