928 results found for 'Dogger Bank Wind Farm'

928 results found for 'Dogger Bank Wind Farm'
Order results by

A list of search results

  • 8 November 2024
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Production of the last transition piece (TP) for the 3.6 GW Dogger Bank Wind Farm, the world’s largest offshore wind farm under construction, is underway at Smulders facility in Hoboken, Belgium. The consortium comprising Sif and Smulders was awarded contracts for the manufacture of all monopiles and transition pieces for the three-phased Dogger Bank Wind […]

  • 31 March 2025
    Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    The offshore installation vessel Seaway Strashnov will install the remaining two monopiles at the Dogger Bank B offshore wind farm site next month. According to a Notice to Mariners from the project, the work is planned to commence on 7 April and continue until approximately 30 April. The heavy lift vessel, owned by Seaway7, completed […]

  • 12 December 2024
    Business & Finance, Contracts & Tenders, Supply Chain, Wind Turbines

    Dogger Bank Wind Farm, a joint venture between SSE Renewables, Equinor, and Vårgrønn, has signed a vessel reservation agreement with Seaway7 to charter a second turbine installation vessel to support the ongoing delivery of the offshore wind farm off the coast of England. Starting in 2026, the Seaway Ventus jack-up installation vessel is planned to […]

  • 23 April 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    After installing all 95 monopiles at Dogger Bank B, the offshore installation vessel Seaway Strashnov has moved on to the third phase of the UK’s Dogger Bank Wind Farm, where it has now begun foundation work at Dogger Bank C. Seaway Strashnov and Seaway Alfa Lift commenced the installation work at Dogger Bank B in the spring of […]

  • 3 January 2025
    Fixed-Bottom, Foundations, Project Updates, Vessels, Wind Farm Update

    The offshore installation vessel Seaway Strashnov has installed all but two monopile foundations at the Dogger Bank B offshore wind site in the UK and will return in the second quarter of 2025 to complete the installation. Five more transition pieces (TPs) are also left to be installed, according to the latest notices to mariners […]

  • 31 January 2025
    Business & Finance, Vessels

    UK-headquartered North Star has named and delivered its latest service operation vessel (SOV), completing its fleet of vessels chartered for long-term service at the 3.6 GW Dogger Bank offshore wind farm. The Grampian Tweed is the fourth SOV introduced ahead of schedule to support the Dogger Bank offshore wind farm, owned by a consortium of […]

  • 9 December 2024
    Business & Finance, Cables, Contracts & Tenders, Fixed-Bottom, Grid Connection, Supply Chain

    Proserv has been awarded a contract by DEME Offshore to de-risk offshore wind operations at Dogger Bank C, the third phase of the 3.6 GW Dogger Bank Wind Farm project in the UK. According to Proserv, the company will utilise its Electro Cable Guard (ECG) system to identify signs of transmission cable failure far earlier, […]

  • 1 April 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    Spain’s Navantia Seanergies has completed the load-out of the High Voltage Direct Current (HVDC) substation jacket for the 1.2 GW Dogger Bank C offshore wind platform in the UK. The load-out of the substation jacket, which will be installed at the Dogger Bank Wind Farm developed by SSE Renewables, Equinor, and Vårgrønn, was completed at […]

  • 17 December 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    Seaway7, part of the Subsea7 Group, has been awarded a contract by Inch Cape Offshore Limited (ICOL), a joint venture between ESB and Red Rock Renewables, for the transport and installation of pin-pile jacket foundations and transition pieces (TPs) for the 1.1 GW offshore wind project. The deal is worth between USD 150 million and […]

  • 25 February 2025
    Business development, Innovation, Technology, Vessels

    Dutch company Next Ocean is looking at a global reach for its technology that predicts waves and vessel motions minutes beforehand. Following a period of demonstration deployments of WavePredictor and the first vessels using it commercially, Next Ocean says it is witnessing the technology becoming standard equipment onboard vessels working in offshore wind and other […]

  • 3 October 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    SSE has revealed that the completion of Dogger Bank A, the first of the three phases of the UK’s Dogger Bank Wind Farm, is projected for the second half of 2025, which is later than the previously expected first half of the year. In its interim earnings report released on 3 October, SSE said that […]

  • 26 March 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    TGS is scheduled to start geophysical survey work across the Dogger Bank South (DBS) offshore wind farm sites in the UK on 27 March. According to a Notice to Mariners issued by the DBS project, the Norway-based energy data and intelligence company will be using the seismic vessel Ramform Vanguard, supported by the guard/scout vessel […]

  • 11 April 2025
    Fixed-Bottom, Foundations, Innovation, Project Updates, Supply Chain, Technology, Wind Farm Update

    RWE, in collaboration with Hydrotechnik Offshore, a Germany-based bubble curtain developer, has deployed the underwater noise abatement technology during monopile installation at the Sofia offshore wind farm, marking the first time the technology has been used in the UK. Currently under construction on Dogger Bank, 195 kilometres off the UK coast, the 1.4 GW Sofia […]

  • 21 March 2025
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    Cadeler’s wind turbine installation vessel (WTIV) Wind Peak is en route to the site of the Sofia offshore wind farm with the first set of Siemens Gamesa’s SG 14-222 DD turbine components. The vessel departed the port of Hull on 20 March, according to the available AIS data, and is heading towards the project site […]

  • 4 November 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Van Oord, using its jack-up vessel Aeolus, has installed 34 of the total 100 monopiles at the Sofia offshore wind farm site in the UK, according to a Notice to Mariners issued on 29 October. Aeolus installed the first monopile at the Sofia project site, located on Dogger Bank in the central North Sea, in […]

  • 27 February 2025
    Authorities, Business & Finance, Fixed-Bottom, Grid Connection, Planning & Permitting

    Ofgem is inviting tenders to own and operate electricity transmission links worth GBP 4 billion (about EUR 4.8 billion), connecting the Sofia offshore wind farm to Great Britain’s mainland energy network. Ofgem has opened the Offshore Transmission Owner (OFTO) regime Tender Round 12, which invites investors to bid to own and operate infrastructure connecting RWE’s […]

  • 7 November 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Vårgrønn has agreed to acquire a 27.4 per cent stake in the 288 MW Baltic 2 offshore wind farm from PGGM Infrastructure Fund, marking its entry into the German market. Following the deal closing, Vårgrønn and EnBW will own 27.4 per cent and 50.1 per cent, respectively, with EnBW responsible for operations and maintenance activities. […]

  • 5 December 2024
    Business & Finance, Fixed-Bottom, Floating Wind

    Shell has decided to cease investments in new offshore wind developments as part of a review of the Shell Energy business. The oil and gas major, which has built a significant portfolio of renewable energy and clean fuel projects, will not abandon its existing offshore wind projects, but investing in new offshore wind farms is […]

  • 21 January 2025
    Authorities, Fixed-Bottom, Planning & Permitting

    The US Bureau of Ocean Energy Management (BOEM) and the Bureau of Safety and Environmental Enforcement (BSEE) have completed the review and approved the revised Construction and Operations Plan (COP) for the Vineyard Wind 1 offshore wind farm. Last week, the federal government lifted the suspension on Vineyard Wind’s installation of the remaining GE Vernova […]

  • 17 March 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    RWE’s Sofia offshore wind farm in the UK has reached several major milestones in the construction of foundations and onshore and offshore electrical systems and is now preparing for the first turbine installation expected in the coming weeks. Last week, Cadeler’s wind turbine installation vessel (WTIV) Wind Peak arrived, ready to transport the first set […]

  • 1 January 2025
    Business development, Equipment, Fixed-Bottom, Floating Wind, Operations & Maintenance, Project Updates, Supply Chain, Technology, Vessels, Wind Farm Update, Wind Turbines

    New wind turbine models, vessels and equipment, and project updates were the most read topics on offshoreWIND.biz in 2024. In this overview, we are bringing the ten most popular news in 2024. In January 2024, Siemens Gamesa received a EUR 30 million grant from the EU for a project called Highly Innovative Prototype of the […]

  • 24 October 2024
    Cables, Grid Connection, Project Updates, Vessels, Wind Farm Update

    Van Oord’s new, next-generation cable-laying vessel (CLV) Calypso has begun installing cables at its first offshore wind project, marking its official debut. Calypso’s first project is RWE’s Sofia offshore wind farm, being constructed on Dogger Bank in the central North Sea, 195 kilometres from the North East coast of the UK, which, with a capacity […]

  • 10 February 2025
    Authorities, Floating Wind, Planning & Permitting, Ports & Logistics

    A new bill has been introduced in California’s state legislature that would add an assessment of funding opportunities for offshore wind port infrastructure to the Governor’s Five-Year Infrastructure Plan. Introduced on 6 February, Assembly Bill 472 would amend the definition of “infrastructure” in the California Infrastructure Planning Act to include offshore wind port infrastructure as […]

  • 22 November 2024
    Business development, Contracts & Tenders, Environment, Fixed-Bottom, Floating Wind, Planning & Permitting, Supply Chain

    The Netherlands is a pioneer in including nature enhancement stipulations in offshore (wind) energy tenders. The Dutch event for the international offshore energy and maritime industries, Offshore Energy Exhibition & Conference (OEEC), has also given nature enhancement a prime spot in this year’s edition, including it more prominently in the conference programme and on the […]

  • 16 January 2025
    Authorities, Business & Finance, Business development, Environment, Planning & Permitting

    Relying only on renewable energy targets and expecting the industry and economic growth would follow “does not work”, Mark van Stiphout, Deputy Head of Unit for Research, Innovation, Competitiveness and Digitalisation at European Commission’s DG Energy, said during a panel session about green growth at Offshore Energy Exhibition & Conference (OEEC) in November 2024. Van […]

  • 20 January 2025
    Business & Finance, Business development, Cables, Collaboration, Energy Islands, Environment, Green Hydrogen, Grid Connection, Industry, Infrastructure, Innovation, Market Outlooks, Offshore Platforms, Outlook & Strategy, Planning & Permitting, Technology, Transition

    Energy islands are no longer being considered in the Netherlands. Instead, the focus has been shifted to offshore energy hubs and interconnectors. With rising (cyber)security concerns as a result of a number of recent incidents in European waters, as well as the Russia-Ukraine war, diversification of the energy system is high on the agenda. Offshore […]