Search results for: Formosa 1 Phase 1

146 results

A list of search results

  • 17 April 2019
    Wind Farm Update

    Ørsted has posted a photo showing the first wind turbine components destined for the Formosa 1 Phase 2 offshore wind farm lined up at the Taichung Port in Taiwan. The first 75m long blades, 378t nacelles and 37m long tower sections began their journey to Taiwan from Aalborg, Denmark, and Cuxhaven, Germany, on board three vessels. Formosa 1 Phase 2 will […]

  • 15 April 2019
    Ports & Logistics, Wind Farm Update

    DHL Industrial Projects has delivered first wind turbine components for the Formosa 1 Phase 2 offshore wind farm to the Taichung Port in Taiwan. The first three vessels have been loaded in Aalborg, Denmark, Cuxhaven, Germany, and Phu My, Vietnam. The vessels are carrying 75-metre blades, 378-tonne nacelles, and tower sections up to 37 metres long. The two vessels carrying blades […]

  • 9 April 2019
    Wind Farm Update

    All 20 foundation monopiles built for the Formosa 1 Phase 2 have left the EEW SPC yard in Germany onboard two heavy load transport vessels and are en route to Taichung port in Taiwan, Jan De Nul said. Now that these components for the offshore construction are mobilized, the actual installation operations on site can be kicked […]

  • 22 February 2019
    Contracts & Tenders, Grid Connection, Wind Farm Update

    UK-based Correll Services Ltd has secured a contract to provide subsea and land cable termination and testing works on the Formosa 1 Phase 2 offshore wind farm in Taiwan. The contract has been awarded by Formosa 1 project turnkey contractor Jan De Nul Group. Correll Services – a specialist in high voltage, low voltage and fibre […]

  • 4 February 2019
    Authorities, Wind Farm Update

    The European Commission has approved, under the EU Merger Regulation, the proposed acquisition of joint control over Formosa I offshore wind project in Taiwan by Macquarie, Ørsted, Swancor, and Japan’s utility JERA. Formosa 1 is currently a joint venture between Ørsted (35% ownership), Taiwanese developer Swancor Renewable (15%), and Macquarie Capital (50%). As reported, JERA agreed […]

  • 1 February 2019
    Jobs & Recruitment

    FairWind is sending the first group of prospective Taiwanese wind turbine technicians to Europe this month to train at European Wind Academy ahead of their deployment on the Formosa 1 Phase 2 offshore wind power project. Under the terms of a Letter of Intent signed between FairWind and Siemens Gamesa to collaborate on pre-assembly work for the […]

  • 28 December 2018
    Business & Finance, Wind Farm Update

    Japanese utility JERA has entered into an agreement with Macquarie Capital and Swancor to acquire a combined 32.5% equity interest in the Formosa 1 offshore wind power project located off the north-western coast of Taiwan.

  • 12 December 2018
    Authorities, Business & Finance, Wind Farm Update

    Swancor has signed a power purchase agreement (PPA) with Taipower for the Formosa 2 offshore wind farm.

  • 5 December 2018
    Contracts & Tenders, Wind Farm Update

    Palfinger Marine has signed a contract with Siemens Gamesa for the delivery of 20 PF9000-2.9 fixed boom cranes to the Formosa 1 Phase 2 offshore wind farm in Taiwan.

  • 6 November 2018
    Business & Finance

    Siemens Gamesa Renewable Energy (SGRE) reported an offshore wind turbine order intake totalling 2,272MW in its fiscal year 2018 – 31% more than in FY 2017 – with a total value of approx. EUR 2.78 billion.

  • 11 October 2018
    Business & Finance, Vessels

    Njord Offshore Ltd has secured a contract to manage a new purpose-built service accommodation and transfer vessel (SATV) for Siemens Gamesa at the Formosa 1 offshore wind project in Taiwan.

  • 20 August 2018
    Contracts & Tenders, Wind Farm Update

    Management, engineering and development consultancy Mott MacDonald is reviewing the design of the anchor bolt system on the second phase of the 128MW Formosa I offshore wind farm in north-west Taiwan.

  • 27 July 2018
    Business & Finance

    Siemens Gamesa’s offshore wind order intake reached a peak in the third quarter of the fiscal year 2018 with 1,368MW in firm orders, due to agreements to supply 165 turbines for Hornsea Project Two and 120MW for the Formosa I Phase II offshore wind project.

  • 20 June 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    UK-based JDR Cable Systems has been selected by Jan De Nul Group to manufacture and supply inter-array, export and land cables for Taiwan’s Formosa 1 development.

  • 8 June 2018
    Business & Finance, Wind Farm Update

    Formosa 1, Taiwan’s first offshore wind farm, has reached financial close.

  • 26 April 2018
    Business & Finance, Wind Farm Update

    Ørsted has taken final investment decision (FID) for the second phase of the Formosa 1 offshore wind farm in Chunan Town, Miaoli County, on Taiwan’s North-Western coast.

  • 27 March 2018
    Contracts & Tenders

    Siemens Gamesa’s Offshore CEO Andreas Nauen and Swancor’s Chairman Robert Tsai have signed two agreements in Taiwan: the first one focused on bringing additional local content to Taiwan’s offshore wind industry, followed by a memorandum of understanding (MoU) on the Formosa II offshore wind project. 

  • 12 March 2018
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Taiwan-based offshore wind developer Swancor Holding plans to secure the funds necessary for the full development of the Formosa I offshore wind projects through financing deals with banks in the second quarter of 2018, according to local media.

  • 2 January 2018

    The Offshore WIND editorial team brings you a list of what, in our opinion, were the most significant developments in the offshore wind industry in 2017. Germany Accepts First Subsidy-Free Offshore Wind Auction Bid Germany’s Bundesnetzagentur has selected three offshore wind projects by DONG Energy and one project by EnBW in the first auction for […]

  • 1 June 2017
    Authorities, Business & Finance, Environment, Grid Connection, Operations & Maintenance, R&D, Technology, Training & Education, Vessels, Wind Farm Update

    Four Scottish Offshore Wind Projects Back in Business The Inner House of the Court of Session, Scotland’s supreme civil court, has overturned the ruling which halted further development of four wind projects with a total capacity of 2,284MW in the Firth of Forth and Firth of Tay. France Pre-Selects 10 Dunkerque Offshore Wind Bidders France’s […]

  • 9 May 2017
    Business & Finance, Grid Connection, Technology, Wind Farm Update

    UK-based Tekmar Energy has supplied its TEKLINK Cable Protection System (CPS) to protect the underwater power cables as they enter the wind turbine foundations on the Formosa 1 Phase 1 project, the first offshore wind farm in Taiwan.

  • 2 March 2017
    Authorities, Business & Finance, Wind Farm Update

    The European Commission has approved, under the EU Merger Regulation, the proposed acquisition of joint control over Formosa 1 International Investment of Taiwan by DONG Energy, Australia’s Macquarie and Swancor Holding of Taiwan.

  • 3 February 2017
    Business & Finance, Contracts & Tenders

    DONG Energy yesterday revealed its ambition to increase the installed offshore wind capacity to 11-12GW at the end of 2025.

  • 25 January 2017
    Business & Finance, Wind Farm Update

    DONG Energy and Macquarie Capital have signed agreements to acquire a combined 85% ownership interest in the Taiwanese offshore wind project Formosa I from local developer Swancor Renewable. Completion of the transactions is subject to a number of conditions precedent including approval from the EU and from the Investment Commission under Taiwan’s Ministry of Economic Affairs, […]

  • 19 December 2016
    Wind Farm Update

    IHC IQIP today informed its S-2000 Hydrohammer was used to install two monopiles for the first two Formosa 1 offshore wind turbines in Taiwan.  The company delivered the S-2000 Hydroammer with a 5.5m pile sleeve to Jiangsu Longyuan Zhenhua Marine Engineering Co. Ltd, which carried out the installation of foundations for the project, developed by Swancor/Formosa Wind Power […]

  • 1 September 2016
    Vessels, Wind Farm Update

    The charter of A2SEA’s M/V Torben ended on 15 August without the company’s crew being able to complete the installation of two foundations and two Siemens 4MW turbines at the Formosa 1 pilot project in Taiwan. The installation of the two foundations and the two turbines was initially scheduled to start in June 2016. The A2SEA project […]