939 results found for 'dogger bank wind farm'

939 results found for 'dogger bank wind farm'
Order results by

A list of search results

  • 22 May 2025
    Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The jacket foundation and the topside for Dogger Bank C, the third phase of the 3.6 GW Dogger Bank Wind Farm, have been installed in the UK. According to the recent Notice to Mariners from the project, Heerema Marine Contractors’ semi-submersible crane vessel Sleipnir installed the jacket foundation and the topside at the Dogger Bank […]

  • 31 March 2025
    Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    The offshore installation vessel Seaway Strashnov will install the remaining two monopiles at the Dogger Bank B offshore wind farm site next month. According to a Notice to Mariners from the project, the work is planned to commence on 7 April and continue until approximately 30 April. The heavy lift vessel, owned by Seaway7, completed […]

  • 12 December 2024
    Business & Finance, Contracts & Tenders, Supply Chain, Wind Turbines

    Dogger Bank Wind Farm, a joint venture between SSE Renewables, Equinor, and Vårgrønn, has signed a vessel reservation agreement with Seaway7 to charter a second turbine installation vessel to support the ongoing delivery of the offshore wind farm off the coast of England. Starting in 2026, the Seaway Ventus jack-up installation vessel is planned to […]

  • 29 April 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    More than half of the wind turbines at Dogger Bank A, the first phase of the UK’s 3.6 GW Dogger Bank Wind Farm, have been installed. So far, 52 of the 95 GE Haliade-X 13 MW wind turbines that Dogger Bank A will feature are in place, according to a Notice to Mariners from the […]

  • 23 April 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    After installing all 95 monopiles at Dogger Bank B, the offshore installation vessel Seaway Strashnov has moved on to the third phase of the UK’s Dogger Bank Wind Farm, where it has now begun foundation work at Dogger Bank C. Seaway Strashnov and Seaway Alfa Lift commenced the installation work at Dogger Bank B in the spring of […]

  • 3 January 2025
    Fixed-Bottom, Foundations, Project Updates, Vessels, Wind Farm Update

    The offshore installation vessel Seaway Strashnov has installed all but two monopile foundations at the Dogger Bank B offshore wind site in the UK and will return in the second quarter of 2025 to complete the installation. Five more transition pieces (TPs) are also left to be installed, according to the latest notices to mariners […]

  • 23 May 2025
    Business & Finance, Vessels

    Norway-based vessel operator and service provider, Integrated Wind Solutions (IWS), has reported revenue for its business unit providing offshore wind vessels, IWS Fleet, of EUR 14.2 million in the first quarter of 2025 (Q1 2025) and new contracts and contract extensions that were signed during the quarter. IWS Fleet marked a revenue increase in Q1 […]

  • 31 January 2025
    Business & Finance, Vessels

    UK-headquartered North Star has named and delivered its latest service operation vessel (SOV), completing its fleet of vessels chartered for long-term service at the 3.6 GW Dogger Bank offshore wind farm. The Grampian Tweed is the fourth SOV introduced ahead of schedule to support the Dogger Bank offshore wind farm, owned by a consortium of […]

  • 9 December 2024
    Business & Finance, Cables, Contracts & Tenders, Fixed-Bottom, Grid Connection, Supply Chain

    Proserv has been awarded a contract by DEME Offshore to de-risk offshore wind operations at Dogger Bank C, the third phase of the 3.6 GW Dogger Bank Wind Farm project in the UK. According to Proserv, the company will utilise its Electro Cable Guard (ECG) system to identify signs of transmission cable failure far earlier, […]

  • 7 May 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The installation of the offshore substation jacket foundation and topside for the third phase of the Dogger Bank Wind Farm, the world’s biggest offshore wind farm under construction, will commence soon. Heerema Marine Contractors’ semi-submersible crane vessel (SSCV) Sleipnir will install the offshore substation jacket and topside at the Dogger Bank C site in the […]

  • 20 May 2025
    Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    All foundations, including the transition pieces (TPs), are now in place at Dogger Bank B, the second phase of the world’s largest offshore wind farm under construction, as the heavy-lift vessel (HLV) Seaway Alfa Lift recently installed the final TP. The vessel started installing the final five TPs earlier this month, after Seaway Strashnov installed the […]

  • 1 April 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    Spain’s Navantia Seanergies has completed the load-out of the High Voltage Direct Current (HVDC) substation jacket for the 1.2 GW Dogger Bank C offshore wind platform in the UK. The load-out of the substation jacket, which will be installed at the Dogger Bank Wind Farm developed by SSE Renewables, Equinor, and Vårgrønn, was completed at […]

  • 15 May 2025
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    RWE plans to sell a stake in its 1.4 GW Sofia offshore wind farm next year, which is currently under construction in the UK. In a press conference call speech published on 15 May, Michael Müller, CFO of RWE AG, said that the company intends to sell stakes in the Sofia offshore wind project next […]

  • 9 May 2025
    Authorities, Planning & Permitting

    The Crown Estate is proceeding with its Capacity Increase Programme to maximise the potential of existing offshore wind lease areas and add 4.7 GW of renewable energy. According to The Crown Estate, an additional 4.7 GW of renewable energy could be generated from the delivery of the programme by amending existing seabed rights to increase […]

  • 17 December 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    Seaway7, part of the Subsea7 Group, has been awarded a contract by Inch Cape Offshore Limited (ICOL), a joint venture between ESB and Red Rock Renewables, for the transport and installation of pin-pile jacket foundations and transition pieces (TPs) for the 1.1 GW offshore wind project. The deal is worth between USD 150 million and […]

  • 8 November 2024
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Production of the last transition piece (TP) for the 3.6 GW Dogger Bank Wind Farm, the world’s largest offshore wind farm under construction, is underway at Smulders facility in Hoboken, Belgium. The consortium comprising Sif and Smulders was awarded contracts for the manufacture of all monopiles and transition pieces for the three-phased Dogger Bank Wind […]

  • 25 February 2025
    Business development, Innovation, Technology, Vessels

    Dutch company Next Ocean is looking at a global reach for its technology that predicts waves and vessel motions minutes beforehand. Following a period of demonstration deployments of WavePredictor and the first vessels using it commercially, Next Ocean says it is witnessing the technology becoming standard equipment onboard vessels working in offshore wind and other […]

  • 26 March 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    TGS is scheduled to start geophysical survey work across the Dogger Bank South (DBS) offshore wind farm sites in the UK on 27 March. According to a Notice to Mariners issued by the DBS project, the Norway-based energy data and intelligence company will be using the seismic vessel Ramform Vanguard, supported by the guard/scout vessel […]

  • 11 April 2025
    Fixed-Bottom, Foundations, Innovation, Project Updates, Supply Chain, Technology, Wind Farm Update

    RWE, in collaboration with Hydrotechnik Offshore, a Germany-based bubble curtain developer, has deployed the underwater noise abatement technology during monopile installation at the Sofia offshore wind farm, marking the first time the technology has been used in the UK. Currently under construction on Dogger Bank, 195 kilometres off the UK coast, the 1.4 GW Sofia […]

  • 21 March 2025
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    Cadeler’s wind turbine installation vessel (WTIV) Wind Peak is en route to the site of the Sofia offshore wind farm with the first set of Siemens Gamesa’s SG 14-222 DD turbine components. The vessel departed the port of Hull on 20 March, according to the available AIS data, and is heading towards the project site […]

  • 14 May 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    Eleven wind turbines are now standing tall at the Sofia offshore wind farm site in the UK, where the work started in March and will continue until the end of the year. Foundation installation is also underway at the UK project site, with 76 monopile foundations now in place. The 1.4 GW project, developed by […]

  • 27 February 2025
    Authorities, Business & Finance, Fixed-Bottom, Grid Connection, Planning & Permitting

    Ofgem is inviting tenders to own and operate electricity transmission links worth GBP 4 billion (about EUR 4.8 billion), connecting the Sofia offshore wind farm to Great Britain’s mainland energy network. Ofgem has opened the Offshore Transmission Owner (OFTO) regime Tender Round 12, which invites investors to bid to own and operate infrastructure connecting RWE’s […]

  • 8 May 2025
    Business development, Contracts & Tenders, Fixed-Bottom, Research & Development, Supply Chain

    RWE and Masdar have signed contracts with TGS and Fugro to conduct detailed geophysical and geotechnical surveys for the eastern array of the proposed Dogger Bank South (DBS) offshore wind farms. According to the developers, these site investigations will enhance understanding of the seabed conditions of the sites, which are over 122 kilometres off the […]

  • 5 December 2024
    Business & Finance, Fixed-Bottom, Floating Wind

    Shell has decided to cease investments in new offshore wind developments as part of a review of the Shell Energy business. The oil and gas major, which has built a significant portfolio of renewable energy and clean fuel projects, will not abandon its existing offshore wind projects, but investing in new offshore wind farms is […]

  • 21 January 2025
    Authorities, Fixed-Bottom, Planning & Permitting

    The US Bureau of Ocean Energy Management (BOEM) and the Bureau of Safety and Environmental Enforcement (BSEE) have completed the review and approved the revised Construction and Operations Plan (COP) for the Vineyard Wind 1 offshore wind farm. Last week, the federal government lifted the suspension on Vineyard Wind’s installation of the remaining GE Vernova […]

  • 17 March 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    RWE’s Sofia offshore wind farm in the UK has reached several major milestones in the construction of foundations and onshore and offshore electrical systems and is now preparing for the first turbine installation expected in the coming weeks. Last week, Cadeler’s wind turbine installation vessel (WTIV) Wind Peak arrived, ready to transport the first set […]