Search results for: SeaMade

13951 results

A list of search results

  • 3 December 2018
    Business & Finance, Contracts & Tenders, Grid Connection, Wind Farm Update

    SeaMade NV has awarded the consortium of ENGIE Fabricom, Tractebel, Smulders and GeoSea an Engineering, Procurement, Construction and Installation (EPCI) contract for the two substations of the SeaMade offshore wind farm in Belgium.

  • 3 May 2019
    Business & Finance

    Dutch offshore foundations manufacturer Sif has begun work for the SeaMade offshore wind farm in Belgium, according to the company’s latest report. Sif is responsible for producing the monopiles for the 487MW project and, in a joint venture with Smulders, for the manufacture of transition pieces. The Dutch company said it plans to begin works […]

  • 6 September 2019
    Wind Farm Update

    DEME Group’s jack-up vessel Innovation has arrived at Sif’s Maasvlakte terminal in Rotterdam to load the first monopiles for the SeaMade offshore wind project in Belgium. DEME is in charge of installing the 58 foundations, as well as the turbines, inter-array cables, export cables and two offshore substations. Sif won a contract at the end of […]

  • 15 February 2019
    Contracts & Tenders, Wind Farm Update

    Belgian offshore wind developer SeaMade NV has selected Waves Group to provide Marine Warranty Surveyor services during the construction of the 487MW SeaMade offshore wind farm. Waves Group is currently providing MWS services for the installation of foundations, infield cables, wind turbines, export cables, and two offshore substations. Associated operations include loadouts, installations, and pulling in cables to both […]

  • 18 December 2019
    Grid Connection, Wind Farm Update

    DEME Group has completed the pull-in of two export cables of the SeaMade offshore wind project into Elia’s Offshore SwitchYard (OSY) platform.  DEME’s cable-laying vessel Living Stone picked up the export cables for the 487MW project from Hellenic Cables’ facility in Soussaki, Greece, in mid-November. SeaMade will have two offshore substations, which will collect the […]

  • 12 September 2019
    Wind Farm Update

    DEME Group’s jack-up vessel Innovation has installed the first foundation at the SeaMade offshore wind farm in Belgium. DEME is picking up the monopile foundations at Sif’s Maasvlakte terminal in Rotterdam and is in charge of installing all 58 pieces at the project site some 50km off the coast from Ostend. The company is also responsible for […]

  • 19 November 2019
    Contracts & Tenders, Grid Connection

    JECS Offshore Services has secured a contract to provide support to Hellenic Cables during termination works on the export cables at the SeaMade offshore wind farm in Belgium. JECS Offshore will design, supply and erect the scaffolding access platforms required for technicians to prepare and position the cables and carry out the terminations of the […]

  • 11 December 2018
    Business & Finance, Grid Connection, Wind Farm Update

    Eneco has concluded a long-term power purchase agreement (PPA) for the SeaMade offshore wind project in Belgium.

  • 17 December 2018
    Contracts & Tenders, Ports & Logistics, Wind Farm Update

    On 14 December, Siemens Gamesa and REBO (Renewable Energy Base Oostende) signed a contract for Belgian SeaMade offshore wind farm, which will feature 58 Siemens Gamesa offshore wind turbines. 

  • 7 January 2020
    Wind Farm Update

    DEME Group has completed the installation of 58 turbine foundations and two substation foundations at the SeaMade offshore wind project in Belgium. DEME’s jack-up vessel Innovation installed the last monopile foundation at the project site some 50km off the coast from Ostend on 2 January. According to the company, a new monopile gripper was deployed onboard […]

  • 3 December 2018
    Business & Finance, Wind Farm Update

    The 487MW SeaMade offshore wind farm in the Belgian North Sea has reached financial close.

  • 10 March 2020
    Grid Connection, Wind Farm Update

    The second offshore substation for the SeaMade wind farm has arrived in Vlissingen, the Netherlands, from where it will leave for installation off Belgium. The substation destined for the Seastar offshore wind concession completed its trip from Engie Fabricom’s construction yard in Hoboken, Belgium, to the Netherlands yesterday, Otary said. According to the company, the […]

  • 13 December 2018
    Business & Finance, Contracts & Tenders

    Dredging International has contracted Sif to produce the monopiles and, in joint venture with Smulders, the transition pieces for the SeaMade offshore wind farm in Belgium.

  • 5 June 2019
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Hartlepool-based JDR Cables has signed a contract with DEME Offshore to provide inter-array cables and accessories for the SeaMade offshore wind farm in the Belgian North Sea. JDR, part of the TFKable Group, will design, manufacture and deliver 78.1 kilometres of aluminium core inter-array cables and a range of cable accessories, including repair joints and connectors. […]

  • 20 March 2020
    Wind Farm Update

    Tekmar Energy Limited has completed the delivery of TekLink® cable protection systems to DEME Offshore for the SeaMade offshore wind farm in Belgium. SeaMade is a 487MW offshore wind farm currently under construction off the coast of Belgium and integrates two wind farm sites known as Mermaid and Seastar. Tekmar Energy was awarded a contract […]

  • 23 July 2019
    Operations & Maintenance, Vessels

    DEME Group’s jack-up vessel Innovation is undergoing a major maintenance and repair program at the Damen Verolme yard in Rotterdam, the Netherlands. According to DEME, the program is almost completed and saw the installation of two new leg sections on the offshore installation vessel. After the extensive dry dock, Innovation will set sail to the SeaMade offshore […]

  • 18 March 2020
    Grid Connection, Wind Farm Update

    The second SeaMade offshore substation topside has been installed in the Seastar concession area in the Belgian North Sea. The wind farm’s first substation was installed in the Mermaid concession area at the beginning of March. Each with a weight of 1,200 tonnes, the substations transform the wind energy that is produced to 225kV, which in […]

  • 5 March 2020
    Grid Connection, Wind Farm Update

    The first of two offshore substations for the SeaMade offshore wind farm has been installed at the project site in the Belgian North Sea. The 487MW SeaMade wind farm is a combination of the 235MW Mermaid and the 252MW Seastar offshore wind projects. The 1,200t topside, which has four decks and is 14m tall, has been installed […]

  • 3 March 2020
    Grid Connection, Wind Farm Update

    The first of two offshore substations for the SeaMade offshore wind farm has left Engie Fabricom’s construction yard in Hoboken and is on its way towards the project site in the Belgian North Sea. The 487MW SeaMade wind farm is a combination of the 235MW Mermaid and the 252MW Seastar offshore wind projects. The 1,200t topside, […]

  • 28 February 2020
    Grid Connection, Wind Farm Update

    The first of the two offshore substation topsides to be installed on the SeaMade wind farm in the Belgian North Sea has been loaded onto a barge at ENGIE Fabricom’s yard in Hoboken, Belgium. The 487MW SeaMade is a combination of two offshore wind projects previously known as Mermaid and Seastar. The 1,200-tonne topside will now be […]

  • 30 January 2019
    Business & Finance, Operations & Maintenance

    Siemens Gamesa has placed an order with Seasight Davits for 58 davit cranes for the SeaMade offshore wind farm in Belgium. The cranes will be manufactured by Seasight Davits’ parent company Hvide Sande Shipyard, Steel and Service and will have an outreach of 3.2m and a one-ton lifting capacity. According to the Danish davit crane supplier, the […]

  • 26 March 2020
    Wind Farm Update

    The first two turbine towers destined for the SeaMade offshore wind project have arrived at the Port of Ostend, Belgium. According to Otary, the first six tower parts arrived in Belgium on 24 March from the port of Avileson in Spain onboard the special purpose vessel Rotra Vente. Over the coming months, Rotra Vente and […]

  • 13 March 2020
    Grid Connection, Wind Farm Update

    Scaldis Salvage & Marine Contractors is currently preparing for the installation of the second offshore substation at the SeaMade wind farm in Belgium. The 487MW SeaMade wind farm is a combination of the 235MW Mermaid and the 252MW Seastar offshore wind projects. This second topside, which recently arrived in Vlissingen, the Netherlands, will be installed at the Seastar […]

  • 15 November 2019
    Grid Connection, Wind Farm Update

    DEME’s cable laying vessel Living Stone has departed Greece carrying the export cables for the 487MW SeaMade offshore wind farm in the Belgian North Sea. Living Stone loaded the export cables with a combined length of around 28 kilometres at Hellenic Cables’ facility in Soussaki. The vessel is currently en route to Vlissingen, the Netherlands. […]

  • 18 October 2019
    Wind Farm Update

    The first offshore substation transition piece and J-tube cage for the SeaMade offshore wind farm are on their way from Belgium to the Sif terminal in Rotterdam, the Netherlands, DEME Group said. The transition piece was loaded out at Smulders’ yard in Hoboken. Together with the foundation, which is already in Rotterdam, the transition piece and […]

  • 3 December 2018
    Business & Finance, Contracts & Tenders, Operations & Maintenance, Wind Farm Update

    Siemens Gamesa has received the order for the 487MW SeaMade offshore wind power project in Belgium from Seamade NV.