1015 results found for 'Baltic 2'

1015 results found for 'Baltic 2'
Order results by

A list of search results

  • 28 April 2026
    Contracts & Tenders, Fixed-Bottom, Operations & Maintenance, Supply Chain

    EnBW has awarded framework agreements for subsea inspection services across its offshore wind fleet in the Baltic Sea and North Sea, with RS Diving Contractor selected for both of the two lots covering the company’s assets in the Baltic Sea and the North Sea. The contracts, signed on 7 April, cover inspections executed using remotely […]

  • 23 February 2026
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    UK-registered Novastar Energy Holdings, a wholly-owned subsidiary of UAE-based HEA Energy, which bought three Seajacks vessels from Eneti in 2023, has secured a contract for Baltica 2, a 1.5 GW offshore wind farm being built by PGE and Ørsted in Poland. According to a contract award notice published this month on an EU tender website, […]

  • 20 March 2026
    Contracts & Tenders, Manufacturing, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Polish offshore wind tower manufacturer Baltic Towers has signed a cooperation agreement with Siemens Gamesa for the supply of the largest batch of wind turbine towers for the Baltica 2 offshore wind project in Poland, jointly developed by PGE Polska Grupa Energetyczna and Ørsted.  Baltic Towers was established in 2023 as a joint venture between […]

  • 5 August 2026
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Steelwind Nordenham has completed the delivery of all monopiles under its contract for the 1.5 GW Baltica 2 offshore wind farm in the Polish Baltic Sea, with the final two foundations shipped from the company’s port facility. Under its scope, Steelwind manufactured and delivered 34 monopiles for the project, processing around 56,000 tonnes of steel. […]

  • 11 May 2026
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Major offshore construction work has started on the 1.5 GW Baltica 2 offshore wind farm, developed by Ørsted and PGE Polska Grupa Energetyczna, as Van Oord has installed the first monopile foundations at the project site in the Polish Baltic Sea. The offshore installation campaign, for which Van Oord is using its vessels Aeolus and […]

  • 17 April 2026
    Contracts & Tenders, Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update

    OEG will provide crew transfer vessels (CTVs) during the construction of the Baltica 2 offshore wind farm in Poland, jointly developed by PGE Polska Grupa Energetyczna and Ørsted.  According to a contract award notice on the EU tenders’ website, on 27 February, Ørsted selected Opus Marine (which was acquired by OEG in 2022) to provide […]

  • 6 August 2026
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Elektrownia Wiatrowa Baltica – 2, the project company developing the 1.5 GW Baltica 2 offshore wind farm, has awarded contracts for two walk-to-work (W2W) accommodation vessels that will support construction and offshore operations at the project in the Polish Baltic Sea. The contracts were awarded through a tender procedure conducted by Ørsted on behalf of […]

  • 27 February 2026
    Authorities, Fixed-Bottom, Planning & Permitting, Wind Farm Update

    On 25 February, the President of the Polish Energy Regulatory Office (URE) published a formal update stating that the regulator has granted a “promise of concession” for the Baltica 2 offshore wind farm, which is jointly developed by Polish utility PGE and Danish energy company Ørsted. This is the second official concession promise issued for […]

  • 10 June 2026
    Business & Finance, Business development, Fixed-Bottom, Ports & Logistics, Project Updates

    Orlen Neptun and the Szczecin and Świnoujście Seaports Authority have signed a letter of intent to explore the expansion of the Świnoujście Offshore Terminal, Poland’s first installation terminal dedicated to offshore wind projects. The move comes one year after the facility entered operation and amid growing demand for offshore wind logistics infrastructure in the Baltic […]

  • 25 February 2026
    Grid Connection

    Lithuania, Latvia, and Germany are planning a joint offshore interconnector that would enable electricity trading between the Baltic countries and Germany and allow for the integration of up to 2 GW of offshore wind capacity in Lithuania and Latvia. The energy ministers of the three countries signed a joint declaration of intent on 18 February, […]

  • 13 April 2026
    Authorities, Business & Finance, Planning & Permitting

    The Polish government has introduced a new “local content” framework designed to increase the share of domestically generated value in large-scale investments, including energy projects, by modifying procurement practices and evaluation criteria. Speaking on 10 April, Prime Minister Donald Tusk stated that the government would strive to ensure that, wherever possible, Polish companies are prioritised […]

  • 24 March 2026
    Cables, Contracts & Tenders, Offshore Platforms, Supply Chain, Wind Turbines

    Bilfinger has been selected to provide supervision services for the Bałtyk 2 and Bałtyk 3 offshore wind farms in the Polish Baltic Sea, developed by Equinor and Polenergia. The company’s scope covers supervision of the installation of offshore substations, wind turbines and more than 120 kilometres of export cables, including landfall connections to the onshore […]

  • 20 February 2026
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Boskalis has completed the preparation of 150 kilometres of inter-array cable routes at the 1.5 GW Baltica 2 offshore wind farm site in Poland. In 2023, Boskalis was awarded a contract for the transportation and installation of export and inter-array cables for the Polish offshore wind farm, owned by PGE and Ørsted. Under the contract, the Dutch […]

  • 26 May 2026
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Heerema Marine Contractors’ heavy-lift vessel Thialf has installed the first foundations at the Bałtyk 2 & 3 offshore wind farms, owned by Equinor and Polenergia, which said on 25 May that “the first dozen sets of monopiles and transition pieces” were in place at the project site in the Polish Baltic Sea. The monopiles, measuring […]

  • 5 August 2026
    Grid Connection, Offshore Platforms, Vessels

    German transmission system operator (TSO) 50Hertz has launched a preliminary market consultation to assess the availability of service operation vessel (SOV) and walk-to-work (W2W) solutions for the operation and maintenance (O&M) of its future offshore grid connection platforms in the German Baltic Sea. The non-binding consultation has been launched to support a future procurement and […]

  • 18 February 2026
    Fixed-Bottom, Foundations, Grid Connection, Offshore Platforms, Project Updates, Supply Chain, Wind Farm Update

    Offshore construction has begun on the Bałtyk 2 and Bałtyk 3 offshore wind projects in Poland, developed by Equinor and Polenergia, which will together have 100 wind turbines and an installed capacity of 1.4 GW. The 2026 offshore construction campaign will see the installation of 100 monopiles, transition pieces (TPs), offshore substation components, subsea cables […]

  • 27 February 2026
    Vessels

    Heerema Marine Contractors has put its semi-submersible crane vessel (SSCV) Thialf, the second-largest SSCV in the world, through a lifetime extension programme, with the vessel currently undergoing the first stage of the work in Rotterdam, ahead of its mobilisation for a Polish offshore wind project next month. Thialf will undergo what Heerema Marine Contractors says is […]

  • 7 May 2026
    Cables, Contracts & Tenders, Fixed-Bottom, Supply Chain

    SPIE Global Services Energy has been awarded a contract by Seaway7 to deliver inter-array cable termination and testing works for the Bałtyk 2 and Bałtyk 3 offshore wind farms in Poland.   The work will be carried out by SPIE Wind Connect, the group’s specialist high-voltage wind power business unit, with the offshore campaign scheduled […]

  • 16 June 2026
    Energy Islands, Fixed-Bottom, Floating Wind, Grid Connection, Infrastructure, Ports & Logistics, Power-to-X, Research & Development, Vessels

    Offshore wind farms, energy islands, ports and proposed “Offshore Power Zones” could together form the foundation of an integrated maritime energy system capable of supporting large-scale vessel electrification across Northern Europe, according to a study by Maersk’s Stillstrom, Baltic Energy Island and the Port of Roenne. In a whitepaper titled Bornholm Energy Island: Powering Maritime […]

  • 11 February 2026
    Fixed-Bottom, Grid Connection, Wind Farm Update

    Germany’s total offshore wind power generation in 2025 amounted to 26.1 TWh, of which 20.8 TWh came from the North Sea and 5.38 TWh from the Baltic Sea, according to TenneT Germany, the transmission system operator (TSO) in charge of the country’s North Sea grid. In this article: With onshore wind farms contributing 106.5 TWh […]

  • 18 June 2026
    Authorities, Business & Finance, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    Germany has rejected a request from TotalEnergies to return one of its offshore wind sites in the North Sea to the State, with the country’s economy minister underlining that a concession award constitutes a binding commitment, according to a Bloomberg report from 17 June. The minister’s comment comes days after TotalEnergies confirmed it had been […]

  • 7 August 2026
    Authorities, Floating Wind, Planning & Permitting, Project Updates, Wind Farm Update

    The Welsh government has granted Section 36 consent to the Llŷr Wind Farm, a floating wind test and demonstration project being developed by Cierco Energy in the Celtic Sea off Pembrokeshire. Llŷr was one of two projects selected in the Crown Estate’s 2021 leasing opportunity for early commercial-scale floating wind projects in the Celtic Sea, […]

  • 20 February 2026
    Contracts & Tenders, Fixed-Bottom, Planning & Permitting, Project Updates, Supply Chain, Wind Farm Update

    ELWIND has signed a contract with Haskoning for the design phase of the joint Estonian-Latvian state-run offshore wind project in the Baltic Sea. Haskoning’s work will include layout optimisation, transmission grid studies and integration of site investigations and environmental assessment. The Dutch company will carry out the project together with subconsultant partner Empire Engineering, which […]

  • 18 February 2026
    Grid Connection, Manufacturing, Offshore Platforms, Project Updates, Supply Chain

    McDermott has cut first steel for the offshore converter platform for TenneT’s LanWin1 offshore grid connection in Germany. The LanWin1 project will include an offshore converter station in the North Sea and an onshore converter station in the region of Wesermarsch. The platform will be delivered under a contract GE Vernova and McDermott International signed with the […]

  • 29 April 2026
    Contracts & Tenders, Operations & Maintenance, Supply Chain, Vessels

    HEA Energy has secured a new offshore wind operations and maintenance (O&M) contract in Europe, the company said via social media on 29 April, leaving the project and the client unnamed. The campaign, to be carried out at an offshore wind farm in the North Sea, is scheduled to begin in the summer of 2026. […]

  • 4 August 2026
    Authorities, Business development, Floating Wind, Planning & Permitting, Project Updates, Research & Development, Wind Farm Update

    Cierco Energy has signed an Agreement for Lease with the Crown Estate for its two test and demonstration projects off Wales, named Llŷr 1 and Llŷr 2, which are expected to use two different types of floating wind technology. The Llŷr projects were selected for development in 2021 in the Crown Estate’s leasing opportunity for early commercial-scale […]