190 results found for 'SG 14-222 DD'

190 results found for 'SG 14-222 DD'
Order results by

A list of search results

  • 18 June 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The last three monopiles for RWE’s Sofia offshore wind farm in the UK have been loaded at the quay of EEW Special Pipe Constructions (EEW SPC) in Rostock, Germany. According to EEW SPC, a total of 100 monopiles, with weights of 1,143 to 1,521 tonnes and lengths of up to 91.8 metres, were loaded onto […]

  • 16 April 2025
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The first of 66 Siemens Gamesa 14 MW wind turbines that will make up the Greater Changhua 2b & 4 offshore wind farm in Taiwan has been installed. The major milestone for Ørsted’s 920 MW offshore wind project also marks a milestone for Siemens Gamesa, whose SG 14-236 DD wind turbine model is installed offshore […]

  • 27 March 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    CSBC-DEME Wind Engineering (CDWE), utilising its Green Jade vessel, has installed the offshore topside on the jacket foundation for the Hai Long 3 offshore wind farm in Taiwan. CDWE placed the offshore topside on the jacket, which was installed at the site in August 2024. The offshore substation at the Hai Long 2 phase is […]

  • 24 April 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    The UK Secretary of State for Scotland, Ian Murray, switched on full power at the 882 MW Moray West offshore wind farm, built by Ocean Winds some 20 kilometres off the coast of Buckie. Moray West comprises 60 Siemens Gamesa SG 14-222 DD wind turbines, each of which can generate up to 14.7 MW with […]

  • 28 March 2025
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The first wind turbine has been installed at the Sofia offshore wind farm in the UK. The 1.4 GW project, developed by RWE, will comprise 100 Siemens Gamesa 14 MW turbines, half of which will be fitted with recyclable blades. The wind turbine was installed by Cadeler’s wind turbine installation vessel (WTIV), Wind Peak, which […]

  • 21 March 2025
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    Cadeler’s wind turbine installation vessel (WTIV) Wind Peak is en route to the site of the Sofia offshore wind farm with the first set of Siemens Gamesa’s SG 14-222 DD turbine components. The vessel departed the port of Hull on 20 March, according to the available AIS data, and is heading towards the project site […]

  • 7 March 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    CSBC-DEME Wind Engineering (CDWE) has started the 2025 installation campaign for the 1 GW Hai Long offshore wind project in Taiwan. The 1,022 MW Hai Long project comprises two offshore wind farms, the 518 MW Hai Long 2 and the 504 MW Hai Long 3, and is being developed in three phases. Hai Long 2 is […]

  • 14 May 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    Eleven wind turbines are now standing tall at the Sofia offshore wind farm site in the UK, where the work started in March and will continue until the end of the year. Foundation installation is also underway at the UK project site, with 76 monopile foundations now in place. The 1.4 GW project, developed by […]

  • 15 May 2025
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    RWE plans to sell a stake in its 1.4 GW Sofia offshore wind farm next year, which is currently under construction in the UK. In a press conference call speech published on 15 May, Michael Müller, CFO of RWE AG, said that the company intends to sell stakes in the Sofia offshore wind project next […]

  • 6 March 2025
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    Ventus Energy has secured two contracts with Ocean Winds to support its Scotland-based offshore wind farms, Moray West and Moray East. The first contract, awarded in September 2024 for Moray West, spans an 18-month period and includes operations and maintenance (O&M) for the offshore transmission owner (OFTO) assets. The scope of work includes timely inspections […]

  • 3 June 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    CSBC-DEME Wind Engineering (CDWE), using its heavy lift vessel Green Jade, has completed the installation of pin piles on Taiwan’s Hai Long offshore wind project, with jacket foundations for the project’s third phase to be installed next. The 1,022 MW Hai Long comprises two offshore wind farms, split into three sites: Hai Long 2a (294 MW), […]

  • 12 June 2025
    Project Updates, Wind Farm Update

    The 1 GW Hai Long offshore wind project, jointly developed by Northland Power, Gentari, and Mitsui & Co., has produced its first power, marking the successful energisation of the project and connection to Taipower’s grid in Taiwan. The milestone comes ahead of schedule, initially planned for the second half of 2025, according to the developers. […]

  • 17 March 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    RWE’s Sofia offshore wind farm in the UK has reached several major milestones in the construction of foundations and onshore and offshore electrical systems and is now preparing for the first turbine installation expected in the coming weeks. Last week, Cadeler’s wind turbine installation vessel (WTIV) Wind Peak arrived, ready to transport the first set […]

  • 11 December 2024
    Business & Finance, Fixed-Bottom, Operations & Maintenance

    Ocean Winds, a 50/50 joint venture between EDP Renewables and ENGIE, has contracted Føn Energy Services to provide a fully integrated Balance of Plant (BoP) operations and maintenance (O&M) service programme for the Moray East and Moray West offshore wind farms in Scotland. The contract is valid for three years, with an option to extend […]

  • 21 April 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first Siemens Gamesa 14-222 DD turbine has been installed at the Hai Long 2A offshore wind farm in Taiwan, which is being developed by a joint venture between Northland Power, Mitsui & Co., and Gentari. The Hai Long project comprises two offshore wind farms, the 518 MW Hai Long 2 and the 504 MW […]

  • 27 June 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    The jacket foundation installation at Ørsted’s Greater Changhua 2b & 4 offshore wind farms is nearing completion, with 61 out of 66 foundations already installed at the site in Taiwan. Additionally, a third of the wind turbines for the project are now in place. Offshore construction of the 920 MW Greater Changhua 2b and 4 […]

  • 30 June 2025
    Cables, Grid Connection, Project Updates, Wind Farm Update

    Jan De Nul has pulled two export cables for the 1,080 MW Thor offshore wind farm, currently under construction in Denmark. The export cables will transport clean, renewable electricity from the offshore site 22 kilometres out in the North Sea to the Danish mainland. In 2023, Jan De Nul, together with Hellenic Cables, won a […]

  • 13 June 2025
    Fixed-Bottom, Operations & Maintenance, Project Updates, Wind Farm Update

    The operations and maintenance (O&M) base for the Danish 1 GW offshore wind farm, Thor, is nearing completion. On 12 June, RWE and Danish construction company Østermark Entreprenørforretning held a topping-out ceremony for the new building located at Thorsminde port. The O&M base is expected to be completed by the end of this year and […]

  • 14 January 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    Dajin Heavy Industry has shipped the last ten monopiles of the total 36 the company was contracted to produce for the Danish Thor offshore wind farm from its Penglai facility in China. The monopiles, each weighing over 1,100 tons will be delivered to the Port of Eemshaven, Dajin said in a social media post on 13 […]

  • 22 April 2025
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    EEW Special Pipe Constructions (EEW SPC) has delivered the first monopiles for RWE’s Thor offshore wind farm in Denmark. In March 2025, the first of twelve shipments for the 1.1 GW Thor project was completed at Rostock Port. So far, 15 out of the total 36 monopiles being produced by EEW SPC have been collected, […]

  • 18 June 2025
    Grid Connection, Onshore Infrastructure, Project Updates, Wind Farm Update

    Danish transmission system operator (TSO) Energinet has completed the construction work related to the connection of the 1 GW Thor offshore wind farm to the national grid. The construction work began in January 2023 and has been completed on time, said Energinet. The scope of work included moving 95,000 cubic metres of soil and laying […]

  • 30 January 2025
    Business & Finance, Business development, Contracts & Tenders, Fixed-Bottom, Research & Development, Supply Chain

    Norway-headquartered DeepOcean has been awarded a subsea survey contract for the Bałtyk 2 and Bałtyk 3 offshore wind projects in Poland, which are jointly developed by Equinor and Polenergia. Under the contract, DeepOcean will carry out geophysical seabed surveys of the export and inter-array cable corridors, utilising a dedicated survey remotely operated vehicle (SROV). The […]

  • 24 March 2025
    Business & Finance, Contracts & Tenders, Supply Chain

    ProCon Wind Energy has awarded Glamox a contract to light Thor, Denmark’s largest offshore wind farm, with its LED marine lighting. The contract will see Glamox install lights on 72 wind turbine foundations for the project being constructed by RWE. The external and internal lights use Glamox’s second-generation family of MIR linear luminaires. These will […]

  • 20 May 2025
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Equinor and Polenergia have taken a final investment decision for the Bałtyk 2 and Bałtyk 3 offshore wind farms, which will have 1.44 GW of installed capacity in Poland. The total investment of the project is approximately PLN 27 billion (approximately EUR 6.28 billion) in the construction, excluding financing costs, according to the joint venture […]

  • 23 May 2025
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Equinor and Polenergia have reached financial close for the Bałtyk 2 and Bałtyk 3 offshore wind farms in Poland, for which the joint venture partners secured two project financing packages of over EUR 3 billion for each wind farm, including ancillary facilities. The finance packages will fund the capital investment and other expenses of each […]

  • 30 April 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    Jan De Nul’s heavy-lift vessel Les Alizés has installed the first of 72 monopiles at RWE’s 1.1 GW Thor offshore wind farm in the Danish North Sea. The monopiles were shipped from the heavy-lift terminal in Eemshaven, the Netherlands, to the Thor construction site located approximately 22 kilometres off the west coast of Jutland. In 2023, […]