970 results found for 'Arcadis Ost 1'

970 results found for 'Arcadis Ost 1'
Order results by

A list of search results

  • 5 December 2025
    Contracts & Tenders, Fixed-Bottom, Supply Chain

    Elektrownia Wiatrowa Baltica – 1, a project company set up by PGE Polska Grupa Energetyczna (PGE), has issued a contract notice for geotechnical investigation services for its 900 MW Baltica 1 offshore wind project. The work is planned to be carried out along the export cable route and in the offshore wind farm area of […]

  • 4 November 2025
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    PGE Polska Grupa Energetyczna (PGE) has obtained environmental approval for its 900 MW Baltica 1 offshore wind project, clearing the way for its participation in Poland’s upcoming offshore wind auction on 17 December 2025. The approval was issued by the Regional Directorate for Environmental Protection in Gdańsk. “This is a clear signal to the market […]

  • 8 July 2025
    Business & Finance, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Haesong Offshore Wind Company has signed a grid interconnection agreement with Korea Electric Power Corporation (KEPCO) for the Haesong Offshore Wind 1 and Haesong Offshore Wind 3 projects. Haesong Offshore Wind 1 and 3 projects are managed and funded by Copenhagen Infrastructure Partners (CIP), while project development, including implementation, permitting, and technical development, is carried […]

  • 27 June 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    The jacket foundation installation at Ørsted’s Greater Changhua 2b & 4 offshore wind farms is nearing completion, with 61 out of 66 foundations already installed at the site in Taiwan. Additionally, a third of the wind turbines for the project are now in place. Offshore construction of the 920 MW Greater Changhua 2b and 4 […]

  • 31 October 2025
    Authorities, Business & Finance, Contracts & Tenders, Fixed-Bottom, Planning & Permitting

    The Dutch government has confirmed that no applications were submitted for the latest offshore wind tender for the 1 GW Nederwiek I-A site in the North Sea. The tender closed on 30 October without bids, the Netherlands Enterprise Agency (RVO) said in a press release issued the same day. In a letter to Parliament, Dutch […]

  • 30 July 2025
    Cables, Contracts & Tenders, Grid Connection, Supply Chain

    Prysmian has awarded two contracts to Next Geosolutions (NextGeo), one of which is in the Dutch offshore wind market, where NextGeo will carry out export cable route surveys for the IJmuiden Ver Alpha and Nederwiek 1 offshore wind sites. The second contract NextGeo secured with Prysmian is for the Bay of Biscay interconnection project, an […]

  • 17 July 2025
    Fixed-Bottom, Grid Connection, Manufacturing, Offshore Platforms, Project Updates, Supply Chain, Wind Farm Update

    The offshore substation for the 1 GW Thor offshore wind farm has left HSM Offshore Energy’s Schiedam yard in the Netherlands and is on its way to the project site in the Danish North Sea. “[The] sail-away of the fully assembled substation for THOR is an important step for us in the project team”, said […]

  • 8 July 2025
    Business & Finance, Environment, Fixed-Bottom, Floating Wind, Research & Development

    Allocating just 1 per cent of the global offshore wind investments from now until 2050, which are projected to be USD 6 trillion (approximately EUR 5.1 trillion), to marine conservation and restoration could restore millions of square kilometres of marine ecosystems, a new international study has found. The scientists who conducted the study have urged […]

  • 4 September 2025
    Floating Wind, R&D, Technology

    Floating offshore wind projects featuring Principle Power’s WindFloat technology have delivered more than 1 TWh of energy production since the first pilot project was installed in 2011, the company announced on 3 September. The 1 TWh output includes generation from WindFloat 1, a 2 MW pilot project in Portugal (2011-2016) and Scotland (2018-2020); WindFloat Atlantic, […]

  • 23 December 2025
    Authorities, Planning & Permitting, Project Updates, Safety, Wind Farm Update

    The US Department of Interior has paused the leases and suspended construction at all large-scale offshore wind projects currently under construction in the United States, citing ”national security risks identified by the Department of War in recently completed classified reports.” The five projects have a combined capacity of 5.8 GW and include Coastal Virginia Offshore […]

  • 15 May 2025
    Operations & Maintenance

    German transmission system operator (TSO) 50Hertz has unveiled its plans to build a new operating site in Rostock on the Baltic Sea to support its offshore operations. The 90-million facility is scheduled to be completed in 2028. The investment costs for the new location amount to around EUR 90 million, with Germany’s federal state of […]

  • 22 July 2025
    Business development, Environment, Research & Development

    A research project carried out by The Oyster Restoration Company (TORC) and supported by RWE has established that large-scale native oyster reef restoration at offshore wind farms in the North Sea is feasible. “Flat oysters are an important species because they can create reefs that provide food and breeding grounds for many other species. Due […]

  • 4 July 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The fully assembled offshore substation for the 1 GW Thor offshore wind farm has been loaded out at HSM Offshore Energy’s Schiedam yard in the Netherlands. Both the jacket and the topside are now on the barges, and the structures are being prepared for sail-away to their destination off the Danish coast. In 2022, RWE, […]

  • 15 December 2025
    Cables, Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    Jan De Nul has installed three HVAC subsea cables, delivered by Hellenic Cables, between TenneT’s offshore converter station DolWin kappa and Nordseecluster 1 and 2 sites in the German North Sea. The two locations make up the 660 MW Nordseecluster A offshore wind farm, which itself is part of a bigger, two-phased Nordseecluster project. With […]

  • 10 December 2025
    Authorities, Fixed-Bottom, Floating Wind, Grid Connection, Planning & Permitting

    The European Commission just published a European Grids Package that includes Guidance on Contracts for Difference (CfDs), making the offshore wind industry’s much-sought-after procurement model soon to be mandated by the EU. While the new package has yet to be adopted and will serve as a foundation for EU and national legislation moving forward, a […]

  • 19 November 2025
    Business & Finance, Business development

    [PRESS RELEASE BY NAVINGO BV] The energy is rising as we enter the final countdown to the 18th edition of the Offshore Energy Exhibition & Conference (OEEC), taking place on 25–26 November at RAI Amsterdam. In less than one week, thousands of professionals from across the offshore energy sector will gather for two days dedicated […]

  • 21 November 2025
    Floating Wind, Foundations, Supply Chain, Technology

    BayWa r.e. has received concept certification from DNV for its BayFloat floating wind semi-submersible concrete substructure and mooring system design. The design was validated using the 22 MW generic reference turbine “IEA-22-280-RWT”. The certification process was conducted in accordance with DNV-SE-0422:2021-09 “Certification of floating wind turbines” scheme, including DNV-ST-0119:2021-06 “Floating wind turbine structures” as the […]

  • 22 December 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The business alliance formed by Navantia Seanergies and Windar Renovables has completed the manufacturing of 45 monopiles for the East Anglia THREE offshore wind farm, developed by Iberdrola in the UK North Sea. The Navantia-Windar consortium is delivering 45 monopiles for the 1.4 GW East Anglia Three offshore wind farm under a contract with ScottishPower Renewables, […]

  • 15 December 2025
    Authorities, Business & Finance, Business development, Floating Wind, Innovation

    Norwegian state enterprise Enova, owned by the Ministry of Climate and Environment, has launched a call for applications for a competition round to award funding to small-scale floating wind projects. Projects that can apply are those looking to test and demonstrate new solutions that can lower the cost of floating offshore wind energy, with the […]

  • 6 August 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The consortium of Navantia Seanergies and Windar Renovables has delivered the last monopiles to Iberdrola for the 315 MW Windanker offshore wind farm in the German Baltic Sea. The monopile foundations have been produced at the factory that both companies operate jointly at the Navantia Seanergies shipyard in Fene, Spain. Each of the units measures […]

  • 23 August 2025
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    Only days after Ørsted reported in its half-year results that Revolution Wind was at 80 per cent of completion, the US Department of the Interior’s (DOI) Bureau of Ocean Energy Management (BOEM) issued a stop-work order halting all offshore construction activities on the 704 MW project that is scheduled to start feeding electricity into Connecticut […]

  • 18 June 2025
    Grid Connection, Onshore Infrastructure, Project Updates, Wind Farm Update

    Danish transmission system operator (TSO) Energinet has completed the construction work related to the connection of the 1 GW Thor offshore wind farm to the national grid. The construction work began in January 2023 and has been completed on time, said Energinet. The scope of work included moving 95,000 cubic metres of soil and laying […]

  • 30 June 2025
    Grid Connection, Onshore Infrastructure, Project Updates, Wind Farm Update

    Equinor and Polenergia’s Bałtyk 2 and Bałtyk 3 offshore wind farms in Poland have entered the construction phase, with work on the onshore infrastructure now underway. After the final investment decisions were made in May this year, Bałtyk 2 and Bałtyk 3 offshore wind farms have entered the implementation phase. Almost 200 people took part […]

  • 5 September 2025
    Authorities, Business & Finance, Project Updates, Wind Farm Update

    Revolution Wind, a joint venture (JV) between Ørsted and a consortium led by Skyborn Renewables, filed a complaint in the US District Court for the District of Columbia on 4 September, challenging the stop-work order issued by the US Department of the Interior’s (DOI) Bureau of Ocean Energy Management (BOEM). The states of Connecticut and […]

  • 24 December 2025
    Business & Finance, Collaboration, Fixed-Bottom, Industry, Outlook & Strategy, Project Updates, Transition, Wind Farm Update

    Ørsted has signed an agreement with Cathay Life Insurance, and its affiliate Cathay Power, under which Cathay will acquire a 55 per cent ownership stake of Ørsted’s 632 MW Greater Changhua 2 offshore wind farm. Located approximately 50–60 kilometres off the coast of Changhua County, the Greater Changhua 2 site comprises the 295 MW Greater Changhua 2a, which is operational, […]

  • 2 September 2025
    Business & Finance, Business development, Fixed-Bottom, Foundations, Manufacturing, Supply Chain

    Dutch offshore wind foundation manufacturer, Sif Group, is facing a delay in the ramp-up of production at its new monopile production facility at Maasvlakte 2 in Rotterdam and expects to achieve this in the first half of 2026, instead of this year. Also in this article: In its half-year results for 2025, the company reported a […]