Search results for: Borssele 1&2

29762 results

A list of search results

  • 4 June 2020
    Wind Farm Update

    DEME Offshore’s jack-up vessel Innovation has completed the installation of the 94 monopile foundations at the Borssele 1 & 2 offshore wind project. The installation, which began in mid-January in the Dutch North Sea, was completed on time despite the COVID-19 crisis, DEME said. Sif provided 47 monopiles for the project and EEW SPC, the parent […]

  • 10 April 2020
    Wind Farm Update

    DEME has installed half of the 94 monopile foundations at the Borssele 1+2 offshore wind farm site.

  • 30 January 2020
    Wind Farm Update

    DEME Offshore’s jack-up vessel Innovation has installed 13 of the 94 monopile foundations on the 752MW Borssele 1&2 offshore wind farm in the Dutch North Sea, Ørsted said. Innovation is loading the monopiles and transition pieces at Sif’s Maasvlakte 2 facility before transporting and installing them at the site located some 22 kilometres off the […]

  • 13 January 2020
    Wind Farm Update

    DEME Group has installed the first foundations at Ørsted’s Borssele 1&2 offshore wind project in the Netherlands. DEME’s jack-up vessel Innovation loaded the first set of monopiles at Sif’s facility on Maasvlakte 2 earlier this month and transported them to the wind farm. “The first monopile installed was also the heaviest and tallest on the wind farm, […]

  • 14 May 2020
    Wind Farm Update

    Ørsted has provided an update on the ongoing offshore construction work at the 752 MW Borssele 1 + 2 offshore wind farm in the Dutch North Sea, saying that all activities are going according to plans. So far, DEME’s installation vessel Innovation has installed 73 out of the 94 monopile foundations at the site some […]

  • 29 April 2020
    Wind Farm Update

    Ørsted’s Borssele 1 & 2 offshore wind farm has delivered first power to the Dutch grid. According to the Danish company, the first Siemens Gamesa 8 MW turbine began producing electricity on 28 April. “This is a big milestone for Borssele 1 & 2. Ørsted is doing its utmost to allow the construction of the […]

  • 2 November 2018
    Contracts & Tenders, Jobs & Recruitment, Wind Farm Update

    Ørsted has selected ERSG to supply temporary specialist staff for the Borssele 1+2 offshore wind project in the Dutch North Sea.

  • 13 February 2020
    Vessels, Wind Farm Update

    DEME Offshore’s jack-up Innovation has installed 18 out of 94 monopile foundations on the 752MW Borssele 1+2 offshore wind farm in the Dutch North Sea. Innovation is loading the monopiles and the transition pieces at Sif’s facility on Maasvlakte 2 in Rotterdam and installing them at the site some 22 kilometres off the coast of […]

  • 7 November 2018
    Business & Finance, Contracts & Tenders, Grid Connection

    Nexans will provide up to 190km of inter-array cable rated at a maximum operating capacity of 72.5kV for the 752MW Borssele 1 and 2 offshore wind project in the Netherlands as part of the recently-announced contract.

  • 28 May 2019
    Wind Farm Update

    EEW Offshore Structures Britain has produced the first transition piece for the Borssele 1&2 offshore wind farm in the Dutch North Sea. The Teesside-based company rolled out the first of 35 transition pieces destined for Ørsted’s Borssele 1&2 project at the beginning of April. EEW SPC, the parent company of EEW OSB, is in charge of manufacturing 47 monopiles […]

  • 27 February 2020
    Grid Connection, Wind Farm Update

    The first inter-array cable has been installed at the Borssele 1 & 2 offshore wind project in the Netherlands. Nexans is providing up to 190km of inter-array cable rated at a maximum operating capacity of 72.5kV for the 752MW project, while Van Oord is in charge of the transport and installation. Van Oord is deploying its […]

  • 19 December 2017
    Contracts & Tenders, Technology

    Siemens Convergence Creators has signed an eight-year frame agreement with Ørsted for the supply and maintenance of SCADA Networks and Telecommunication Systems for Ørsted’s current and future offshore wind farms, with the offshore wind giant immediately placing its first order for Borssele 1 & 2.

  • 1 June 2020
    Wind Farm Update

    DEME Offshore’s jack-up vessel Innovation has arrived at the Borssele 1+2 offshore wind farm in the Dutch North Sea with the final monopiles. Innovation picked up the monopiles last night at Sif Rotterdam, a spokesperson from DEME Offshore said. Sif was in charge of providing 47 monopiles for the project, with EEW SPC, the parent […]

  • 13 April 2020
    Wind Farm Update

    The first Siemens Gamesa 8 MW turbine has been installed on the 752 MW Borssele 1+2 offshore wind farm in the Dutch North Sea. The team working on DEME’s jack-up Sea Challenger installed the wind farm’s first turbine over the weekend, Ørsted said. In total, the wind farm will comprise 94 of the Siemens Gamesa […]

  • 9 January 2020
    Ports & Logistics, Vessels, Wind Farm Update

    DEME Offshore’s jack-up vessel Innovation has loaded the first set of monopiles to be installed on the Borssele 1+2 offshore wind farm in the Dutch North Sea. Innovation loaded the first set of monopiles at Sif’s facility on Maasvlakte 2 in the Port of Rotterdam. DEME is in charge of transporting and installing the 94 monopile […]

  • 27 September 2019
    Contracts & Tenders, Grid Connection

    Dutch energy network company Alliander and Ørsted have signed an agreement through which Alliander will purchase green certificates from the Borssele 1+2 offshore wind farm. The agreement takes effect in 2021 and has a duration of fifteen years. Alliander aims to have a climate-neutral business operation by 2023. The annual CO2-emissions of the company are mainly […]

  • 24 October 2018
    Business & Finance, Contracts & Tenders, Jobs & Recruitment, Wind Farm Update

    UK-based EEW OSB has secured a contract to provide 35 transition pieces for Ørsted’s Borssele 1 + 2 offshore wind farm in the Dutch North Sea.

  • 1 May 2020
    Operations & Maintenance

    NHV Group has started carrying out its helicopter services for the Borssele 1 & 2 offshore wind farm in the Netherlands. The flights depart from NHV’s recently installed base in Arnemuiden, Midden-Zeeland, to the project site located 23km from Westkapelle. The company stated it had taken delivery of a new H145 aircraft for the Midden-Zeeland […]

  • 17 March 2020
    Wind Farm Update

    30 monopile foundations and 14 inter-array cables have so far been installed on the 752MW Borssele 1 + 2 offshore wind farm in the Dutch North Sea, Ørsted said. Located some 23 kilometres off the coast of Zeeland, Borssele 1 + 2 will comprise 94 Siemens Gamesa 8MW wind turbines scheduled to be operational by […]

  • 28 January 2020
    Contracts & Tenders, Wind Farm Update

    Ørsted has contracted Manor Renewable Energy (MRE) to provide temporary power during the turbine commissioning phase at the Borssele 1 + 2 offshore wind project.

  • 29 November 2018
    Contracts & Tenders

    Ørsted has awarded Atlas Professionals with a contract to supply personnel for the Borssele 1 & 2 offshore wind farm in the Netherlands.

  • 9 January 2019
    Wind Farm Update

    EEW Offshore Structures (Britain) has commenced the production of the transition pieces for the Borssele 1 & 2 offshore wind farm in the Dutch North Sea. A ceremony was held to mark the cutting of the first steel at the company’s site at Haverton Hill in the UK. EEW OSB won the contract for the production of 35 transition pieces […]

  • 17 March 2020
    Wind Farm Update

    Bladt Industries A/S has loaded out the last six transition pieces and anode cages for the Borssele 1 & 2 offshore wind farm project in the Netherlands. Bladt Industries’ scope covered the manufacture of 59 transition pieces, each one weighing approximately 390 tonnes, with a diameter of up to 6 metres and a length of […]

  • 3 December 2019
    Wind Farm Update

    SAL Heavy Lift’s multi-purpose cargo ship Svenja has arrived at the Redcar Bulk Terminal, the UK, to pick up the third batch of transition pieces for the Borssele 1+2 offshore wind project. Svenja is picking up six transition pieces, which were produced by EEW Offshore Structures Britain (OSB) and barged down to the Redcar terminal […]

  • 30 May 2018
    Grid Connection, Wind Farm Update

    Work on the jacket foundation for the 700MW Borssele Alpha offshore transformer station is in full swing at HSM Offshore’s yard in Schiedam, the Netherlands, as this photo shared by Ørsted shows.

  • 13 November 2018
    Contracts & Tenders, Jobs & Recruitment, Wind Farm Update

    UK-based recruitment company Light Source People has won a contract for the supply of temporary staff for Ørsted’s Borssele 1 + 2 offshore wind project in the Netherlands.