151 results
A list of search results
-
Business & Finance, Contracts & Tenders, Wind Farm Update
TotalEnergies and Corio Generation have signed a joint venture partnership to develop the Formosa 3 offshore wind farms in Taiwan. Under this agreement, Corio will remain the majority shareholder and lead developer with 50 per cent plus ten shares overall in the project. The announcement comes after Taiwan’s Bureau of Energy confirmed in late December […]
-
Business & Finance, Wind Farm Update
Ørsted expects to reach a final investment decision (FID) on its next offshore wind project in Taiwan, the 920 MW Greater Changhua 2b & 4, during this year, as planned. This will move the project into the construction phase and set it on the path towards commissioning in 2025. Ørsted was awarded rights to build […]
-
Two Siemens 4MW turbines were installed off Taiwanese coast in October, representing the completion of the first phase of the Formosa 1 offshore wind farm, which is set to comprise 32 turbines by 2019. Both the foundations and turbines were installed by using the vessel M/V TORBEN, formerly known as Friedrich Ernestine, owned by RWE Offshore […]
-
Taiwan’s first two offshore wind turbines, set up as the first phase of the Formosa 1 offshore wind farm, are reportedly set to enter operations in May.
-
Authorities, Contracts & Tenders, Wind Farm Update
Taiwan’s Ministry of Economic Affairs (MOEA) has selected ten offshore wind projects in the first auction of the Round 3 Zonal Development Phase. The ten projects are proposed by: Copenhagen Infrastructure Partners (CIP); Corio Generation and JERA; Northland Power; Synera Renewable Energy (SRE; formerly known as Swancor Renewable Energy); Taiya Renewable Energy and EDF Renewables; and […]
-
Business & Finance, Contracts & Tenders, Operations & Maintenance
CWind Taiwan has been awarded a balance of plant (BOP) contract for the Formosa 1 offshore wind farm. The company is providing inspection and maintenance services to the 22 turbines at Formosa 1 Phase 1 and Formosa 1 Phase 2 sites, including internal and external inspections and painting. Under the contract, signed with Formosa 1 […]
-
Business & Finance, Grid Connection, Technology, Wind Farm Update
UK-based Tekmar Energy has supplied its TEKLINK Cable Protection System (CPS) to protect the underwater power cables as they enter the wind turbine foundations on the Formosa 1 Phase 1 project, the first offshore wind farm in Taiwan.
-
Ørsted and project partners have held an inauguration ceremony for the Formosa 1 Phase 2 offshore wind project in Taiwan. Formosa 1 Phase 2 is an extension of the existing two-turbine Formosa 1 Phase 1 project, which was officially commissioned in April 2017. The 120MW project comprises 20 Siemens Gamesa 6MW turbines installed approximately 2 […]
-
The Formosa 1 Phase 2 project has entered the construction phase following a groundbreaking ceremony held in Taiwan’s Miaoli County over the past weekend. Formosa 1 Phase 2 will comprise 20 Siemens Gamesa 6MW turbines installed on monopile foundations some 6km off the west coast of the Miaoli district in the Taiwan Strait. The project is owned by Formosa I Wind […]
-
Jack-up vessel Seajacks Zaratan has installed the first of the 20 Siemens Gamesa 6MW wind turbines on the 120MW Formosa 1 Phase 2 wind farm in Taiwan. The project is located around six kilometers off the west coast of the Miaoli district in the Taiwan Strait, with water depths ranging between 15 and 30m. Seajacks […]
-
Contracts & Tenders, Wind Farm Update
Jan De Nul has won a contract for the design, procurement and installation of the wind turbine foundations for the 120MW Formosa 1 Phase 2 wind farm offshore Taiwan.
-
Penguin International Ltd. has delivered the service accommodation and transfer vessel (SATV) for the Formosa 1 offshore wind project to a Taiwanese operator. The 35m SATV Ventus Formosa was built by the Penguin Shipyard in Singapore and designed by the UK BMT. According to Penguin, the prototype vessel is purpose-built for 12 technicians to live […]
-
The Formosa 1 offshore wind project in Taiwan started commercial operation on 27 December, according to JERA. The 128MW wind farm consists of the 8MW Formosa 1 Phase 1, inaugurated in May 2017, and the 120MW Formosa 1 Phase 2 which was officially commissioned in November. Formosa 1 comprises two Siemens Gamesa 4MW turbines from the first phase […]
-
SeaPlanner, SeaRoc Group’s marine management system, has been selected to support the operations and maintenance phase of the Formosa 1 offshore wind farm in Taiwan. Under the 10-year contract, SeaPlanner will be deployed by the O&M team to coordinate all personnel and marine logistics for the 128MW wind farm. SeaPlanner also supported the construction of […]
-
All 20 Siemens Gamesa 6MW turbines have been installed at the Formosa 1 Phase 2 offshore wind project in Taiwan. To remind, jack-up vessel Seajacks Zaratan installed the first turbine at the project site 6km off the west coast of the Miaoli district in the Taiwan Strait in July. Prior to commercial operation, each turbine goes through […]
-
Ørsted has posted a photo showing the first wind turbine components destined for the Formosa 1 Phase 2 offshore wind farm lined up at the Taichung Port in Taiwan. The first 75m long blades, 378t nacelles and 37m long tower sections began their journey to Taiwan from Aalborg, Denmark, and Cuxhaven, Germany, on board three vessels. Formosa 1 Phase 2 will […]
-
UK-based Tekmar Energy Limited has secured two contracts within Taiwan for the supply of its TEKLINK® cable protection system and associated accessories. The combined value of the two contracts is circa GBP 4 million. Further details on the contracts will be provided in due course, Tekmar said. The two contract awards have come in addition to Tekmar’s earlier […]
-
Grid Connection, Wind Farm Update
Jan De Nul’s cable-laying vessel Willem de Vlamingh has completed the installation of the export cables on the Formosa 1 Phase 2 offshore wind farm in Taiwan. Under the EPCI contract, Jan De Nul installed 17 inter-array and three export cables at the 120MW offshore wind farm. According to the company, at the beach landing, the […]
-
Vessels, Wind Farm Update
The self-propelled jack-up Seajacks Zaratan is on its way to Vlissingen in the Netherlands to undergo mobilisation in preparation for the Formosa 1 Phase 2 offshore wind project in Taiwan. Seajacks Zaratan will install all 20 Siemens Gamesa SWT-6.0-154 wind turbines on the 120MW wind farm in the Taiwan Strait. This is the first renewables contract for […]
-
The self-propelled jack-up Seajacks Zaratan has arrived in Taichung, Taiwan, where the vessel will transport and install wind turbines on the 120MW Formosa 1 Phase 2 offshore wind farm. Zaratan will install all 20 Siemens Gamesa SWT-6.0-154 turbines on the wind farm in the Taiwan Strait in what is the first renewables contract for Seajacks outside Europe. The turbine components have already […]
-
Operations & Maintenance, Vessels
The construction of a Service Accommodation Transfer Vessel (SATV) and a Crew Transfer Vessel (CTV) which will service the Formosa 1 wind farm in Taiwan is well underway, BMT, the designer of the vessels, said. BMT has partnered with the Singapore-based Penguin Shipyard International (PSI) for the 36m SATV and the 26m CTV. The keel […]
-
Correll Services has completed the subsea and land cable termination and testing works at the Formosa 1 Phase 2 offshore wind farm in Taiwan. Correll Services was in charge of project documentation, export cable (HV & FO) jointing at the TJB and OSS, array cable terminations (HV & FO) on 22 assets, and post-installation testing from […]
-
Contracts & Tenders, Operations & Maintenance
CWind Taiwan is set to return to Formosa 1 offshore wind farm this spring to deliver Inspection, Maintenance and Repair services. The company will deploy its technician team and a crew transfer vessel (CTV) to carry out the work on 22 of the Taiwanese wind farm’s turbines. Formosa 1 started commercial operation on 27 December […]
-
Operations & Maintenance, Vessels
Siemens Gamesa has inaugurated the world’s first Service Accommodation Transfer Vessel (SATV) in Taiwan. The 35-metre Ventus Formosa will operate from Taichung. The vessel will support Siemens Gamesa’s full service agreement for the Formosa 1 offshore wind project. Penguin International built the SATV at its shipyard in Singapore and delivered it at the beginning of […]
-
Ventus Marine has taken delivery of crew transfer vessel (CTV) Ventus Lugang which will service the Formosa 1 offshore wind project in Taiwan. Ventus Lugang was delivered on 1 August at the Port of Kaohsiung and will join its sisters CTV Ventus Beigang and service accommodation transfer vessel (SATV) Ventus Formosa as the primary fleet […]
-
Operations & Maintenance, Vessels
Ventus Marine’s service accommodation transfer vessel (SATV) Ventus Formosa has begun its charter on the Formosa 1 offshore wind project in Taiwan. The joint venture of PSA Marine and its Taiwanese partner Ta Tong Marine Group took delivery of the 36-meter purpose-built SATV earlier this year. Ventus Formosa is in charge of providing operations and […]