151 results found for 'SG 14-222 DD'

151 results found for 'SG 14-222 DD'
Order results by

A list of search results

  • 7 August 2024
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Vessels, Wind Farm Update

    Heerema Marine Contractors’ semi-submersible crane vessel (SSCV) Sleipnir is expected to sail to the Sofia offshore wind farm site in the UK in a few days to install the project’s HVDC offshore converter platform. According to a recent Notice to Mariners from the project, Sleipnir will start the work on or around 10 August and […]

  • 27 May 2024
    Fixed-Bottom, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Lamprell has completed the final delivery of transition pieces (TPs) for Ocean Winds’ Moray West offshore wind farm in Scotland. All 62 TPs, including the penultimate and final batch destined for Scotland, have been delivered and handed over to Lamprell’s client Ocean Winds. According to the UAE-based company, the project was completed on schedule and […]

  • 11 September 2024
    Business & Finance, Cables, Grid Connection, Project Updates, Vessels, Wind Farm Update

    Van Oord’s new, next-generation cable-laying vessel (CLV) is getting ready for its first project with the pick up of inter-array cables destined for RWE’s largest offshore wind farm to date. Calypso, Van Oord’s second CLV which will mostly be used for installing inter-array and export cables for offshore wind projects, is equipped with two cable […]

  • 10 April 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    The installation of foundations is scheduled to kick off this month at the Sofia offshore wind farm site, located on Dogger Bank in the central North Sea, 195 kilometres from the nearest point on the UK’s northeast coast. Van Oord’s offshore wind installation vessel Aeolus and special service support vessel (SSSV) Baltic Explorer are expected […]

  • 3 October 2024
    Fixed-Bottom, Manufacturing, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    RWE has unveiled the first 108-metre turbine blade made at the Siemens Gamesa factory in Hull, which will be part of 100 wind turbines to be installed at the 1.4 GW Sofia offshore wind farm in the UK. Each of the 100 wind turbines, rated at 14 MW, will be equipped with 108-metre-long blades that […]

  • 24 April 2024
    Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The first of two offshore substations built for the Hai Long 2 and Hai Long 3 offshore wind projects has set sail from Vung Tau, Vietnam, and is en route to the Taiwan Strait. A consortium comprising Semco Maritime and PTSC Mechanical & Construction (PTSC M&C) is responsible for delivering the two offshore substations for […]

  • 28 May 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    All transition pieces (TPs) have been installed at the 882 MW Moray West offshore wind farm in Scotland, according to a Notice to Mariners issued on 27 May by Moray Offshore Windfarm (West). In addition, Cadeler’s Wind Orca has installed ten wind turbines so far at the offshore site in the Moray Firth. The final […]

  • 26 June 2024
    Business & Finance, Contracts & Tenders, Supply Chain

    UK-headquartered 2H has been awarded a four-year integrity management (IM) contract for the 882 MW Moray West offshore wind farm in Scotland. The contract’s scope covers IM for all balance of plant (BoP) equipment, including the wind turbine’s monopile foundations and tower structures, inter-array and export cables, and offshore and onshore substations. According to 2H, […]

  • 21 August 2024
    Onshore Infrastructure, Project Updates, Wind Farm Update

    Seventeen people working on the Hai Long Changhua onshore substation, part of the Hai Long offshore wind project in Taiwan, were hospitalised on 20 August after a carbon dioxide leak at the substation. First reported by Taiwanese media citing information provided by Changhua County Fire Department, the incident is said to have left 14 on-site […]

  • 29 August 2024
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The high-voltage direct current (HVDC) offshore converter platform (OCP) has been installed at the Sofia offshore wind farm site in the UK. The installation was carried out by Heerema Marine Contractors, using its Sleipnir heavy-lift vessel as a subcontractor to the GE Vernova/Seatrium consortium responsible for the OCP. The platform, equivalent in height to an […]

  • 20 May 2024
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The first offshore substation (OSS) topside has been installed at the Hai Long offshore wind farm by CSBC-DEME Wind Engineering’s (CDWE) Green Jade vessel in Taiwan. The 1,022 MW Hai Long comprises two offshore wind farms, the 532 MW Hai Long 2 and the 512 MW Hai Long 3 and is being developed in three phases as […]

  • 22 April 2024

    Moray West, an offshore wind farm in the outer Moray Firth, Scotland, has installed the first of 60 Siemens Gamesa SG 14-222 DD wind turbines. Supplied with “Power Boost”, each turbine can generate up to 14.7 MW output. The 882 MW wind farm is being developed by Ocean Winds. The pre-assembly activity of the 60 […]

  • 12 April 2024
    Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    Offshore construction has started at the Hai Long offshore wind farm site in Taiwan with the vessel Green Jade installing pin piles for the project’s jacket foundations. The Hai Long Offshore Wind Project joint venture (Northland Power, Yushan Energy, Mitsui & Co., and Gentari) announced the official start of offshore construction on 11 April. The […]

  • 8 May 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The jacket foundation for the Hai Long 2 offshore substation has been installed by CSBC-DEME Wind Engineering’s (CDWE) Green Jade vessel in Taiwan. Hai Long comprises two offshore wind farms, the 532 MW Hai Long 2 and the 512 MW Hai Long 3 and is being developed in three phases as Hai Long 2 is […]

  • 31 July 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    UPDATE: On 16 August, the Moray West project developer, Ocean Winds, said via social media that more than half of the wind turbines were now installed. The Moray West offshore wind farm in Scotland is nearing the halfway point of its wind turbine installation, according to the latest Notice to Mariners issued by the Moray […]

  • 10 September 2024
    Operations & Maintenance

    Ocean Winds has opened its new operations & maintenance (O&M) base in Buckie, Scotland, that will service the Moray West offshore wind farm once it becomes fully operational in 2025. The First Minister of Scotland, John Swinney, visited the facility on 9 September to mark the opening of the Ocean Winds’ O&M base with associated […]

  • 15 April 2024
    Equipment, Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Belgian offshore construction company DEME, using its vessel Orion, has completed the installation of monopiles at the Moray West offshore wind farm site in Scotland.  Monopile installation at Moray West started in October 2023, with Boskalis’s vessel Bokalift 2 deployed for the work and Orion taking over in February. DEME’s Orion installed 29 monopiles for Ocean […]

  • 21 May 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    Van Oord’s offshore installation vessel, Aeolus, has installed the first of 100 monopile foundations at the 1.4 GW Sofia project in the UK, RWE’s largest offshore wind farm to date. The Sofia offshore wind farm is located on Dogger Bank in the central North Sea, 195 kilometres from the North East coast of the UK. […]

  • 4 April 2024
    Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The first 14 MW turbine nacelles have been loaded onto the roll-on/roll-off (Ro-Ro) vessel, Rotra Vente, at Siemens Gamesa’s Cuxhaven plant in Germany. They are destined for the Moray West offshore wind farm and are heading toward the Port of Nigg, Scotland, according to AIS data available online. The vessel left Cuxhaven on 3 April […]

  • 5 July 2024
    Business development, Equipment, Fixed-Bottom, Foundations, Innovation, Supply Chain, Technology

    A consortium comprising some of the world’s leading offshore wind developers and Tier 1 suppliers have initiated a joint industry project that aims to commercialise a new foundation connection technology developed by the Netherlands-based company C1 Connections. “With the increasing size of wind turbines, the traditional L-flange design has reached a point where in cases […]

  • 17 April 2024
    Equipment, Fixed-Bottom, Supply Chain, Vessels

    As construction work has started on Taiwan’s 1 GW Hai Long offshore wind farm with the vessel Green Jade installing the first jacket foundation pin piles, TWD and Seatools each revealed their contracts for the provision of pre-piling and piling equipment and services with the vessel owner, CSBC-DEME Wind Engineering (CDWE). The Hai Long joint […]

  • 27 March 2024
    Equipment, Fixed-Bottom, Offshore Platforms, Supply Chain

    Palfinger has signed a contract to deliver an equipment package for two substations at the 1,044 MW Hai Long offshore wind farm in Taiwan. The substations will be equipped with two stiff boom cranes with an outreach of 26 metres, four life raft davits and four fixed boom cranes, with the latter to be used […]

  • 26 March 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first Siemens Gamesa wind turbine blades and tower components for Ocean Winds’ Moray West offshore wind farm have arrived at the Port of Nigg in Scotland. The 882 MW offshore wind farm, developed by Ocean Winds, will comprise 60 wind turbines and will be the first project to feature Siemens Gamesa’s SG 14-222 DD model. The turbines […]

  • 19 March 2024
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The installation of Siemens Gamesa’s 14 MW wind turbines at the Moray West offshore wind farm site in Scotland is scheduled to start in April. The vessel chartered to install the turbines, Cadeler’s Wind Orca, has just arrived in Esbjerg, Denmark, to mobilise for the project after completing a crane upgrade in the Netherlands. In […]

  • 20 June 2024
    Contracts & Tenders, Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Skyborn Renewables has signed an updated Master Supply Agreement with Siemens Gamesa for the delivery of 63 SG 14-236 DD wind turbines, with a power boost of 15 MW, for its 945 MW Gennaker offshore wind project in the German Baltic Sea. The agreement strengthens the long-term partnership between the two companies and replaces the […]

  • 8 July 2024
    Contracts & Tenders, Foundations, Supply Chain

    Ramboll has been selected as the foundation designer for the Gennaker offshore wind project in the German Baltic Sea, owned by Skyborn Renewables. Under the contract, Ramboll will be responsible for developing the basic and detailed design of 63 monopile foundations supporting Siemens Gamesa’s SG 14-236 DD wind turbines. In addition, the company’s role extends […]