170 results found for 'SG 14-222 DD'

170 results found for 'SG 14-222 DD'
Order results by

A list of search results

  • 12 November 2024
    Equipment, Manufacturing, Supply Chain, Technology, Wind Turbines

    Siemens Gamesa has completed the manufacturing and testing of the first 14 MW wind turbine nacelle outside of Europe. Following the recent inauguration of its new nacelle production facility in Taichung, Taiwan, Siemens Gamesa finished the testing of the nacelle for the 14 MW wind turbines that will be installed at the Hai Long offshore […]

  • 21 March 2025
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    Cadeler’s wind turbine installation vessel (WTIV) Wind Peak is en route to the site of the Sofia offshore wind farm with the first set of Siemens Gamesa’s SG 14-222 DD turbine components. The vessel departed the port of Hull on 20 March, according to the available AIS data, and is heading towards the project site […]

  • 1 November 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Cadeler heavy lift vessel Wind Orca is nearing completion of turbine installations at the Moray West offshore wind farm site in Scotland, with just six turbines remaining to be installed, according to the latest Notice to Mariners. Moray West, part of Ocean Winds’ 6 GW portfolio of secured offshore wind farms in the UK, features 60 […]

  • 10 October 2024
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Seaway7 has finished the full engineering, procurement, installation, and commissioning (EPIC) work for the cables at the 882 MW Moray West offshore wind farm in Scotland. Seaway7 has installed 118 kilometres of 66 kV inter-array cables, linking the wind farm’s 60 turbines to two offshore substations, along with an additional 15 kilometres of 66 kV […]

  • 7 March 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    CSBC-DEME Wind Engineering (CDWE) has started the 2025 installation campaign for the 1 GW Hai Long offshore wind project in Taiwan. The 1,022 MW Hai Long project comprises two offshore wind farms, the 518 MW Hai Long 2 and the 504 MW Hai Long 3, and is being developed in three phases. Hai Long 2 is […]

  • 6 March 2025
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    Ventus Energy has secured two contracts with Ocean Winds to support its Scotland-based offshore wind farms, Moray West and Moray East. The first contract, awarded in September 2024 for Moray West, spans an 18-month period and includes operations and maintenance (O&M) for the offshore transmission owner (OFTO) assets. The scope of work includes timely inspections […]

  • 3 October 2024
    Fixed-Bottom, Manufacturing, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    RWE has unveiled the first 108-metre turbine blade made at the Siemens Gamesa factory in Hull, which will be part of 100 wind turbines to be installed at the 1.4 GW Sofia offshore wind farm in the UK. Each of the 100 wind turbines, rated at 14 MW, will be equipped with 108-metre-long blades that […]

  • 11 December 2024
    Business & Finance, Fixed-Bottom, Operations & Maintenance

    Ocean Winds, a 50/50 joint venture between EDP Renewables and ENGIE, has contracted Føn Energy Services to provide a fully integrated Balance of Plant (BoP) operations and maintenance (O&M) service programme for the Moray East and Moray West offshore wind farms in Scotland. The contract is valid for three years, with an option to extend […]

  • 19 November 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    CSBC-DEME Wind Engineering (CDWE) has completed the first offshore installation campaign for the Hai Long offshore wind project in Taiwan, with all jacket foundations installed at Hai Long 2. The overall project includes two offshore wind farms, namely the 518 MW Hai Long 2 and the 504 MW Hai Long 3. Hai Long 2 is […]

  • 24 October 2024
    Cables, Grid Connection, Project Updates, Vessels, Wind Farm Update

    Van Oord’s new, next-generation cable-laying vessel (CLV) Calypso has begun installing cables at its first offshore wind project, marking its official debut. Calypso’s first project is RWE’s Sofia offshore wind farm, being constructed on Dogger Bank in the central North Sea, 195 kilometres from the North East coast of the UK, which, with a capacity […]

  • 17 March 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    RWE’s Sofia offshore wind farm in the UK has reached several major milestones in the construction of foundations and onshore and offshore electrical systems and is now preparing for the first turbine installation expected in the coming weeks. Last week, Cadeler’s wind turbine installation vessel (WTIV) Wind Peak arrived, ready to transport the first set […]

  • 18 November 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The 60th and final turbine has been installed at the 882 MW Moray West offshore wind farm in the Moray Firth, located in northern Scotland. The Moray West offshore wind farm is nearing the end of the construction phase and will become fully operational during 2025, in line with the originally projected commercial operations date, […]

  • 11 September 2024
    Business & Finance, Cables, Grid Connection, Project Updates, Vessels, Wind Farm Update

    Van Oord’s new, next-generation cable-laying vessel (CLV) is getting ready for its first project with the pick up of inter-array cables destined for RWE’s largest offshore wind farm to date. Calypso, Van Oord’s second CLV which will mostly be used for installing inter-array and export cables for offshore wind projects, is equipped with two cable […]

  • 10 September 2024
    Operations & Maintenance

    Ocean Winds has opened its new operations & maintenance (O&M) base in Buckie, Scotland, that will service the Moray West offshore wind farm once it becomes fully operational in 2025. The First Minister of Scotland, John Swinney, visited the facility on 9 September to mark the opening of the Ocean Winds’ O&M base with associated […]

  • 29 August 2024
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The high-voltage direct current (HVDC) offshore converter platform (OCP) has been installed at the Sofia offshore wind farm site in the UK. The installation was carried out by Heerema Marine Contractors, using its Sleipnir heavy-lift vessel as a subcontractor to the GE Vernova/Seatrium consortium responsible for the OCP. The platform, equivalent in height to an […]

  • 19 November 2024
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The Dutch company, HSM Offshore Energy, has rolled out the offshore high-voltage substation (OHVS) for the Thor offshore wind farm and lifted the GIS modules for RWE Renewables at its Schiedam yard in the Netherlands. The offshore substation will function as the central hub, collecting electricity generated by Siemens Gamesa SG 14-236 DD wind turbines and […]

  • 4 December 2024
    Business & Finance, Cables, Contracts & Tenders, Fixed-Bottom, Grid Connection, Project Updates, Supply Chain, Wind Farm Update

    ScottishPower Renewables, part of the Iberdrola Group, has awarded an export cable contract for East Anglia Two (EA2), a 960 MW offshore wind farm in the UK, to Nexans. Under the contract, Nexans will supply and install approximately 100 kilometres of 275 kV high-voltage subsea export cables and 55 kilometres of onshore cables, which the […]

  • 2 October 2024
    Business & Finance, Cables, Fixed-Bottom, Grid Connection, Offshore Platforms

    Axess Technologies has secured a cable installation contract with HSM Offshore Energy for the Thor offshore wind farm located off the Danish west coast. The scope of work includes project management, engineering, pulling, terminating, and testing the internal platform cables into the Thor offshore substation topside, covering both 66 kV and 275 kV cable systems. […]

  • 30 January 2025
    Business & Finance, Business development, Contracts & Tenders, Fixed-Bottom, Research & Development, Supply Chain

    Norway-headquartered DeepOcean has been awarded a subsea survey contract for the Bałtyk 2 and Bałtyk 3 offshore wind projects in Poland, which are jointly developed by Equinor and Polenergia. Under the contract, DeepOcean will carry out geophysical seabed surveys of the export and inter-array cable corridors, utilising a dedicated survey remotely operated vehicle (SROV). The […]

  • 14 January 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    Dajin Heavy Industry has shipped the last ten monopiles of the total 36 the company was contracted to produce for the Danish Thor offshore wind farm from its Penglai facility in China. The monopiles, each weighing over 1,100 tons will be delivered to the Port of Eemshaven, Dajin said in a social media post on 13 […]

  • 21 August 2024
    Onshore Infrastructure, Project Updates, Wind Farm Update

    Seventeen people working on the Hai Long Changhua onshore substation, part of the Hai Long offshore wind project in Taiwan, were hospitalised on 20 August after a carbon dioxide leak at the substation. First reported by Taiwanese media citing information provided by Changhua County Fire Department, the incident is said to have left 14 on-site […]

  • 15 October 2024
    Cables, Contracts & Tenders, Fixed-Bottom, Grid Connection, Supply Chain

    Correll, part of SPIE Group, has been awarded a contract by Jan De Nul to complete the 66 kV inter-array cable (IAC) termination and testing on wind turbines for RWE’s 1 GW Thor offshore wind project in Denmark. The works are planned to commence in July 2025 with the mock-up scheduled for November 2024. RWE […]

  • 7 November 2024
    Fixed-Bottom, Operations & Maintenance, Project Updates, Wind Farm Update

    The construction of the operations & maintenance (O&M) base for RWE’s Thor offshore wind farm has officially started with a ground-breaking ceremony at the Port of Thorsminde. The construction works on the new base are scheduled to take around twelve months. A team of 50 to 60 people will work from the new building to […]

  • 31 October 2024
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The Danish Energy Agency (DEA) has granted RWE the offshore construction permit for its Thor offshore wind farm, enabling RWE to begin construction at sea in spring 2025. RWE said that good progress is already being made on land, with the laying of cables and the construction of an onshore substation in the municipality of […]

  • 22 October 2024
    Fixed-Bottom, Foundations, Ports & Logistics, Supply Chain

    The first batch of eight monopiles for RWE’s Thor offshore wind project, being built in the Danish North Sea, have been offloaded and stored at the base Port of Eemshaven in the Netherlands. Buss Terminal Eemshaven, part of the Hamburg-based terminal operator Buss Ports, provides storage space, heavy unloading equipment, and operators at the port […]

  • 7 August 2024
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Vessels, Wind Farm Update

    Heerema Marine Contractors’ semi-submersible crane vessel (SSCV) Sleipnir is expected to sail to the Sofia offshore wind farm site in the UK in a few days to install the project’s HVDC offshore converter platform. According to a recent Notice to Mariners from the project, Sleipnir will start the work on or around 10 August and […]