Search results for: SG 14-222 DD

133 results

A list of search results

  • 19 March 2024
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The installation of Siemens Gamesa’s 14 MW wind turbines at the Moray West offshore wind farm site in Scotland is scheduled to start in April. The vessel chartered to install the turbines, Cadeler’s Wind Orca, has just arrived in Esbjerg, Denmark, to mobilise for the project after completing a crane upgrade in the Netherlands. In […]

  • 21 December 2023
    Contracts & Tenders, Supply Chain

    OEG Energy Group (OEG) has revealed that Specialist Marine Consultants (SMC) and Fern Communications (Fern), both OEG Renewables businesses, have been contracted to deliver a turnkey marine coordination solution to the 1 GW Hai Long offshore wind farm in Taiwan. The turnkey contract will be for the duration of the installation and commissioning works and […]

  • 26 March 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first Siemens Gamesa wind turbine blades and tower components for Ocean Winds’ Moray West offshore wind farm have arrived at the Port of Nigg in Scotland. The 882 MW offshore wind farm, developed by Ocean Winds, will comprise 60 wind turbines and will be the first project to feature Siemens Gamesa’s SG 14-222 DD model. The turbines […]

  • 10 April 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    The installation of foundations is scheduled to kick off this month at the Sofia offshore wind farm site, located on Dogger Bank in the central North Sea, 195 kilometres from the nearest point on the UK’s northeast coast. Van Oord’s offshore wind installation vessel Aeolus and special service support vessel (SSSV) Baltic Explorer are expected […]

  • 20 February 2024
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The first Siemens Gamesa 108-metre-long wind turbine blades have left its manufacturing factory in Hull for the Moray West offshore wind project in Scotland. Nine of the 180 blades destined for the 882 MW offshore wind farm were loaded onto the Rotra Mare transporter ship at the Siemens Gamesa blade factory in Hull, and are […]

  • 26 February 2024
    Manufacturing, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Siemens Gamesa has rolled out the first 14 MW wind turbine nacelles at its Cuxhaven plant in Germany as the production of wind turbine components for the Moray West offshore wind farm is currently underway. The first batch of nacelles is now awaiting shipment and installation at the Moray West project site offshore Scotland, Siemens […]

  • 24 April 2024
    Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The first of two offshore substations built for the Hai Long 2 and Hai Long 3 offshore wind projects has set sail from Vung Tau, Vietnam, and is en route to the Taiwan Strait. A consortium comprising Semco Maritime and PTSC Mechanical & Construction (PTSC M&C) is responsible for delivering the two offshore substations for […]

  • 27 March 2024
    Equipment, Fixed-Bottom, Offshore Platforms, Supply Chain

    Palfinger has signed a contract to deliver an equipment package for two substations at the 1,044 MW Hai Long offshore wind farm in Taiwan. The substations will be equipped with two stiff boom cranes with an outreach of 26 metres, four life raft davits and four fixed boom cranes, with the latter to be used […]

  • 18 December 2023
    Contracts & Tenders, Equipment, Supply Chain

    Norway-headquartered Glamox has won a contract from Dutch engineering company, Bakker Sliedrecht, to provide specialist marine LED lighting for the foundation platforms for 100 14 MW wind turbines for the Sofia offshore wind farm in the UK. For the Sofia offshore wind farm, Glamox will provide 800 marine-certified LED luminaires, which will illuminate the platforms […]

  • 2 February 2024
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    EEW Korea Heavy Pipe Construction (EEW KHPC) has loaded out the first twelve pin piles for the jacket foundations that will be installed at the Hai Long offshore wind farm in Taiwan. The first batch of pin piles, whose load-out took place at the quayside in the port of Gwangyang on 31 January, will soon […]

  • 4 April 2024
    Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The first 14 MW turbine nacelles have been loaded onto the roll-on/roll-off (Ro-Ro) vessel, Rotra Vente, at Siemens Gamesa’s Cuxhaven plant in Germany. They are destined for the Moray West offshore wind farm and are heading toward the Port of Nigg, Scotland, according to AIS data available online. The vessel left Cuxhaven on 3 April […]

  • 14 February 2024
    Business & Finance, Contracts & Tenders, Supply Chain, Vessels

    Siemens Gamesa has awarded a 15-year charter contract to Cyan Renewables for its first service operation vessel (SOV) in Asia. The contract will begin in 2026 and the SOV will be used to service 73 Siemens Gamesa SG 14-222 DD wind turbines at the Hai Long offshore wind farms, located about 50 kilometres off the […]

  • 9 November 2023
    Business & Finance

    UK Export Finance (UKEF), the UK Government’s export credit agency, has guaranteed GBP 380 million (approximately EUR 436 million) in financing for the 1 GW Hai Long offshore wind project in Taiwan. The contribution is said to support a project finance package of over GBP 3 billion issued by more than 15 lenders to the […]

  • 17 January 2024
    Equipment, Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update

    The installation of pin piles for the jacket foundations on Taiwan’s 1,044 MW Hai Long offshore wind farm is expected to start in March. CAPE Holland has been contracted to supply its CAPE Vibro Lifting Tools to CSBC-DEME Wind Engineering (CDWE), whose vessel Green Jade will be installing the piles. CDWE signed a contract for […]

  • 12 April 2024
    Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    Offshore construction has started at the Hai Long offshore wind farm site in Taiwan with the vessel Green Jade installing pin piles for the project’s jacket foundations. The Hai Long Offshore Wind Project joint venture (Northland Power, Yushan Energy, Mitsui & Co., and Gentari) announced the official start of offshore construction on 11 April. The […]

  • 22 April 2024

    Moray West, an offshore wind farm in the outer Moray Firth, Scotland, has installed the first of 60 Siemens Gamesa SG 14-222 DD wind turbines. Supplied with “Power Boost”, each turbine can generate up to 14.7 MW output. The 882 MW wind farm is being developed by Ocean Winds. The pre-assembly activity of the 60 […]

  • 15 April 2024
    Equipment, Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Belgian offshore construction company DEME, using its vessel Orion, has completed the installation of monopiles at the Moray West offshore wind farm site in Scotland.  Monopile installation at Moray West started in October 2023, with Boskalis’s vessel Bokalift 2 deployed for the work and Orion taking over in February. DEME’s Orion installed 29 monopiles for Ocean […]

  • 18 January 2024
    Equipment, Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update

    NOTE: The article was amended on 23 January to include the parts of Dogger Bank Wind Farm’s Supporting Statement filed to the Marine Management Organisation (MMO) that concern the reasons for the delay of the monopile installation on Dogger Bank B. The installation of foundations on two UK offshore wind projects, the 1.4 GW Sofia […]

  • 17 April 2024
    Equipment, Fixed-Bottom, Supply Chain, Vessels

    As construction work has started on Taiwan’s 1 GW Hai Long offshore wind farm with the vessel Green Jade installing the first jacket foundation pin piles, TWD and Seatools each revealed their contracts for the provision of pre-piling and piling equipment and services with the vessel owner, CSBC-DEME Wind Engineering (CDWE). The Hai Long joint […]

  • 2 January 2024
    Fixed-Bottom, Floating Wind, Market Outlooks, Supply Chain, Wind Turbines

    The biggest wind turbines also make for some of the biggest news on offshoreWIND.biz. In 2023, wind turbine OEMs continued making headlines with their models in development and on the path to commercialisation, and by announcing brand new wind turbine generators (WTGs) that further raise the bar in generation capacity and size. Here, we are […]

  • 26 January 2024
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    The first steel cutting of the monopiles for RWE’s Thor offshore wind farm in Denmark has taken place at Dajin Offshore Heavy Industry’s Penglai facility in China, marking the start of the project’s construction phase. In April 2023, Dajin was selected to deliver 36 monopiles as well as secondary structures and electrical outfitting for the […]

  • 28 September 2023
    Business & Finance, Project Updates, Wind Farm Update

    The 1 GW Hai Long offshore wind project in Taiwan, being developed jointly by Northland Power and Mitsui & Co., has reached financial close for its 20-year TWD 117 billion (about EUR 3.4 billion) non-recourse green financing. According to Northland Power, the TWD 117 billion debt amount at closing changed from the TWD 118 billion […]

  • 25 March 2024
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The Danish Energy Agency (DEA) has approved the feasibility study report for RWE’s Thor offshore wind farm in Denmark. Approved on 20 March, the feasibility study report, which covered an area of 286 square kilometres, also included the environmental impact study (EIS). The approval does not give the project developer, Thor Wind Farm I/S, owned […]

  • 19 April 2024
    Contracts & Tenders, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Heerema Marine Contractors has signed reservation and preliminary work agreements with MFW Bałtyk II and MFW Bałtyk III, special purpose companies owned by Polenergia and Equinor, for the transport and installation of wind turbine foundations and an offshore substation. ”The subject of the Reservation Agreements is the obligation of the parties to continue negotiations in […]

  • 19 February 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Netherlands-headquartered Sif Group has signed the final contracts with Polenergia and Equinor for the supply of 100 monopiles for the Bałtyk II and Bałtyk III offshore wind farms in the Polish Baltic Sea. Manufacturing of the monopiles is scheduled for the second quarter of 2025 with completion in 2026. Fred van Beers, CEO of Sif […]

  • 16 February 2024
    Business & Finance, Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Equinor and Polenergia have selected Siemens Gamesa as their wind turbine supplier for the Bałtyk II and Bałtyk III offshore wind farms located in the Polish Baltic Sea. The two energy companies have signed final contracts for the production, delivery and service of 100 SG 14-236 DD wind turbines. The contracts with Siemens Gamesa are […]