212 results found for 'wind osprey'

212 results found for 'wind osprey'
Order results by

A list of search results

  • 14 April 2026
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    Cadeler’s second M-class vessel, Wind Mover, which was delivered by the South Korean shipbuilder Hanwha Ocean to Cadeler in November 2025, has been deployed on its first project, the 1.2 GW Baltic Power offshore wind farm in Poland. The new vessel, designed to install the next generation of offshore wind farm components, has taken over […]

  • 3 March 2026
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    Jack-up vessels Wind Osprey and Wind Pace will start installing wind turbines at the East Anglia Three offshore wind farm site in the UK around 18 March. Both vessels will mobilise at the Port of Esbjerg, Denmark, with first load-out for Wind Osprey expected on 15 March, while the first load-out for Wind Pace is […]

  • 15 June 2026
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    A hundred V236-15.0 MW wind turbines are now installed at sea, a milestone the Danish OEM Vestas reached as construction work advances on the Baltic Power project in Poland. Cadeler’s jack-up vessel Wind Osprey installed the first of 76 Vestas 15 MW turbines at the Polish offshore wind farm site in July 2025. In February/March this […]

  • 20 March 2026
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    All 76 transition pieces (TPs) have been installed on the Baltic Power project, a 1.2 GW offshore wind farm being built in the Polish sector of the Baltic Sea. The work is being carried out by Van Oord, which is utilising the SAL heavy lift vessel MV Lone for transporting and installing transition pieces at […]

  • 12 May 2026
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    Navantia Seanergies and Windar Renovables have shipped the final monopiles for East Anglia Three directly to the offshore project site in the UK. The monopiles for the 95-turbine offshore wind farm are being supplied by Haizea Wind Group and the Navantia-Windar consortium, with Windar also delivering the transition pieces for the project. Navantia and Windar’s share of […]

  • 21 April 2026
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The first wind turbine has been installed at the East Anglia Three offshore wind farm site in the UK, the owners of the GBP 4 billion (around EUR 4.6 billion) project, ScottishPower Renewables and Masdar, said on 21 April. The 1.4 GW East Anglia Three, being built 69 kilometres off the coast of Suffolk, will […]

  • 2 March 2026
    Foundations, Supply Chain

    Steelwind Nordenham has used a Sherwin-Williams coating solution for monopiles the German foundation manufacturer produced for EnBW’s He Dreiht offshore wind farm. The coating selected for the project is Sherwin-Williams’ Dura-Plate SW-501 system, described as a solvent-free epoxy designed to form a barrier between steel surfaces and environmental elements such as water, oxygen and salts. […]

  • 1 January 2026
    Business & Finance, Supply Chain, Technology, Wind Turbines

    In offshoreWIND.biz‘s 2024 annual wind turbine overview, you could have read about the first 16 MW floating wind platform installed offshore and a 26 MW prototype under construction, both in China, and a 21 MW prototype being assembled in Europe. Wind turbine generator (WTG) technology did not stop progressing in 2025, with Chinese OEMs still leading capacity-wise, […]

  • 20 October 2025
    Business & Finance, Infrastructure

    The Danish wind turbine manufacturer, Vestas, has decided to put on hold its plans to open its biggest factory in Poland, as European demand falters, according to Reuters. In 2024, Vestas announced that it would build a second offshore wind turbine manufacturing facility in Poland. The factory, which was expected to open in 2026, would […]

  • 9 December 2025
    Equipment, Foundations, Innovation, R&D, Supply Chain, Technology

    Prometeo, the Offshore Rover by AXIST: A Breakthrough That Reinvents Mono-Pile Flange Measurement In the world of offshore wind, precision is non-negotiable. Even the smallest deviation can lead to deformation, reduced performance, and costly corrective interventions. Measuring the flange of a mono-pile immediately after piling is one of the most critical moments in the entire […]

  • 17 June 2021
    Vessels

    Following the replacement of the main crane on its jack-up vessel Wind Orca, Cadeler has decided to do the same on Wind Osprey, which is currently installing wind turbines on the Triton Knoll offshore wind farm in the UK. The company contracted NOV to upgrade Wind Orca with a new and improved crane in December […]

  • 1 December 2021
    Vessels, Wind Farm Update

    Cadeler’s jack up Wind Osprey has arrived at Able Seaton Port in Hartlepool to load the first batch of Vestas V164-10.0 MW turbines to be installed at the 1.1 GW Seagreen wind farm offshore Scotland. Wind Osprey is expected to arrive at the installation site some 27 kilometres off the Angus coast with the first […]

  • 3 August 2021
    Contracts & Tenders, Vessels

    Houston-headquartered NOV has been contracted by Cadeler to upgrade the wind turbine installation vessel Wind Osprey with a new, large capacity leg crane. Last year, NOV was selected to manufacture the new heavy-lift crane for Cadeler’s Wind Orca. Within that contract, Cadeler had an option to replace the main crane of the Wind Osprey. The […]

  • 8 April 2022
    Ports & Logistics, Vessels, Wind Farm Update

    Cadeler’s wind turbine installation vessel Wind Osprey has undergone seafastening mobilisation and is now ready to head to the Netherlands to start installing turbines on the 1.5 GW Hollandse Kust Zuid offshore wind farm. Wind Osprey is expected to leave the Port of Esbjerg in Denmark in a few days and head to Sif’s Maasvlakte […]

  • 20 January 2021
    Wind Farm Update

    Cadeler’s wind farm installation vessel Wind Osprey has arrived at the Triton Knoll wind farm loaded with the first sets of MHI Vestas V164-9.5 MW turbines. The installation of the first wind turbine at the site some 32 kilometres offshore Lincolnshire, UK, is ongoing. Wind Osprey loaded the turbine components at Able Seaton Port, MHI […]

  • 22 June 2023
    Vessels

    Cadeler has purchased the latest-generation Liebherr Ram Luffing Offshore Crane for its O-class wind farm installation vessel (WFIV) Wind Osprey. The acquisition is part of the company’s upgrade initiatives through which by early 2024, its O-class vessels will be ready to support the next generation of wind turbines. According to Liebherr, its RL 2600 deck […]

  • 24 August 2021
    Business & Finance, Vessels

    Cadeler’s wind farm installation vessels Wind Orca and Wind Osprey have achieved 87 per cent utilisation, and at competitive market rates, in the first half of this year, bringing the company a 253 per cent increase in revenue compared to the same period in 2020. Last year, Cadeler reported a EUR 9 million revenue for […]

  • 13 January 2021
    Vessels, Wind Farm Update

    Cadeler has mobilized and handed over its jack-up vessel Wind Osprey for the installation of turbines at the Triton Knoll offshore wind project in the UK. The jack-up is now in Able Seaton Port where load out operations will take place for the duration of the project. According to Cadeler, the vessel was able to […]

  • 23 January 2023
    Contracts & Tenders, Vessels

    Denmark-headquartered Cadeler has awarded its compatriot Semco Maritime a contract for vessel modifications to upgrade the main crane capacity on Cadeler’s two O-class wind farm installation vessels (WFIV). Semco Maritime has previously fitted new and extended crane booms on the two WFIVs, Wind Orca and Wind Osprey. The scope of work comprises planning and supplier […]

  • 1 March 2023
    Contracts & Tenders, Technology, Vessels

    Danish wind farm installation vessel owner and operator Cadeler A/S has invested in Høglund Ship Performance Monitor (SPM) which could reduce fuel consumption and improve the environmental footprint of their two offshore wind vessels, Wind Osprey and Wind Orca. “The Høglund SPM system will give us detailed insight on the efficiency of our engines. We are constantly […]

  • 5 June 2023
    Wind Farm Update

    The installation of the last batch of wind turbines is now underway at the Hollandse Kust Zuid offshore wind farm in the Netherlands after the vessel Wind Osprey picked up the components in Rotterdam last week. This weekend, Vattenfall said via social media that the components for the last turbines were being loaded onto Cadeler’s […]

  • 25 December 2020
    Vessels

    Cadeler A/S, formerly Swire Blue Ocean, will open an office in Vejle, Denmark, in order to be closer to key customers and suppliers in the offshore wind industry. Many of the largest and most influential companies within the offshore wind industry are headquartered along Jutland’s eastern coast – including original equipment manufacturers, wind farm developers, […]

  • 1 November 2022
    Ports & Logistics, Vessels, Wind Farm Update

    Cadeler’s wind turbine installation vessel Wind Osprey has installed the 70th Siemens Gamesa 11 MW wind turbine at the 1.5 GW Hollandse Kust Zuid offshore wind farm in the Dutch North Sea. The installation of the 70th turbine marks the halfway milestone on the 140-turbine project, Cadeler said. Once fully installed and commissioned in the […]

  • 11 November 2021
    Contracts & Tenders, Vessels, Wind Farm Update

    Cadeler has signed a firm contract for a wind turbine installation vessel to be used on Ørsted’s Gode Wind 3 and Borkum Riffgrund 3 offshore wind farms in Germany, following a preferred supplier agreement signed last month. The contract covers the transportation and installation of a minimum of 48 Siemens Gamesa 11 MW turbines. The […]

  • 21 October 2022
    Contracts & Tenders, Vessels

    Cadeler has signed a Letter of Intent with an undisclosed party described by the Danish wind farm installation vessel owner and operator as ”a blue chip client in the industry” to explore the possibility of long-term use of one of Cadeler’s two O-class vessels. The LoI covers offshore wind farm assignments taking place in the […]

  • 27 February 2023
    Wind Farm Update

    100 out of the 140 Siemens Gamesa 11.0-200 DD wind turbines have been installed at the 1.5 GW Hollandse Kust Zuid, the world’s first subsidy-free offshore wind farm and soon to be the largest offshore wind farm in operation. ”We have finished the installation of offshore wind turbine number 100 at the Hollandse Kust Zuid […]