1383 results found for 'hai long 2'

1383 results found for 'hai long 2'
Order results by

A list of search results

  • 8 May 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The jacket foundation for the Hai Long 2 offshore substation has been installed by CSBC-DEME Wind Engineering’s (CDWE) Green Jade vessel in Taiwan. Hai Long comprises two offshore wind farms, the 532 MW Hai Long 2 and the 512 MW Hai Long 3 and is being developed in three phases as Hai Long 2 is […]

  • 24 April 2024
    Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The first of two offshore substations built for the Hai Long 2 and Hai Long 3 offshore wind projects has set sail from Vung Tau, Vietnam, and is en route to the Taiwan Strait. A consortium comprising Semco Maritime and PTSC Mechanical & Construction (PTSC M&C) is responsible for delivering the two offshore substations for […]

  • 20 May 2024
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The first offshore substation (OSS) topside has been installed at the Hai Long offshore wind farm by CSBC-DEME Wind Engineering’s (CDWE) Green Jade vessel in Taiwan. The 1,022 MW Hai Long comprises two offshore wind farms, the 532 MW Hai Long 2 and the 512 MW Hai Long 3 and is being developed in three phases as […]

  • 27 March 2024
    Equipment, Fixed-Bottom, Offshore Platforms, Supply Chain

    Palfinger has signed a contract to deliver an equipment package for two substations at the 1,044 MW Hai Long offshore wind farm in Taiwan. The substations will be equipped with two stiff boom cranes with an outreach of 26 metres, four life raft davits and four fixed boom cranes, with the latter to be used […]

  • 2 February 2024
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    EEW Korea Heavy Pipe Construction (EEW KHPC) has loaded out the first twelve pin piles for the jacket foundations that will be installed at the Hai Long offshore wind farm in Taiwan. The first batch of pin piles, whose load-out took place at the quayside in the port of Gwangyang on 31 January, will soon […]

  • 12 April 2024
    Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    Offshore construction has started at the Hai Long offshore wind farm site in Taiwan with the vessel Green Jade installing pin piles for the project’s jacket foundations. The Hai Long Offshore Wind Project joint venture (Northland Power, Yushan Energy, Mitsui & Co., and Gentari) announced the official start of offshore construction on 11 April. The […]

  • 15 February 2024
    Business & Finance, Contracts & Tenders, Supply Chain, Vessels

    Vard has signed a contract for the design and construction of a hybrid power service operation vessel (SOV) for Singapore-headquartered Cyan Renewables. The 85.5-metre-long vessel will be built, outfitted, commissioned, and delivered from Vard Vung Tau in Vietnam, with the delivery scheduled for the second quarter of 2026. The announcement follows after Siemens Gamesa awarded […]

  • 18 March 2024
    Business & Finance, Contracts & Tenders, Supply Chain

    Norway’s Glamox has secured three separate orders for LED lighting for the turbine foundation transition pieces for offshore wind farms in Taiwan and South Korea. SK Oceanplant awarded Glamox a contract to provide 468 linear Glamox TL60-1200 LED luminaries and 52 Glamox RLX80 floodlights to light 52 transition pieces at the 1,044 MW Hai Long […]

  • 17 January 2024
    Equipment, Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update

    The installation of pin piles for the jacket foundations on Taiwan’s 1,044 MW Hai Long offshore wind farm is expected to start in March. CAPE Holland has been contracted to supply its CAPE Vibro Lifting Tools to CSBC-DEME Wind Engineering (CDWE), whose vessel Green Jade will be installing the piles. CDWE signed a contract for […]

  • 29 December 2023
    Business & Finance, Business development, Collaboration, Fixed-Bottom, Outlook & Strategy, Project Updates, Wind Farm Update

    Northland Power has closed the transaction with Gentari International Renewables through which Gentari acquired 49 per cent of Northland’s ownership in the Hai Long offshore wind project located in Taiwan. Northland now holds a 30.6 per cent ownership interest in the overall project and will continue to take the lead role in Hai Long’s construction […]

  • 16 February 2024
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The US Environmental Protection Agency (EPA) has issued a Clean Air Act permit to Empire Offshore Wind, owned by Equinor. The air quality analysis, conducted by EPA, showed that the impacts on air quality from the construction and operation of the offshore wind project will not cause or contribute to a violation of federal air […]

  • 21 December 2023
    Contracts & Tenders, Supply Chain

    OEG Energy Group (OEG) has revealed that Specialist Marine Consultants (SMC) and Fern Communications (Fern), both OEG Renewables businesses, have been contracted to deliver a turnkey marine coordination solution to the 1 GW Hai Long offshore wind farm in Taiwan. The turnkey contract will be for the duration of the installation and commissioning works and […]

  • 5 June 2024
    Business & Finance, Business development, Cables, Grid Connection, Infrastructure, Outlook & Strategy

    South Korean Taihan Cable & Solution has opened the first phase of its submarine cable plant that will supply the offshore wind industry. The submarine cable plant, covering around 44,800 square metres behind Godae Pier at Pyeongtaek’s Dangjin Port, is being constructed in two phases. The first phase, which focuses on producing inter-array cables, was […]

  • 29 March 2024
    Business & Finance, Contracts & Tenders, Supply Chain

    Seaway7, part of the Subsea7 Group, has been awarded a contract by PGE Polska Grupa Energetyczna and Ørsted for the transportation and installation of the substations for the Baltica 2, which is the first stage of the Baltica Offshore Wind Farm in the Polish Baltic Sea. The deal is worth between USD 50 million and […]

  • 23 July 2024
    Business & Finance, Vessels

    Norway’s Vard has signed a contract with its compatriot Rem Offshore to design and construct another commissioning service operation vessel (CSOV). The VARD 4 19 design CSOV, developed by Vard Design in Ålesund, will be the third vessel Vard delivers to Rem Offshore. The first two, REM Power and REM Wind, were delivered in 2023 […]

  • 23 February 2024
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The US Bureau of Ocean Energy Management (BOEM) has approved the Construction and Operations Plan (COP) for Equinor’s Empire Wind offshore wind project in New York, the US. With this approval secured, the developer is planning to start the construction of Empire Wind 1 later this year. The approved plan includes the construction and operation […]

  • 26 January 2024
    Business & Finance, Project Updates, Wind Farm Update

    Equinor and BP have reached an agreement to restructure the ownership of their joint US offshore wind projects which, following completion, will result in BP taking ownership of Equinor’s 50 per cent stake in the Beacon Wind 1 and 2 projects and Equinor taking ownership of BP’s 50 per cent stake in the Empire Wind […]

  • 15 March 2024
    Business & Finance, Fixed-Bottom, Foundations, Manufacturing, Supply Chain

    The first production line at the new manufacturing halls Sif is building at its Maasvlakte 2 site in Rotterdam is scheduled to go into operation in July 2024, according to the Dutch manufacturer, which is building the new halls as an extension to its existing facilities.  Sif made the final investment decision (FID) to build […]

  • 26 February 2024
    Manufacturing, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Siemens Gamesa has rolled out the first 14 MW wind turbine nacelles at its Cuxhaven plant in Germany as the production of wind turbine components for the Moray West offshore wind farm is currently underway. The first batch of nacelles is now awaiting shipment and installation at the Moray West project site offshore Scotland, Siemens […]

  • 6 February 2024
    Business & Finance, Business development, Research & Development

    The international marine environmental consulting and survey company, CSA Ocean Sciences, has been granted a non-exclusive General Offshore Geophysical Survey permit which allows the firm to conduct low-energy marine surveys within a three-mile zone from the mean high tide line along California’s coast. The permit, granted by the California State Lands Commission (CSLC), allows CSA […]

  • 11 April 2024
    Authorities, Contracts & Tenders, Fixed-Bottom, Planning & Permitting

    The Netherlands Enterprise Agency (RVO) has launched a tender for geotechnical investigations at the Doordewind zone, one of the three new areas the Dutch Government designated in 2022 as part of the plan to add more offshore wind capacity. Valued at a total of more than EUR 42 million, the contract will be awarded for offshore geotechnical […]

  • 9 April 2024
    Contracts & Tenders, Project Updates, Supply Chain, Wind Farm Update

    PGE Baltica, a PGE Group company, has selected Gavin & Doherty Geosolutions (GDG) as a geotechnical and structural designer for the ground survey stage of the EWB1 development under the Baltica 1 Project in the offshore wind farm area and along the export cable route. The scope of activities under the contract includes supervision over […]

  • 23 July 2024
    Authorities, Floating Wind, Planning & Permitting

    The California Public Utilities Commission (CPUC) has issued a proposed decision that could see the US state running three offshore wind solicitations to procure up to 7.6 GW of installed capacity. The first projects under the proposed procurement timeline would be in operation by 1 June 2035. The proposed decision, issued on 19 July, is […]

  • 28 March 2024
    Authorities, Business development, Planning & Permitting, Research & Development

    Four developers have submitted their bids in response to the combined Connecticut-Massachusetts-Rhode Island offshore wind solicitation with the tenders totalling 6.8 GW. The proposals were made by Avangrid Renewables, Ørsted, SouthCoast Wind Energy, and Vineyard Offshore. In October 2023, the three states signed a Memorandum of Understanding (MoU) to collaborate on offshore wind procurement, although […]

  • 18 June 2024
    Business & Finance, Fixed-Bottom, Supply Chain, Wind Turbines

    Vestas has revealed the client and project details for an agreement first announced on 13 June. This conditional agreement, signed with Vattenfall and BASF, involves supplying 112 V236-15.0 MW wind turbines for the Nordlicht 1 and 2 offshore wind projects in the German North Sea. Within the scope of the contract is furthermore a 5-year […]

  • 31 May 2024
    Cables, Grid Connection, Offshore Platforms

    The production of TenneT’s new cables that can transmit up to 2 GW of offshore wind capacity has started at LS Cable in Donghae, South Korea. The new cables with a voltage of 525 kV make it possible to transmit 2 GW of direct current (DC) over long distances with low losses, said the Dutch-German […]