Search results for: Formosa 1 Phase 1

153 results

A list of search results

  • 15 April 2019
    Ports & Logistics, Wind Farm Update

    DHL Industrial Projects has delivered first wind turbine components for the Formosa 1 Phase 2 offshore wind farm to the Taichung Port in Taiwan. The first three vessels have been loaded in Aalborg, Denmark, Cuxhaven, Germany, and Phu My, Vietnam. The vessels are carrying 75-metre blades, 378-tonne nacelles, and tower sections up to 37 metres long. The two vessels carrying blades […]

  • 18 September 2019
    Grid Connection

    First Subsea has delivered beach landing cable protection systems for three export cables at the Formosa 1 Phase 2 offshore wind farm in Taiwan. First Subsea secured a contract in February for the three 250m long systems, which it delivered to Jan De Nul at the end of March. According to the Lancaster-based company, the protection systems were designed […]

  • 28 August 2019
    Wind Farm Update

    UK-based Specialist Marine Consultants (SMC) has been awarded a contract to provide marine coordination services to Siemens Gamesa across the Formosa 1 Phase 2 offshore wind farm in Taiwan. The Formosa 1 Phase 2 project will comprise 20 6MW Siemens Gamesa wind turbines and is an extension to the already operating 8MW Formosa 1 Phase […]

  • 5 December 2018
    Contracts & Tenders, Wind Farm Update

    Palfinger Marine has signed a contract with Siemens Gamesa for the delivery of 20 PF9000-2.9 fixed boom cranes to the Formosa 1 Phase 2 offshore wind farm in Taiwan.

  • 16 April 2020
    Operations & Maintenance, Vessels

    Ventus Marine’s service accommodation transfer vessel (SATV) Ventus Formosa has begun its charter on the Formosa 1 offshore wind project in Taiwan. The joint venture of PSA Marine and its Taiwanese partner Ta Tong Marine Group took delivery of the 36-meter purpose-built SATV earlier this year. Ventus Formosa is in charge of providing operations and […]

  • 4 February 2019
    Authorities, Wind Farm Update

    The European Commission has approved, under the EU Merger Regulation, the proposed acquisition of joint control over Formosa I offshore wind project in Taiwan by Macquarie, Ørsted, Swancor, and Japan’s utility JERA. Formosa 1 is currently a joint venture between Ørsted (35% ownership), Taiwanese developer Swancor Renewable (15%), and Macquarie Capital (50%). As reported, JERA agreed […]

  • 27 November 2019
    Vessels

    Singapore-based PSA Marine and its Taiwanese partner, Ta Tong Marine, have formed a joint venture company, Ventus Marine, to service a long-term contract awarded by Siemens Gamesa for the Formosa 1 offshore wind farm in Taiwan. The charter commenced on 1 November and is served by a 26-metre, 12-pax CTV Ventus Beigang. Ventus Beigang is […]

  • 6 March 2019
    Vessels, Wind Farm Update

    SMC has completed a full inspection of Seajacks’ self-propelled jack-up vessel, Zaratan, ahead of its deployment to Taiwan in the coming weeks. Seajacks Zaratan will be utilised as an installation vessel in the coming months for construction of the 120MW Formosa 1 Phase 2 offshore wind farm. The installation works are scheduled to start in the second […]

  • 17 January 2020
    Grid Connection

    EDS HV has completed electrical safety commissioning and consultancy work at the Formosa 1 Phase 2 offshore wind project in Taiwan. EDS HV stated it had provided skills to the local people enabling them to safely and efficiently run their high-voltage network. The safety rules were adapted and translated from English to Mandarin, before being […]

  • 9 April 2019
    Wind Farm Update

    All 20 foundation monopiles built for the Formosa 1 Phase 2 have left the EEW SPC yard in Germany onboard two heavy load transport vessels and are en route to Taichung port in Taiwan, Jan De Nul said. Now that these components for the offshore construction are mobilized, the actual installation operations on site can be kicked […]

  • 24 April 2019
    Business & Finance

    Danish engineering consulting group COWI has opened a branch office in Taipei to accommodate ongoing and recently won offshore wind projects in Taiwan, and to grow its wind business in the region. “The appetite for wind energy and more specifically offshore wind farms has been increasing exponentially especially in East and South East Asia,” Jan Rønberg, COWI’s Senior […]

  • 28 August 2020
    Business & Finance

    By 2035, Taiwan will become the largest offshore wind market in the Asia-Pacific (APAC) region after China, with 15 GW of capacity estimated to be added by that time, according to GlobalData. “Taiwan offshore wind market is poised to witness multifold expansion to reduce its reliance on fossil fuel generation and build a cleaner sustainable […]

  • 30 January 2018
    Contracts & Tenders

    Nine developers looking to build offshore wind farms in Taiwan have qualified for offshore environmental permits. These developers, offering 10.5GW of offshore wind capacity in total, will now compete for 5.5GW of offshore wind contracts, 3.5GW to be selected for the feed-in-tariff (FIT) and the rest to be awarded at an auction in May.

  • 3 April 2018
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Siemens Gamesa Renewable Energy (SGRE) has been contracted to supply an additional 120MW of capacity for the Formosa 1 Phase 2 offshore wind farm in Taiwan, with the installation of the 20 SWT-6.0-154 wind turbines scheduled to start in 2019.

  • 24 June 2019
    Wind Farm Update

    The installation of foundations has kicked off at the Formosa 1 Phase 2 offshore wind project in Taiwan. The installation began in early June, a spokesperson from COWI, who designed all the steelwork for the 20 monopiles and transition pieces, told Offshore WIND. Seaway Yudin is installing the foundations, which comprise monopiles produced by Germany’s EEW SPC and transition pieces manufactured by […]

  • 14 August 2019
    Grid Connection

    Tekmar Energy has secured a contract with JDR Cables to provide its cable protection system (CPS) for the Formosa 1 Phase 2 offshore wind farm in Taiwan. Tekmar will supply approximately 60 of its TekLink Mechanical Latch CPS for all of the project’s inter-array and export cables, as well as 60 hang off clamps which hold the […]

  • 22 March 2019
    Vessels, Wind Farm Update

    Seajacks’ self-propelled jack-up vessel Zaratan has departed for Taiwan ready to begin installation of the Formosa 1 Phase 2 offshore wind project. Zaratan will install all 20 Siemens Gamesa SWT-6.0-154 turbines on the 120MW wind farm in the Taiwan Strait in what is the first renewables contract for Seajacks outside Europe. The project is located around six kilometers off […]

  • 9 September 2019
    Wind Farm Update

    The Formosa 1 Phase 2 offshore wind project in Taiwan has generated its first power. According to Ørsted, 10 out of 20 Siemens Gamesa 6MW turbines have been installed at the project site, while six units began generating power. Prior to commercial operation, each turbine goes through a power generation test which takes 10 to 14 days […]

  • 29 October 2019
    Wind Farm Update

    Taiwan’s Formosa 2 offshore wind farm has reached financial close, Macquarie’s Green Investment Group (GIG) said. Formosa 2 has been jointly developed by Macquarie Capital (75%) and Swancor Renewable Energy (25%). GIG will now play a role in delivering the project through its construction phase. The 376MW offshore wind project located off the coast of Miaoli […]

  • 19 February 2019
    Operations & Maintenance, Wind Farm Update

    Siemens Gamesa has started producing the blades for the Formosa 1 Phase 2 offshore wind project in Taiwan. The company said the blades were cast at its Aalborg factory in Denmark using Swancor resin and hardener. Siemens Gamesa won the contract to supply 20 SWT-6.0-154 turbines, which will produce a capacity of 120MW, for the project in April last […]

  • 26 April 2018
    Business & Finance, Wind Farm Update

    Ørsted has taken final investment decision (FID) for the second phase of the Formosa 1 offshore wind farm in Chunan Town, Miaoli County, on Taiwan’s North-Western coast.

  • 29 October 2019
    Wind Farm Update

    Jan De Nul has completed the EPCI scope for foundations, power cables, and scour protection on the Formosa 1 (Phase 2) offshore wind farm in Taiwan. Jan De Nul engineered, procured, and installed twenty offshore wind turbine foundations consisting of a monopile and transition piece with a grouted connection. Around the monopile foundations, 56,000 tonnes […]

  • 16 January 2019
    Business & Finance, Contracts & Tenders, Operations & Maintenance

    FairWind has signed a Letter of Intent with Siemens Gamesa to collaborate on turbine pre-assembly for the Formosa 1 Phase 2 offshore wind project in Taiwan. Under the agreement, FairWind will hire and train Taiwanese technicians to prepare them for the pre-assembly operations, which are scheduled to begin in the spring this year. The training […]

  • 13 May 2019
    Ports & Logistics, Vessels, Wind Farm Update

    Transition pieces and monopiles for the Formosa 1 Phase 2 offshore wind farm have started arriving at the Taichung Port in Taiwan. And so have the vessels that will install the 20 monopile foundations and the wind turbines at the site in the Taiwan Strait, Ørsted, one of the owners of the 120MW wind farm, said. Seaway […]

  • 30 January 2020
    Operations & Maintenance

    Renewable Strategy Limited (RSL) has deployed computerized maintenance management software on the Formosa 1 offshore wind project in Taiwan.

  • 26 June 2018
    Contracts & Tenders

    EEW SPC and Jan de Nul have signed a contract for the production of 20 monopile foundations for the Formosa 1 Phase 2 offshore wind farm in Taiwan.