493 results found for 'moray east'

493 results found for 'moray east'
Order results by

A list of search results

  • 8 April 2020
    Contracts & Tenders

    Oceaneering International Services Ltd (OISL) has secured a contract to complete seabed route and debris clearance at the Moray East offshore wind project in Scotland. OISL said it will provide a full suite of services, including vessel, route preparation tools, remotely operated vehicle (ROV), survey, and personnel to complete the operations for the wind farm’s […]

  • 7 June 2019
    Ports & Logistics

    DEME Offshore has selected Global Energy Group to provide the Port of Nigg as a staging port for the Moray East offshore wind farm. Under the contract, the Port of Nigg will be used for receiving the completed turbine jacket foundations destined for the 950MW project. “Using Nigg for jackets complements our previous announcement of the Port […]

  • 6 September 2021
    Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel Blue Tern has seven more Vestas 9.5 MW units to install at the 100-turbine Moray East offshore wind farm in Scotland. The first wind turbines were installed at the project site some 22 kilometres off Aberdeenshire in January by the installation vessel Bold Tern, which left the site in May […]

  • 6 May 2021
    Vessels, Wind Farm Update

    32 out of the 100 Vestas V164-9.5MW wind turbines have been installed at the 950 MW Moray East wind farm offshore Scotland. The wind turbine installation is being carried out by Fred. Olsen Windcarrier’s jack-up vessel Bold Tern. The first turbines were installed some 22 kilometres off the Aberdeenshire coast during the second half of […]

  • 9 November 2020
    Grid Connection, Wind Farm Update

    Work to install the onshore cable which will connect the 950 MW Moray East offshore wind farm to the Scottish grid has ended, Siemens Energy said. The onshore cable, which starts near Banff, Aberdeenshire, takes the power generated offshore from the three 220kV subsea cables, and transmits it to the new onshore substation at New […]

  • 28 August 2020
    Grid Connection

    OSP1, the third and final offshore transformer module (OTM) that will be installed at the Moray East offshore wind farm, is ready to leave Belgium this weekend (29 – 30 August). The OTMs, for which Siemens Energy secured a contract in 2018, were fabricated by Smulders and ENGIE Solutions in Hoboken, Belgium. “This milestone – three […]

  • 15 April 2025
    Authorities, Business & Finance, Fixed-Bottom

    The UK’s energy regulator Ofgem has opened an investigation into whether Moray Offshore Windfarm (East) Ltd was charging excessive prices for reducing power output on the request of the National Energy System Operator (NESO) as part of the grid-balancing mechanism. The Moray East offshore wind farm, owned by a consortium comprising Ocean Winds, DGL (Inpex, […]

  • 24 November 2020
    Wind Farm Update

    Seajacks Scylla has 28 jacket foundations to install at the Moray East offshore wind farm, before it wraps up one of the biggest offshore construction works on the project. Only this month (November 2020), the vessel has put in place 18 jackets, so the foundation installation is expected to be completed in January, weather permitting, […]

  • 10 August 2020
    Grid Connection, Wind Farm Update

    The first of the three Offshore Transformer Modules (OTMs), ME OSP 3, has been installed at the 950 MW Moray East wind farm offshore Scotland. Siemens Energy shipped out the wind farm’s first OTM, ME OSP 2, for offshore installation on 30 June. This OTM will be installed later this week, a spokesperson for DEME […]

  • 7 December 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Siemens has selected Smulders to build the three Offshore Transformer Modules (OTMs) for the 950MW Moray East offshore wind farm.

  • 6 March 2025
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    Ventus Energy has secured two contracts with Ocean Winds to support its Scotland-based offshore wind farms, Moray West and Moray East. The first contract, awarded in September 2024 for Moray West, spans an 18-month period and includes operations and maintenance (O&M) for the offshore transmission owner (OFTO) assets. The scope of work includes timely inspections […]

  • 12 September 2018
    Environment, Wind Farm Update

    APEM’s digital aerial surveys have finished gathering data on marine wildlife for the Moray East offshore wind project off the coast of Scotland.

  • 8 March 2021
    Wind Farm Update

    Twelve Vestas (MHI Vestas) 9.5 MW wind turbines have been installed so far at the Moray East project site, located some 22 kilometres off the Aberdeenshire coast. The wind turbine installation is being carried out by Fred. Olsen Windcarrier’s Bold Tern jack-up vessel, which is picking up the components at the Port of Nigg, where […]

  • 13 September 2019

    PSG Marine & Logistics has completed its pin pile marshaling scope for the Moray East offshore wind farm in the UK. PSG was in charge of handling 159 pin piles and providing heavy lift crawler cranes, SPMTs and all associated heavy lift and transport personnel under a contract with DEME Offshore. The Invergordon-based company started loading in […]

  • 6 December 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Siemens has secured an order to connect the 950MW Moray East offshore wind farm to the Scottish grid.

  • 29 December 2020
    Vessels, Wind Farm Update

    Wind turbine installation at the Moray East offshore wind farm is scheduled to start in the first days of the next year, around 5 January. The wind turbines will be installed by the Bold Tern jack-up vessel, with the commissioning work to be done from Acta Centaurus, supported by two crew transfer vessels, HST Harri […]

  • 2 October 2020
    Grid Connection, Wind Farm Update

    Cable laying vessel Living Stone has started the first inter-array cable installation campaign at the 950 MW Moray East wind farm offshore Scotland. The wind farm will feature 100 66 kV inter-array cables and two offshore substation interconnector cables supplied by JDR Cable System. The installation campaign will be carried out in three phases. The […]

  • 13 November 2020
    Authorities, Contracts & Tenders, Grid Connection

    Ofgem will open a tender round for the offshore transmission licences for the Moray East and Triton Knoll offshore wind farms on 30 November. The authority issued a notice on 12 November, informing that the projects fulfilled all necessary conditions in accordance with regulation, including the submitted requests for qualifying projects, received payments and security […]

  • 5 November 2018
    Contracts & Tenders, Grid Connection, Vessels, Wind Farm Update

    Moray Offshore Windfarm (East) Limited and NKT have signed a final binding agreement for the delivery and installation of export cable systems on the 950MW Moray East offshore wind farm.

  • 3 July 2020
    Grid Connection, Wind Farm Update

    Siemens Energy has shipped off the first of the three Offshore Transformer Modules (OTMs) to be installed on the 950 MW Moray East wind farm offshore Scotland. The first OTM began its journey from the fabricator to be installed at the offshore wind farm some 22 kilometres off the Aberdeenshire coast on 30 June. The […]

  • 2 March 2023
    Business & Finance, Wind Farm Update

    Japan’s Inpex Corporation has acquired a 16.7 per cent stake in the 950 MW Moray East offshore wind farm. Moray East is located approximately 22 kilometers off the Moray East coast of Scotland in the United Kingdom. The wind farm has been in operation since April 2022. The acquisition was enabled through an agreement between […]

  • 26 November 2020
    Vessels, Wind Farm Update

    The last jacket foundation produced for the Moray East offshore wind farm at Lamprell’s yard in Hamriyah has now been unloaded from OHT’s Hawk heavy transportation vessel in the Port of Nigg. The vessel arrived at the Port of Nigg on 12 November with the last batch of ten jackets, completing its second trip to […]

  • 4 December 2020
    Contracts & Tenders, Grid Connection, Wind Farm Update

    UK energy market regulator Ofgem has opened a tender round to grant two offshore transmission licences to connect the Moray East and the Triton Knoll offshore wind farms to the UK grid. The tender process will consist of two stages for each project, an Enhanced Pre-Qualification (EPQ) stage, and an Invitation to Tender (ITT) stage, […]

  • 30 October 2017
    Wind Farm Update

    Moray Offshore Windfarm East (Ltd) plans to install one hundred 9.5MW wind turbines for its 950MW offshore wind farm in the Outer Moray Firth and has now selected MHI Vestas as the preferred turbine supplier.

  • 14 April 2020
    Business & Finance, Ports & Logistics

    The UAE-based Lamprell plans to close its Sharjah facility after completing the portion of work on the Moray East offshore wind project currently carried out at the location. Lamprell already mothballed the Jebel Ali facility in January 2020. The Sharjah yard will close later this year. The Hamriyah yard, the company’s largest facility, will remain […]

  • 16 November 2018
    Business & Finance, Wind Farm Update

    EDP Renováveis has, through its subsidiary EDPR UK Limited, closed the sale of a 13.4% stake in equity shareholding and outstanding shareholder loans on Moray Offshore Windfarm (East) Limited to Diamond Generating Europe Limited.