Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Authorities›Canada-Made GE Vernova Blades to Be Removed from Vineyard Wind 1 Site
Authorities

January 21, 2025 · about 1 year ago

Canada-Made GE Vernova Blades to Be Removed from Vineyard Wind 1 Site

The US Bureau of Ocean Energy Management (BOEM) and the Bureau of Safety and Environmental Enforcement (BSEE) have completed the review and approved the revised Construction and Operations Plan (COP) for the Vineyard Wind 1 offshore wind farm. Last week, the federal government lifted the suspension

2 minutes read
  • LinkedIn
  • X
  • Email
Vineyard Wind 1 first power
Vineyard Wind first power; Photo Credit: Worldview Films

The US Bureau of Ocean Energy Management (BOEM) and the Bureau of Safety and Environmental Enforcement (BSEE) have completed the review and approved the revised Construction and Operations Plan (COP) for the Vineyard Wind 1 offshore wind farm .

Last week, the federal government lifted the suspension on Vineyard Wind’s installation of the remaining GE Vernova wind turbines.

The new COP details the root cause analysis (RCA) conducted by the wind turbine manufacturer regarding the blade failure that occurred in July 2024.

The RCA found that there was insufficient bonding at certain locations within the blade, which should have been detected at the manufacturing plant through inspection and quality control procedures. After reprocessing of the manufacturing data from the installed blades, additional blades with insufficient bonding were identified.

BSEE directed Vineyard Wind to remove all blades manufactured at GE Vernova’s facility in Gaspé, Canada. The COP addendum includes removal activities at 22 locations, and pending further BSEE review, potentially two additional locations where blades from other manufacturing plants were installed.

The 800 MW offshore wind farm will comprise 62 GE Vernova’s Haliade-X 13 MW wind turbines , each with a 220-metre rotor and 107-metre blades.

YOU MIGHT ALSO LIKE

The removal activities may be conducted by the jack-up currently on site southwest of Nantucket (the Sea Installer ) and/or a second jack-up vessel.

In its new plan, Vineyard Wind said it will employ additional mitigation associated with blade installation and power production. One of these measures includes visually inspecting each installed blade before commencing power production.

In addition, each turbine will have a fully functional monitoring system capable of detecting and immediately notifying the operator of potential blade anomalies while the turbine is producing power, according to the COP.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

AuthoritiesFixed-BottomPlanning & Permitting

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Greenpeace Threatens Legal Action Over Crown Estate Fees for Morgan Offshore Wind Farm
  2. 2Acta Marine Christens CSOV Chartered by Vestas
  3. 3New Owner to Continue Operations at German Offshore Wind Farm Previously Set for Decommissioning
  4. 4All Monopiles In at Nordlicht I Offshore Wind Farm

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free