202 results found for 'SG 14-222 DD'

202 results found for 'SG 14-222 DD'
Order results by

A list of search results

  • 29 September 2025
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    More than half of the total 100 wind turbines are now in place at RWE’s Sofia offshore wind farm site in the UK. The project’s SG 14-222 DD wind turbines are being installed by Cadeler’s vessel Wind Peak, which put the first turbine in place in March. Wind Peak, operating from the port of Hull, is carrying components […]

  • 19 February 2026
    Fixed-Bottom, Project Updates, Wind Farm Update

    Seventy wind turbines have been installed at RWE’s Sofia offshore wind farm in the UK, according to a Notice to Mariners recently issued by the project team. The first of the project’s 100 Siemens Gamesa SG 14-222 DD wind turbines was installed in March 2025, and the work reached the halfway mark in September last […]

  • 21 August 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    Siemens Gamesa has installed 50 per cent of the recyclable blades at RWE’s Sofia offshore wind farm in the UK, with the turbine manufacturer continuing installation throughout the rest of the year. According to RWE, the company and Siemens Gamesa have achieved the first-ever large-scale installation of recyclable blades at a UK offshore wind farm. […]

  • 27 October 2025
    Business & Finance, Ports & Logistics

    The Spanish-German engineering company Siemens Gamesa has decided to shelve plans for an offshore wind turbine nacelle factory at the Port of Esbjerg in Denmark. Siemens Gamesa told offshoreWIND.biz that the Port of Esbjerg remains a key hub for its offshore wind activities and that the company continues to assess potential investment options there. “Siemens […]

  • 26 January 2026
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The Danish Energy Agency (DEA) has approved a 30-year electricity production licence to the Thor offshore wind farm, under construction at a site located approximately 22 kilometres off the west coast of Jutland. With a total installed capacity of 1.1 GW, Thor will become Denmark’s largest offshore wind project once fully operational in 2027, generating […]

  • 18 February 2026
    Fixed-Bottom, Foundations, Grid Connection, Offshore Platforms, Project Updates, Supply Chain, Wind Farm Update

    Offshore construction has begun on the Bałtyk 2 and Bałtyk 3 offshore wind projects in Poland, developed by Equinor and Polenergia, which will together have 100 wind turbines and an installed capacity of 1.4 GW. The 2026 offshore construction campaign will see the installation of 100 monopiles, transition pieces (TPs), offshore substation components, subsea cables […]

  • 27 February 2026
    Vessels

    Heerema Marine Contractors has put its semi-submersible crane vessel (SSCV) Thialf, the second-largest SSCV in the world, through a lifetime extension programme, with the vessel currently undergoing the first stage of the work in Rotterdam, ahead of its mobilisation for a Polish offshore wind project next month. Thialf will undergo what Heerema Marine Contractors says is […]

  • 15 July 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    All 100 monopile foundations have been installed at RWE’s 1.4 GW Sofia offshore wind farm site, located 195 kilometres off the northeast coast of the UK. The achievement concludes a 14-month foundation installation campaign carried out by Van Oord as part of a joint engineering, procurement, construction and installation (EPCI) contract for both wind turbine […]

  • 28 July 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The jacket foundation and the substation topside have been installed at the 1 GW Thor offshore wind farm site in Denmark. Following the jacket and topside’s sail-away from HSM Offshore Energy’s Schiedam yard in the Netherlands, the installation of the 2,600-tonne topside was executed offshore, with the heavy-lift vessel Gulliver of Scaldis SMC placing the […]

  • 18 June 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The last three monopiles for RWE’s Sofia offshore wind farm in the UK have been loaded at the quay of EEW Special Pipe Constructions (EEW SPC) in Rostock, Germany. According to EEW SPC, a total of 100 monopiles, with weights of 1,143 to 1,521 tonnes and lengths of up to 91.8 metres, were loaded onto […]

  • 17 July 2025
    Fixed-Bottom, Grid Connection, Manufacturing, Offshore Platforms, Project Updates, Supply Chain, Wind Farm Update

    The offshore substation for the 1 GW Thor offshore wind farm has left HSM Offshore Energy’s Schiedam yard in the Netherlands and is on its way to the project site in the Danish North Sea. “[The] sail-away of the fully assembled substation for THOR is an important step for us in the project team”, said […]

  • 12 June 2025
    Project Updates, Wind Farm Update

    The 1 GW Hai Long offshore wind project, jointly developed by Northland Power, Gentari, and Mitsui & Co., has produced its first power, marking the successful energisation of the project and connection to Taipower’s grid in Taiwan. The milestone comes ahead of schedule, initially planned for the second half of 2025, according to the developers. […]

  • 16 July 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Half of the monopile foundations are now in place at the Thor offshore wind farm site, as Jan De Nul’s heavy-lift vessel Les Alizés installed the 36th of the project’s total 72 monopiles on 15 July. “With Thor we are constructing Denmark’s largest offshore wind farm to date. Reaching halfway in the safe installation of […]

  • 4 July 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The fully assembled offshore substation for the 1 GW Thor offshore wind farm has been loaded out at HSM Offshore Energy’s Schiedam yard in the Netherlands. Both the jacket and the topside are now on the barges, and the structures are being prepared for sail-away to their destination off the Danish coast. In 2022, RWE, […]

  • 3 June 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    CSBC-DEME Wind Engineering (CDWE), using its heavy lift vessel Green Jade, has completed the installation of pin piles on Taiwan’s Hai Long offshore wind project, with jacket foundations for the project’s third phase to be installed next. The 1,022 MW Hai Long comprises two offshore wind farms, split into three sites: Hai Long 2a (294 MW), […]

  • 30 June 2025
    Cables, Grid Connection, Project Updates, Wind Farm Update

    Jan De Nul has pulled two export cables for the 1,080 MW Thor offshore wind farm, currently under construction in Denmark. The export cables will transport clean, renewable electricity from the offshore site 22 kilometres out in the North Sea to the Danish mainland. In 2023, Jan De Nul, together with Hellenic Cables, won a […]

  • 27 June 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    The jacket foundation installation at Ørsted’s Greater Changhua 2b & 4 offshore wind farms is nearing completion, with 61 out of 66 foundations already installed at the site in Taiwan. Additionally, a third of the wind turbines for the project are now in place. Offshore construction of the 920 MW Greater Changhua 2b and 4 […]

  • 18 June 2025
    Grid Connection, Onshore Infrastructure, Project Updates, Wind Farm Update

    Danish transmission system operator (TSO) Energinet has completed the construction work related to the connection of the 1 GW Thor offshore wind farm to the national grid. The construction work began in January 2023 and has been completed on time, said Energinet. The scope of work included moving 95,000 cubic metres of soil and laying […]

  • 15 May 2025
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    RWE plans to sell a stake in its 1.4 GW Sofia offshore wind farm next year, which is currently under construction in the UK. In a press conference call speech published on 15 May, Michael Müller, CFO of RWE AG, said that the company intends to sell stakes in the Sofia offshore wind project next […]

  • 14 May 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    Eleven wind turbines are now standing tall at the Sofia offshore wind farm site in the UK, where the work started in March and will continue until the end of the year. Foundation installation is also underway at the UK project site, with 76 monopile foundations now in place. The 1.4 GW project, developed by […]

  • 13 June 2025
    Fixed-Bottom, Operations & Maintenance, Project Updates, Wind Farm Update

    The operations and maintenance (O&M) base for the Danish 1 GW offshore wind farm, Thor, is nearing completion. On 12 June, RWE and Danish construction company Østermark Entreprenørforretning held a topping-out ceremony for the new building located at Thorsminde port. The O&M base is expected to be completed by the end of this year and […]

  • 24 April 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    The UK Secretary of State for Scotland, Ian Murray, switched on full power at the 882 MW Moray West offshore wind farm, built by Ocean Winds some 20 kilometres off the coast of Buckie. Moray West comprises 60 Siemens Gamesa SG 14-222 DD wind turbines, each of which can generate up to 14.7 MW with […]

  • 16 April 2025
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The first of 66 Siemens Gamesa 14 MW wind turbines that will make up the Greater Changhua 2b & 4 offshore wind farm in Taiwan has been installed. The major milestone for Ørsted’s 920 MW offshore wind project also marks a milestone for Siemens Gamesa, whose SG 14-236 DD wind turbine model is installed offshore […]

  • 15 February 2023
    Equipment, Infrastructure, Technology

    Siemens Gamesa has started the production of the first 108-metre wind turbine blade at its factory in Hull, the UK. The B108 IntegralBlades are one of the key components of Siemens Gamesa’s flagship offshore wind turbine – the SG 14-222 DD. ”Over the past year, we’ve doubled output at the Hull facility, allowing our team […]

  • 12 November 2021
    Technology

    The third and final 108-metre blade has been installed on Siemens Gamesa’s SG 14-222 DD prototype offshore wind turbine at the test centre in Østerild, Denmark. With the final blade in place, the SG 14-222 DD prototype has become the world’s largest and most powerful turbine to be installed, taking the mantle from GE Haliade-X […]

  • 10 December 2021
    R&D, Technology

    Siemens Gamesa’s SG 14-222 DD prototype offshore wind turbine installed at the test centre in Østerild, Denmark, has produced its first electricity and delivered it to the grid. The SG 14-222 DD turbine model has a 14 MW capacity, reaching up to 15 MW using the company’s Power Boost function. The model features a 222-metre […]