Turbine Installation Starts at Rentel Offshore Wind Farm

A2Sea’s jack-up installation vessel Sea Installer left the Port of Ostend, Belgium, on 5 May with the first 7MW Siemens Gamesa wind turbines destined for installation at the 309MW Rentel offshore wind farm in the Belgian North Sea.

Source: Rentel NV

According to the vessel’s AIS, Sea Installer is currently located at the wind farm site some 40 kilometers off the coast of Ostend.

The first turbines are expected to generate electricity by mid-2018, while all 42 turbines will be installed at the Rentel wind farm after the summer, Rentel NV said.

The assembly of the turbines started in the Port of Ostend in mid-February after the first parts arrived at the REBO terminal.

Under the contract signed in April 2016, Siemens Gamesa is also in charge of the servicing and maintenance of the turbines.

The Rentel offshore wind farm is scheduled for full commissioning by the end of the year.

Related news

List of related news articles

Posted: 11 months ago

Ouyang Launches Wind Turbine Installation Vessel (Photos)

China’s Ouyang Offshore has launched its wind turbine installation vessel, OuYang 1, at Dayang...

Categories:
  • Vessels
Posted: 11 months ago
Posted: 11 months ago

Swedish Offshore Wind Farm Is No More

Offshore wind O&M specialist Ziton has completed the decommissioning of the Utgrunden offshore ...

Categories:
  • Business & Finance
Posted: 11 months ago
Posted: 11 months ago

Offshore Wind Majors Book Danish Turbine Test Sites

The Technical University of Denmark (DTU), the operator of the national test centres for large wind ...

Categories:
  • R&D
Posted: 11 months ago
Posted: 11 months ago

Virginia Affirms Offshore Wind Ambitions

Virginia’s Governor Ralph Northam has released the 2018 Virginia Energy Plan which calls for t...

Categories:
  • Authorities
Posted: 11 months ago