482 results found for 'moray east'

482 results found for 'moray east'
Order results by

A list of search results

  • 2 March 2023
    Business & Finance, Wind Farm Update

    Japan’s Inpex Corporation has acquired a 16.7 per cent stake in the 950 MW Moray East offshore wind farm. Moray East is located approximately 22 kilometers off the Moray East coast of Scotland in the United Kingdom. The wind farm has been in operation since April 2022. The acquisition was enabled through an agreement between […]

  • 10 August 2020
    Grid Connection, Wind Farm Update

    The first of the three Offshore Transformer Modules (OTMs), ME OSP 3, has been installed at the 950 MW Moray East wind farm offshore Scotland. Siemens Energy shipped out the wind farm’s first OTM, ME OSP 2, for offshore installation on 30 June. This OTM will be installed later this week, a spokesperson for DEME […]

  • 7 June 2019
    Ports & Logistics

    DEME Offshore has selected Global Energy Group to provide the Port of Nigg as a staging port for the Moray East offshore wind farm. Under the contract, the Port of Nigg will be used for receiving the completed turbine jacket foundations destined for the 950MW project. “Using Nigg for jackets complements our previous announcement of the Port […]

  • 6 September 2021
    Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel Blue Tern has seven more Vestas 9.5 MW units to install at the 100-turbine Moray East offshore wind farm in Scotland. The first wind turbines were installed at the project site some 22 kilometres off Aberdeenshire in January by the installation vessel Bold Tern, which left the site in May […]

  • 7 December 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Siemens has selected Smulders to build the three Offshore Transformer Modules (OTMs) for the 950MW Moray East offshore wind farm.

  • 7 April 2021
    Contracts & Tenders, Wind Farm Update

    RES has won a contract to provide control point, balancing, and asset monitoring services during commissioning and early operations at the 950 MW Moray East wind farm offshore Scotland. RES’ 24/7/365 Control Centre, based in Glasgow, will work as the interface between Moray East and National Grid to support the energisation of 100 turbines at […]

  • 31 August 2020
    Wind Farm Update

    The jacket foundation for the third offshore transformer module (OTM) for Moray East offshore wind farm has been installed at the site off the Scottish coast. According to the project’s latest Notice of Operations, the jack-up vessel Seajacks Scylla installed the OSP1 jacket on 30 August. Meanwhile, the OSP1 topside was scheduled to sail out […]

  • 13 November 2020
    Authorities, Contracts & Tenders, Grid Connection

    Ofgem will open a tender round for the offshore transmission licences for the Moray East and Triton Knoll offshore wind farms on 30 November. The authority issued a notice on 12 November, informing that the projects fulfilled all necessary conditions in accordance with regulation, including the submitted requests for qualifying projects, received payments and security […]

  • 6 May 2021
    Vessels, Wind Farm Update

    32 out of the 100 Vestas V164-9.5MW wind turbines have been installed at the 950 MW Moray East wind farm offshore Scotland. The wind turbine installation is being carried out by Fred. Olsen Windcarrier’s jack-up vessel Bold Tern. The first turbines were installed some 22 kilometres off the Aberdeenshire coast during the second half of […]

  • 9 November 2020
    Grid Connection, Wind Farm Update

    Work to install the onshore cable which will connect the 950 MW Moray East offshore wind farm to the Scottish grid has ended, Siemens Energy said. The onshore cable, which starts near Banff, Aberdeenshire, takes the power generated offshore from the three 220kV subsea cables, and transmits it to the new onshore substation at New […]

  • 26 June 2019
    Contracts & Tenders, Grid Connection, Wind Farm Update

    ABB has won an order from MHI Vestas Offshore Wind to supply its WindSTAR transformers for installation in wind turbines on the 950MW Moray East wind farm offshore Scotland. Under the project, 100 transformers manufactured in ABB’s transformer factory in Vaasa, Finland, will be supplied for Moray Offshore Renewable Power’s Moray East offshore wind project. […]

  • 30 October 2019
    Grid Connection, Wind Farm Update

    Siemens has delivered the first of the three onshore transformers to the onshore substation at New Deer, Scotland, for the Moray East offshore wind farm development. Once the transformer has been skidded into position, the installation of associated electrical equipment will begin. Moray East is Siemens’ largest grid connection project in the UK and needs three transformers […]

  • 28 August 2020
    Grid Connection

    OSP1, the third and final offshore transformer module (OTM) that will be installed at the Moray East offshore wind farm, is ready to leave Belgium this weekend (29 – 30 August). The OTMs, for which Siemens Energy secured a contract in 2018, were fabricated by Smulders and ENGIE Solutions in Hoboken, Belgium. “This milestone – three […]

  • 8 April 2020
    Contracts & Tenders

    Oceaneering International Services Ltd (OISL) has secured a contract to complete seabed route and debris clearance at the Moray East offshore wind project in Scotland. OISL said it will provide a full suite of services, including vessel, route preparation tools, remotely operated vehicle (ROV), survey, and personnel to complete the operations for the wind farm’s […]

  • 5 November 2018
    Contracts & Tenders, Grid Connection, Vessels, Wind Farm Update

    Moray Offshore Windfarm (East) Limited and NKT have signed a final binding agreement for the delivery and installation of export cable systems on the 950MW Moray East offshore wind farm.

  • 3 July 2020
    Grid Connection, Wind Farm Update

    Siemens Energy has shipped off the first of the three Offshore Transformer Modules (OTMs) to be installed on the 950 MW Moray East wind farm offshore Scotland. The first OTM began its journey from the fabricator to be installed at the offshore wind farm some 22 kilometres off the Aberdeenshire coast on 30 June. The […]

  • 12 September 2018
    Environment, Wind Farm Update

    APEM’s digital aerial surveys have finished gathering data on marine wildlife for the Moray East offshore wind project off the coast of Scotland.

  • 1 March 2019
    Grid Connection, Wind Farm Update

    TELE-FONIKA Kable (TFKable) has conducted the first Factory Acceptance Test (FAT) of a 220kV onshore high-voltage cable for the UK’s Moray East offshore wind farm at its Bydgoszcz plant in Poland. The cable supplier informed via social media that it had successfully FAT-tested 1,600mm² and 2,000mm² sizes to industry international standards. At the beginning of […]

  • 15 September 2021
    Wind Farm Update

    The 100th and final wind turbine has been installed at the Moray East offshore wind farm site, located some some 22 kilometres off Aberdeenshire in Scotland, according to an update from Ocean Winds. Fred. Olsen Windcarrier’s jack-up vessel Bold Tern installed the wind farm’s first Vestas 9.5 MW wind turbine in January. The work hit the halfway […]

  • 26 November 2020
    Vessels, Wind Farm Update

    The last jacket foundation produced for the Moray East offshore wind farm at Lamprell’s yard in Hamriyah has now been unloaded from OHT’s Hawk heavy transportation vessel in the Port of Nigg. The vessel arrived at the Port of Nigg on 12 November with the last batch of ten jackets, completing its second trip to […]

  • 16 November 2018
    Business & Finance, Wind Farm Update

    EDP Renováveis has, through its subsidiary EDPR UK Limited, closed the sale of a 13.4% stake in equity shareholding and outstanding shareholder loans on Moray Offshore Windfarm (East) Limited to Diamond Generating Europe Limited.

  • 5 January 2021
    Vessels, Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up Bold Tern is en route to Port of Nigg in Scotland to start the wind turbine installation at the 950 MW Moray East offshore wind farm. Prior to heading to Nigg, Bold Tern completed the mobilisation for the project at the Port of Esbjerg in Denmark. Bold Tern will transport 100 […]

  • 4 December 2020
    Contracts & Tenders, Grid Connection, Wind Farm Update

    UK energy market regulator Ofgem has opened a tender round to grant two offshore transmission licences to connect the Moray East and the Triton Knoll offshore wind farms to the UK grid. The tender process will consist of two stages for each project, an Enhanced Pre-Qualification (EPQ) stage, and an Invitation to Tender (ITT) stage, […]

  • 14 April 2020
    Business & Finance, Ports & Logistics

    The UAE-based Lamprell plans to close its Sharjah facility after completing the portion of work on the Moray East offshore wind project currently carried out at the location. Lamprell already mothballed the Jebel Ali facility in January 2020. The Sharjah yard will close later this year. The Hamriyah yard, the company’s largest facility, will remain […]

  • 1 August 2019
    Wind Farm Update

    Spain’s Navantia has started construction work on the 20 upper jackets for the Moray East wind farm offshore Scotland. The upper jackets, weighing approximately 460 tons each, will be built at the Navantia shipyard in Puerto Real. The first units are scheduled to be delivered in the fourth quarter of 2019, and the last batch […]

  • 30 October 2017
    Wind Farm Update

    Moray Offshore Windfarm East (Ltd) plans to install one hundred 9.5MW wind turbines for its 950MW offshore wind farm in the Outer Moray Firth and has now selected MHI Vestas as the preferred turbine supplier.