  • 20 December 2016
    Wind Farm Update

    Two Siemens 4MW turbines were installed off Taiwanese coast in October, representing the completion of the first phase of the Formosa 1 offshore wind farm, which is set to comprise 32 turbines by 2019.  Both the foundations and turbines were installed by using the vessel M/V TORBEN, formerly known as Friedrich Ernestine, owned by RWE Offshore […]

  • 21 April 2017
    Wind Farm Update

    Taiwan’s first two offshore wind turbines, set up as the first phase of the Formosa 1 offshore wind farm, are reportedly set to enter operations in May.

  • 20 May 2019
    Wind Farm Update

    The Formosa 1 Phase 2 project has entered the construction phase following a groundbreaking ceremony held in Taiwan’s Miaoli County over the past weekend. Formosa 1 Phase 2 will comprise 20 Siemens Gamesa 6MW turbines installed on monopile foundations some 6km off the west coast of the Miaoli district in the Taiwan Strait. The project is owned by Formosa I Wind […]

  • 9 May 2017
    Business & Finance, Grid Connection, Technology, Wind Farm Update

    UK-based Tekmar Energy has supplied its TEKLINK Cable Protection System (CPS) to protect the underwater power cables as they enter the wind turbine foundations on the Formosa 1 Phase 1 project, the first offshore wind farm in Taiwan.

  • 7 January 2020
    Wind Farm Update

    The Formosa 1 offshore wind project in Taiwan started commercial operation on 27 December, according to JERA. The 128MW wind farm consists of the 8MW Formosa 1 Phase 1, inaugurated in May 2017, and the 120MW Formosa 1 Phase 2 which was officially commissioned in November. Formosa 1 comprises two Siemens Gamesa 4MW turbines from the first phase […]

  • 12 November 2019
    Wind Farm Update

    Ørsted and project partners have held an inauguration ceremony for the Formosa 1 Phase 2 offshore wind project in Taiwan. Formosa 1 Phase 2 is an extension of the existing two-turbine Formosa 1 Phase 1 project, which was officially commissioned in April 2017. The 120MW project comprises 20 Siemens Gamesa 6MW turbines installed approximately 2 […]

  • 9 October 2019
    Wind Farm Update

    All 20 Siemens Gamesa 6MW turbines have been installed at the Formosa 1 Phase 2 offshore wind project in Taiwan. To remind, jack-up vessel Seajacks Zaratan installed the first turbine at the project site 6km off the west coast of the Miaoli district in the Taiwan Strait in July. Prior to commercial operation, each turbine goes through […]

  • 25 July 2019
    Wind Farm Update

    Jack-up vessel Seajacks Zaratan has installed the first of the 20 Siemens Gamesa 6MW wind turbines on the 120MW Formosa 1 Phase 2 wind farm in Taiwan. The project is located around six kilometers off the west coast of the Miaoli district in the Taiwan Strait, with water depths ranging between 15 and 30m. Seajacks […]

  • 17 April 2019
    Wind Farm Update

    Ørsted has posted a photo showing the first wind turbine components destined for the Formosa 1 Phase 2 offshore wind farm lined up at the Taichung Port in Taiwan. The first 75m long blades, 378t nacelles and 37m long tower sections began their journey to Taiwan from Aalborg, Denmark, and Cuxhaven, Germany, on board three vessels. Formosa 1 Phase 2 will […]

  • 23 April 2020
    Operations & Maintenance, Vessels

    Siemens Gamesa has inaugurated the world’s first Service Accommodation Transfer Vessel (SATV) in Taiwan. The 35-metre Ventus Formosa will operate from Taichung. The vessel will support Siemens Gamesa’s full service agreement for the Formosa 1 offshore wind project. Penguin International built the SATV at its shipyard in Singapore and delivered it at the beginning of […]

  • 3 March 2020
    Vessels

    Penguin International Ltd. has delivered the service accommodation and transfer vessel (SATV) for the Formosa 1 offshore wind project to a Taiwanese operator. The 35m SATV Ventus Formosa was built by the Penguin Shipyard in Singapore and designed by the UK BMT. According to Penguin, the prototype vessel is purpose-built for 12 technicians to live […]

  • 15 April 2019
    Ports & Logistics, Wind Farm Update

    DHL Industrial Projects has delivered first wind turbine components for the Formosa 1 Phase 2 offshore wind farm to the Taichung Port in Taiwan. The first three vessels have been loaded in Aalborg, Denmark, Cuxhaven, Germany, and Phu My, Vietnam. The vessels are carrying 75-metre blades, 378-tonne nacelles, and tower sections up to 37 metres long. The two vessels carrying blades […]

  • 29 November 2019
    Business & Finance

    SeaPlanner, SeaRoc Group’s marine management system, has been selected to support the operations and maintenance phase of the Formosa 1 offshore wind farm in Taiwan. Under the 10-year contract, SeaPlanner will be deployed by the O&M team to coordinate all personnel and marine logistics for the 128MW wind farm. SeaPlanner also supported the construction of […]

  • 17 May 2018
    Contracts & Tenders, Wind Farm Update

    Jan De Nul has won a contract for the design, procurement and installation of the wind turbine foundations for the 120MW Formosa 1 Phase 2 wind farm offshore Taiwan.

  • 20 August 2019
    Contracts & Tenders

    UK-based Tekmar Energy Limited has secured two contracts within Taiwan for the supply of its TEKLINK® cable protection system and associated accessories. The combined value of the two contracts is circa GBP 4 million. Further details on the contracts will be provided in due course, Tekmar said. The two contract awards have come in addition to Tekmar’s earlier […]

  • 8 August 2019
    Grid Connection, Wind Farm Update

    Jan De Nul’s cable-laying vessel Willem de Vlamingh has completed the installation of the export cables on the Formosa 1 Phase 2 offshore wind farm in Taiwan. Under the EPCI contract, Jan De Nul installed 17 inter-array and three export cables at the 120MW offshore wind farm. According to the company, at the beach landing, the […]

  • 13 August 2019
    Wind Farm Update

    Jumbo has completed the transport of all transition pieces for the Formosa 1 Phase 2 offshore wind farm from Thailand to the Taichung Port in Taiwan. Jumbo Kinetic transported the 20 transition pieces in three shipments from CUEL Limited’s yard in Laem Chabang in Thailand to the Taichung Port. Additionally, Jumbo coordinated the fabrication of 12 grillages which act […]

  • 15 October 2019
    Grid Connection

    Correll Services has completed the subsea and land cable termination and testing works at the Formosa 1 Phase 2 offshore wind farm in Taiwan. Correll Services was in charge of project documentation, export cable (HV & FO) jointing at the TJB and OSS, array cable terminations (HV & FO) on 22 assets, and post-installation testing from […]

  • 13 August 2020
    Vessels

    Ventus Marine has taken delivery of crew transfer vessel (CTV) Ventus Lugang which will service the Formosa 1 offshore wind project in Taiwan. Ventus Lugang was delivered on 1 August at the Port of Kaohsiung and will join its sisters CTV Ventus Beigang and service accommodation transfer vessel (SATV) Ventus Formosa as the primary fleet […]

  • 30 January 2019
    Vessels, Wind Farm Update

    The self-propelled jack-up Seajacks Zaratan is on its way to Vlissingen in the Netherlands to undergo mobilisation in preparation for the Formosa 1 Phase 2 offshore wind project in Taiwan. Seajacks Zaratan will install all 20 Siemens Gamesa SWT-6.0-154 wind turbines on the 120MW wind farm in the Taiwan Strait. This is the first renewables contract for […]

  • 20 May 2019
    Operations & Maintenance, Vessels

    The construction of a Service Accommodation Transfer Vessel (SATV) and a Crew Transfer Vessel (CTV) which will service the Formosa 1 wind farm in Taiwan is well underway, BMT, the designer of the vessels, said. BMT has partnered with the Singapore-based Penguin Shipyard International (PSI) for the 36m SATV and the 26m CTV. The keel […]

  • 13 May 2019
    Vessels

    The self-propelled jack-up Seajacks Zaratan has arrived in Taichung, Taiwan, where the vessel will transport and install wind turbines on the 120MW Formosa 1 Phase 2 offshore wind farm. Zaratan will install all 20 Siemens Gamesa SWT-6.0-154 turbines on the wind farm in the Taiwan Strait in what is the first renewables contract for Seajacks outside Europe. The turbine components have already […]

  • 18 September 2019
    Grid Connection

    First Subsea has delivered beach landing cable protection systems for three export cables at the Formosa 1 Phase 2 offshore wind farm in Taiwan. First Subsea secured a contract in February for the three 250m long systems, which it delivered to Jan De Nul at the end of March. According to the Lancaster-based company, the protection systems were designed […]

  • 28 August 2019
    Wind Farm Update

    UK-based Specialist Marine Consultants (SMC) has been awarded a contract to provide marine coordination services to Siemens Gamesa across the Formosa 1 Phase 2 offshore wind farm in Taiwan. The Formosa 1 Phase 2 project will comprise 20 6MW Siemens Gamesa wind turbines and is an extension to the already operating 8MW Formosa 1 Phase […]

  • 6 March 2019
    Vessels, Wind Farm Update

    SMC has completed a full inspection of Seajacks’ self-propelled jack-up vessel, Zaratan, ahead of its deployment to Taiwan in the coming weeks. Seajacks Zaratan will be utilised as an installation vessel in the coming months for construction of the 120MW Formosa 1 Phase 2 offshore wind farm. The installation works are scheduled to start in the second […]

  • 5 December 2018
    Contracts & Tenders, Wind Farm Update

    Palfinger Marine has signed a contract with Siemens Gamesa for the delivery of 20 PF9000-2.9 fixed boom cranes to the Formosa 1 Phase 2 offshore wind farm in Taiwan.