  • 1 November 2022
    Ports & Logistics, Vessels, Wind Farm Update

    Cadeler’s wind turbine installation vessel Wind Osprey has installed the 70th Siemens Gamesa 11 MW wind turbine at the 1.5 GW Hollandse Kust Zuid offshore wind farm in the Dutch North Sea. The installation of the 70th turbine marks the halfway milestone on the 140-turbine project, Cadeler said. Once fully installed and commissioned in the […]

  • 21 October 2022
    Contracts & Tenders, Vessels

    Cadeler has signed a Letter of Intent with an undisclosed party described by the Danish wind farm installation vessel owner and operator as ”a blue chip client in the industry” to explore the possibility of long-term use of one of Cadeler’s two O-class vessels. The LoI covers offshore wind farm assignments taking place in the […]

  • 2 August 2022
    Wind Farm Update

    The 1.5 GW Hollandse Kust Zuid – the world’s first subsidy-free offshore wind farm – has generated first electricity. While still in their testing phase, the first operating turbines are already producing electricity, which is transferred to shore via an offshore transformation station and fed into the Dutch grid. Hollandse Kust Zuid is located in […]

  • 21 October 2022
    Contracts & Tenders, Wind Farm Update

    EnBW He Dreiht GmbH has issued a contract notice seeking setup and operation of marine coordination during the construction phase of the 960 MW He Dreiht offshore wind farm in the German North Sea. The contract covers the provision of qualified marine coordinators in various shift systems, and marine coordinator assistance, as well as necessary […]

  • 12 October 2022
    Wind Farm Update

    Cadeler’s wind farm installation vessel Wind Orca has hit the halfway mark on the Seagreen offshore wind farm in Scotland, where 57 out of the 114 Vestas 10 MW wind turbines have now been installed. The first wind turbine was installed in early December 2021 by the Wind Osprey vessel, which was replaced by its sister vessel […]

  • 23 September 2022
    Ports & Logistics, Wind Farm Update

    50 out of the 114 Vestas V164-10.0 MW turbines have been installed at the 1.1 GW Seagreen offshore wind farm, Scotland’s largest and the world’s deepest fixed-bottom offshore wind farm. The wind turbines are being transported from Vestas’ turbine marshalling base at Able Seaton Port in Hartlepool and installed at the site by Cadeler’s wind […]

  • 13 July 2022
    Vessels, Wind Farm Update

    Cadeler has signed a Vessel Reservation Agreement with ScottishPower Renewables for the transportation and installation of 95 wind turbines for the 1.4 GW East Anglia Three offshore wind farm. In February 2021, ScottishPower Renewables selected Siemens Gamesa as the preferred bidder to supply and install 14+ MW wind turbines on East Anglia Hub, including East Anglia Three, […]

  • 22 November 2022
    Contracts & Tenders, Vessels

    Cadeler has placed an order to build its second F-class wind farm installation vessel (WFIV) at COSCO Heavy Industries in China. The latest newbuild will bring the number of vessels in Cadeler’s fleet to six, with the two existing O-class vessels, Wind Osprey and Wind Orca, two X-class vessels under construction, and the two F-class newbuilds. The global […]

  • 5 May 2022
    Business & Finance, Contracts & Tenders, Vessels

    Denmark-based Cadeler has revealed that the company is in advanced talks with COSCO Shipyard regarding a possible order to build a new “hybrid” offshore wind farm foundation installation vessel. The potential foundation installation vessel could be delivered in the fourth quarter of 2025, with an expected cost currently estimated to be in the range of […]

  • 19 August 2022
    Business & Finance

    After establishing a consortium to develop offshore wind projects in Norway in 2021, TotalEnergies, Iberdrola, and Norsk Havvind have now officially announced the consortium’s name: Skjoldblad. The three companies joined forces in November 2021 with a goal to respond to the Norwegian 4.5 GW Utsira Nord and Sørlige Nordsjø II tenders for the development of […]

  • 25 April 2022
    Contracts & Tenders, Wind Farm Update

    Vattenfall has selected German-based 8.2 Consulting AG for commissioning and quality surveillance work on the Hollandse Kust Zuid offshore wind farm in the Netherlands. From May 2022, the installation and commissioning of the 140 Siemens Gamesa 11.0-200 DD wind turbines will start 18 to 36 kilometres off the Dutch coast, where 8.2 Consulting AG will […]

  • 26 April 2022
    Grid Connection, Ports & Logistics, Vessels, Wind Farm Update

    Installation works are well underway at the 1.5 GW Hollandse Kust Zuid – the world’s first subsidy-free offshore wind farm – to ensure that electricity starts flowing to the Dutch grid in early May. As reported, the first of the wind farm’s 140 Siemens Gamesa 11.0-200 DD wind turbines was installed at the site some […]

  • 19 April 2022
    Business & Finance, Environment, Grid Connection, Vessels, Wind Farm Update

    The first of the 140 Siemens Gamesa 11.0-200 DD wind turbines has been installed on the 1.5 GW Hollandse Kust Zuid – the world’s first subsidy-free offshore wind farm. This is also the first SG 11.0-200 DD unit to be installed offshore and the largest and most powerful wind turbine to be installed on an […]

  • 27 June 2022
    Environment, R&D

    Ørsted and the World Wide Fund for Nature (WWF Denmark) are testing how 3D-printed reefs can benefit biodiversity in the Kattegat, a strait between Denmark and Sweden, which is experiencing a historically low cod stock, the Danish energy company said. This is the first time 3D-printed reefs are used in Danish waters, and they will […]

  • 18 April 2022
    Business & Finance, Ports & Logistics, Vessels, Wind Farm Update

    Cadeler’s jack-up Wind Osprey has left Sif’s facility at Maasvlakte 2 in the Port of Rotterdam loaded with the first batch of Siemens Gamesa 11 MW wind turbines to be installed at the 1.5 GW Hollandse Kust Zuid wind farm in the Dutch North Sea. The project milestone marks a series of firsts for the […]

  • 15 November 2022
    Environment, Wind Farm Update

    Ørsted and Yorkshire Wildlife Trust have teamed up to develop a seagrass restoration project as part of Ørsted’s 2.6 GW Hornsea Project Four offshore wind farm in the UK. The initial phase of the project has already started as the Trust was commissioned to collect and plant seagrass seed across a 9.8 acres pilot area, […]

  • 8 April 2022
    Ports & Logistics, Vessels, Wind Farm Update

    Cadeler’s wind turbine installation vessel Wind Osprey has undergone seafastening mobilisation and is now ready to head to the Netherlands to start installing turbines on the 1.5 GW Hollandse Kust Zuid offshore wind farm. Wind Osprey is expected to leave the Port of Esbjerg in Denmark in a few days and head to Sif’s Maasvlakte […]

  • 13 April 2022
    Vessels, Wind Farm Update

    21 out of the 114 Vestas V164-10.0 MW turbines have been installed at the 1.1 GW Seagreen offshore wind farm, Scotland’s largest and the world’s deepest fixed-bottom offshore wind farm. The turbines have been installed on all available 21 jacket foundations, and the installation activity will recommence when further foundations are installed, according to the […]

  • 29 March 2022
    Business & Finance, Vessels

    Danish wind farm installation vessel owner and operator Cadeler A/S said that the company tripled its revenue in 2021 and returned to profitability. The revenue for 2021 totaled EUR 61 million, an increase of 212 per cent against EUR 19.5 million in 2020. The growth reflects a 77 per cent utilization rate of the vessels […]

  • 28 April 2022

    Heavy plates for offshore wind towers have to withstand enormous forces. Therefore, leading manufacturers of wind tower steel foundations rely on milling technology from LINSINGER. The use of wind power off the coasts (offshore wind farms) is booming: despite COVID disruptions, 2020 was the second highest year for offshore wind installations – worldwide 6.1 GW […]

  • 3 March 2022
    Wind Farm Update

    Ten out of the 114 Vestas V164-10.0 MW turbines have been installed at the 1.1 GW Seagreen offshore wind farm, Scotland’s largest and the world’s deepest fixed-bottom offshore wind farm. The first wind turbine was installed at the site some 27 kilometres off the Angus coast in early December. This marked the first time a […]

  • 27 January 2022
    Contracts & Tenders, Vessels

    Danish wind farm installation vessel owner and operator Cadeler A/S has secured a contract with Vestas, and a reservation agreement with an undisclosed client. The contract with Vestas is said to have strengthened Cadeler’s order backlog and ensured optimal utilization of the company’s O-class vessels, Wind Osprey and Wind Orca, up until the planned vessel […]

  • 2 February 2022
    Vessels

    Offshore wind turbines are growing in size as technology advances and demand for renewable energy soars but installing them could be a headache for operators as demand will outpace the supply of capable vessels by 2024, Rystad Energy research shows. Operators will have to invest in new vessels or upgrade existing ones to install the […]

  • 1 December 2021
    Vessels, Wind Farm Update

    Cadeler’s jack up Wind Osprey has arrived at Able Seaton Port in Hartlepool to load the first batch of Vestas V164-10.0 MW turbines to be installed at the 1.1 GW Seagreen wind farm offshore Scotland. Wind Osprey is expected to arrive at the installation site some 27 kilometres off the Angus coast with the first […]

  • 17 June 2021
    Vessels

    Following the replacement of the main crane on its jack-up vessel Wind Orca, Cadeler has decided to do the same on Wind Osprey, which is currently installing wind turbines on the Triton Knoll offshore wind farm in the UK. The company contracted NOV to upgrade Wind Orca with a new and improved crane in December […]

  • 20 January 2021
    Wind Farm Update

    Cadeler’s wind farm installation vessel Wind Osprey has arrived at the Triton Knoll wind farm loaded with the first sets of MHI Vestas V164-9.5 MW turbines. The installation of the first wind turbine at the site some 32 kilometres offshore Lincolnshire, UK, is ongoing. Wind Osprey loaded the turbine components at Able Seaton Port, MHI […]