142 results found for 'SG 14-222 DD'

142 results found for 'SG 14-222 DD'
Order results by

A list of search results

  • 19 March 2024
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The installation of Siemens Gamesa’s 14 MW wind turbines at the Moray West offshore wind farm site in Scotland is scheduled to start in April. The vessel chartered to install the turbines, Cadeler’s Wind Orca, has just arrived in Esbjerg, Denmark, to mobilise for the project after completing a crane upgrade in the Netherlands. In […]

  • 27 May 2024
    Fixed-Bottom, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Lamprell has completed the final delivery of transition pieces (TPs) for Ocean Winds’ Moray West offshore wind farm in Scotland. All 62 TPs, including the penultimate and final batch destined for Scotland, have been delivered and handed over to Lamprell’s client Ocean Winds. According to the UAE-based company, the project was completed on schedule and […]

  • 27 March 2024
    Equipment, Fixed-Bottom, Offshore Platforms, Supply Chain

    Palfinger has signed a contract to deliver an equipment package for two substations at the 1,044 MW Hai Long offshore wind farm in Taiwan. The substations will be equipped with two stiff boom cranes with an outreach of 26 metres, four life raft davits and four fixed boom cranes, with the latter to be used […]

  • 10 April 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    The installation of foundations is scheduled to kick off this month at the Sofia offshore wind farm site, located on Dogger Bank in the central North Sea, 195 kilometres from the nearest point on the UK’s northeast coast. Van Oord’s offshore wind installation vessel Aeolus and special service support vessel (SSSV) Baltic Explorer are expected […]

  • 20 February 2024
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The first Siemens Gamesa 108-metre-long wind turbine blades have left its manufacturing factory in Hull for the Moray West offshore wind project in Scotland. Nine of the 180 blades destined for the 882 MW offshore wind farm were loaded onto the Rotra Mare transporter ship at the Siemens Gamesa blade factory in Hull, and are […]

  • 24 April 2024
    Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The first of two offshore substations built for the Hai Long 2 and Hai Long 3 offshore wind projects has set sail from Vung Tau, Vietnam, and is en route to the Taiwan Strait. A consortium comprising Semco Maritime and PTSC Mechanical & Construction (PTSC M&C) is responsible for delivering the two offshore substations for […]

  • 26 March 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first Siemens Gamesa wind turbine blades and tower components for Ocean Winds’ Moray West offshore wind farm have arrived at the Port of Nigg in Scotland. The 882 MW offshore wind farm, developed by Ocean Winds, will comprise 60 wind turbines and will be the first project to feature Siemens Gamesa’s SG 14-222 DD model. The turbines […]

  • 26 February 2024
    Manufacturing, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Siemens Gamesa has rolled out the first 14 MW wind turbine nacelles at its Cuxhaven plant in Germany as the production of wind turbine components for the Moray West offshore wind farm is currently underway. The first batch of nacelles is now awaiting shipment and installation at the Moray West project site offshore Scotland, Siemens […]

  • 4 April 2024
    Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The first 14 MW turbine nacelles have been loaded onto the roll-on/roll-off (Ro-Ro) vessel, Rotra Vente, at Siemens Gamesa’s Cuxhaven plant in Germany. They are destined for the Moray West offshore wind farm and are heading toward the Port of Nigg, Scotland, according to AIS data available online. The vessel left Cuxhaven on 3 April […]

  • 14 February 2024
    Business & Finance, Contracts & Tenders, Supply Chain, Vessels

    Siemens Gamesa has awarded a 15-year charter contract to Cyan Renewables for its first service operation vessel (SOV) in Asia. The contract will begin in 2026 and the SOV will be used to service 73 Siemens Gamesa SG 14-222 DD wind turbines at the Hai Long offshore wind farms, located about 50 kilometres off the […]

  • 28 May 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    All transition pieces (TPs) have been installed at the 882 MW Moray West offshore wind farm in Scotland, according to a Notice to Mariners issued on 27 May by Moray Offshore Windfarm (West). In addition, Cadeler’s Wind Orca has installed ten wind turbines so far at the offshore site in the Moray Firth. The final […]

  • 2 February 2024
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    EEW Korea Heavy Pipe Construction (EEW KHPC) has loaded out the first twelve pin piles for the jacket foundations that will be installed at the Hai Long offshore wind farm in Taiwan. The first batch of pin piles, whose load-out took place at the quayside in the port of Gwangyang on 31 January, will soon […]

  • 26 June 2024
    Business & Finance, Contracts & Tenders, Supply Chain

    UK-headquartered 2H has been awarded a four-year integrity management (IM) contract for the 882 MW Moray West offshore wind farm in Scotland. The contract’s scope covers IM for all balance of plant (BoP) equipment, including the wind turbine’s monopile foundations and tower structures, inter-array and export cables, and offshore and onshore substations. According to 2H, […]

  • 20 May 2024
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The first offshore substation (OSS) topside has been installed at the Hai Long offshore wind farm by CSBC-DEME Wind Engineering’s (CDWE) Green Jade vessel in Taiwan. The 1,022 MW Hai Long comprises two offshore wind farms, the 532 MW Hai Long 2 and the 512 MW Hai Long 3 and is being developed in three phases as […]

  • 22 April 2024

    Moray West, an offshore wind farm in the outer Moray Firth, Scotland, has installed the first of 60 Siemens Gamesa SG 14-222 DD wind turbines. Supplied with “Power Boost”, each turbine can generate up to 14.7 MW output. The 882 MW wind farm is being developed by Ocean Winds. The pre-assembly activity of the 60 […]

  • 12 April 2024
    Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    Offshore construction has started at the Hai Long offshore wind farm site in Taiwan with the vessel Green Jade installing pin piles for the project’s jacket foundations. The Hai Long Offshore Wind Project joint venture (Northland Power, Yushan Energy, Mitsui & Co., and Gentari) announced the official start of offshore construction on 11 April. The […]

  • 8 May 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The jacket foundation for the Hai Long 2 offshore substation has been installed by CSBC-DEME Wind Engineering’s (CDWE) Green Jade vessel in Taiwan. Hai Long comprises two offshore wind farms, the 532 MW Hai Long 2 and the 512 MW Hai Long 3 and is being developed in three phases as Hai Long 2 is […]

  • 15 April 2024
    Equipment, Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Belgian offshore construction company DEME, using its vessel Orion, has completed the installation of monopiles at the Moray West offshore wind farm site in Scotland.  Monopile installation at Moray West started in October 2023, with Boskalis’s vessel Bokalift 2 deployed for the work and Orion taking over in February. DEME’s Orion installed 29 monopiles for Ocean […]

  • 21 May 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    Van Oord’s offshore installation vessel, Aeolus, has installed the first of 100 monopile foundations at the 1.4 GW Sofia project in the UK, RWE’s largest offshore wind farm to date. The Sofia offshore wind farm is located on Dogger Bank in the central North Sea, 195 kilometres from the North East coast of the UK. […]

  • 5 July 2024
    Business development, Equipment, Fixed-Bottom, Foundations, Innovation, Supply Chain, Technology

    A consortium comprising some of the world’s leading offshore wind developers and Tier 1 suppliers have initiated a joint industry project that aims to commercialise a new foundation connection technology developed by the Netherlands-based company C1 Connections. “With the increasing size of wind turbines, the traditional L-flange design has reached a point where in cases […]

  • 17 April 2024
    Equipment, Fixed-Bottom, Supply Chain, Vessels

    As construction work has started on Taiwan’s 1 GW Hai Long offshore wind farm with the vessel Green Jade installing the first jacket foundation pin piles, TWD and Seatools each revealed their contracts for the provision of pre-piling and piling equipment and services with the vessel owner, CSBC-DEME Wind Engineering (CDWE). The Hai Long joint […]

  • 17 January 2024
    Equipment, Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update

    The installation of pin piles for the jacket foundations on Taiwan’s 1,044 MW Hai Long offshore wind farm is expected to start in March. CAPE Holland has been contracted to supply its CAPE Vibro Lifting Tools to CSBC-DEME Wind Engineering (CDWE), whose vessel Green Jade will be installing the piles. CDWE signed a contract for […]

  • 18 January 2024
    Equipment, Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update

    NOTE: The article was amended on 23 January to include the parts of Dogger Bank Wind Farm’s Supporting Statement filed to the Marine Management Organisation (MMO) that concern the reasons for the delay of the monopile installation on Dogger Bank B. The installation of foundations on two UK offshore wind projects, the 1.4 GW Sofia […]

  • 20 June 2024
    Contracts & Tenders, Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Skyborn Renewables has signed an updated Master Supply Agreement with Siemens Gamesa for the delivery of 63 SG 14-236 DD wind turbines, with a power boost of 15 MW, for its 945 MW Gennaker offshore wind project in the German Baltic Sea. The agreement strengthens the long-term partnership between the two companies and replaces the […]

  • 26 January 2024
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    The first steel cutting of the monopiles for RWE’s Thor offshore wind farm in Denmark has taken place at Dajin Offshore Heavy Industry’s Penglai facility in China, marking the start of the project’s construction phase. In April 2023, Dajin was selected to deliver 36 monopiles as well as secondary structures and electrical outfitting for the […]

  • 8 July 2024
    Contracts & Tenders, Foundations, Supply Chain

    Ramboll has been selected as the foundation designer for the Gennaker offshore wind project in the German Baltic Sea, owned by Skyborn Renewables. Under the contract, Ramboll will be responsible for developing the basic and detailed design of 63 monopile foundations supporting Siemens Gamesa’s SG 14-236 DD wind turbines. In addition, the company’s role extends […]