Search results for: moray east

455 results

A list of search results

  • 31 August 2020
    Wind Farm Update

    The jacket foundation for the third offshore transformer module (OTM) for Moray East offshore wind farm has been installed at the site off the Scottish coast. According to the project’s latest Notice of Operations, the jack-up vessel Seajacks Scylla installed the OSP1 jacket on 30 August. Meanwhile, the OSP1 topside was scheduled to sail out […]

  • 9 November 2017
    Business & Finance, Contracts & Tenders, Grid Connection, Technology, Wind Farm Update

    Moray Offshore Windfarm (East) Ltd and Siemens have signed a Preferred Bidder Agreement (PBA) for the onshore works, and offshore substation platform topsides for the 950MW Moray East offshore wind farm.

  • 20 July 2023
    Collaboration, Floating Wind, Outlook & Strategy

    The Offshore Wind Consultants (OWC) has entered into a partnership with Portugal-based WavEC to jointly offer services to the Portuguese offshore wind market. The partners said that this collaboration pools OWC’s global capabilities and track record in more than 50 floating wind projects with WavEC’s market presence, offshore site testing resources and expertise in environmental […]

  • 13 July 2021
    Wind Farm Update

    According to the latest update from the Moray East project, there are now 64 wind turbines installed at the site off the Aberdeenshire coast, which puts Moray East ahead of Scotland’s Beatrice offshore wind farm in terms of installed capacity. With each Vestas turbine having an output of 9.5 MW, Moray East is now on […]

  • 24 May 2021
    Vessels, Wind Farm Update

    40 out of the 100 Vestas V164-9.5MW wind turbines have been installed at the 950 MW Moray East wind farm offshore Scotland. The 40th turbine was installed at the site some 22 kilometres off the Aberdeenshire coast on 20 May, the project’s latest Notice of Operations shows. Fred. Olsen Windcarrier’s jack-up vessel Bold Tern installed […]

  • 28 March 2019
    Vessels

    DEME Offshore’s newbuild jack-up vessel Apollo is currently undergoing mobilization for the Moray East offshore wind project at Damen Shiprepair Dunkerque in France. The multi-purpose, self-propelled jack-up vessel will carry out one-month mobilization to prepare for pre-piling works at the 950MW project in the UK. Apollo was constructed by Croatian shipbuilder Uljanik Shipyard and was delivered to DEME in […]

  • 14 May 2020
    Wind Farm Update

    Work has commenced on the onshore sites of the Moray East offshore wind project in Scotland after a break due to the coronavirus crisis. At the end of March, Moray Offshore Windfarm (East) Ltd announced the demobilization of work at the project’s onshore sites, including the new underground cable and substation in Aberdeenshire. Following the […]

  • 16 January 2020
    Wind Farm Update

    The UAE-based Lamprell plans to start delivering the jacket foundations for the Moray East offshore wind farm from its facility in Hamryiah at the end of the first quarter of 2020. The upending of the jackets is ongoing, the company said. Lamprell won a contract to manufacture and deliver 45 wind turbine jacket foundations and three […]

  • 22 October 2021
    Operations & Maintenance, Wind Farm Update

    EDP has inaugurated the operations and maintenance center of the 950 MW Moray East offshore wind farm, which will now be controlled by this new infrastructure located in Fraserburgh Port, Scotland. This new operations and maintenance center will now manage this offshore wind farm, in particular by controlling the vessel ‘Alba’, which regularly spends two-week […]

  • 1 July 2019
    Wind Farm Update

    UAE-based Lamprell has held a steel cutting ceremony to mark the start of construction of jacket foundations for the 950MW Moray East wind project offshore Scotland. GeoSea, part of DEME Offshore, the Engineering, Procurement, Construction and Installation (EPCI) contractor for the project’s 100 wind turbine foundations and three offshore substation foundations, contracted Lamprell to fabricate 45 wind turbine and […]

  • 7 February 2019
    Contracts & Tenders, Wind Farm Update

    Engie has signed a Power Purchase Agreement (PPA) with Moray Offshore Windfarm (East) Ltd to purchase 23.3% of the electricity generated from the 950MW Moray East wind farm. The PPA is for a 15-year period, starting from commercial operation of the wind farm which is scheduled to commence in 2022. Engie currently holds a 23.3% […]

  • 30 November 2018
    Business & Finance

    The Kansai Electric Power Co., Inc (KEPCO) and Mitsubishi UFJ Lease & Finance Company Limited (MUL) have acquired stakes in the Moray East offshore wind project in Scotland.

  • 15 July 2019
    Contracts & Tenders, Grid Connection

    Siemens has placed multi-million pound contracts with companies across the UK for the construction of the transmission infrastructure for the Moray East offshore wind farm. As the lead contractor for onshore transmission infrastructure construction works for the 950MW wind farm, Siemens has placed several subcontracts since work began in September 2018. BAM Nuttall has been […]

  • 6 June 2019
    Contracts & Tenders

    Denmark’s  Welcon has received an order from MHI Vestas to deliver tower sections for the 950MW Moray East wind farm offshore Scotland. In total, Welcon will manufacture and deliver 70 bottom sections, 34 middle sections and 34 top sections for the project. The sections are scheduled to be delivered from the fourth quarter of 2019 until […]

  • 6 May 2021
    Vessels, Wind Farm Update

    32 out of the 100 Vestas V164-9.5MW wind turbines have been installed at the 950 MW Moray East wind farm offshore Scotland. The wind turbine installation is being carried out by Fred. Olsen Windcarrier’s jack-up vessel Bold Tern. The first turbines were installed some 22 kilometres off the Aberdeenshire coast during the second half of […]

  • 5 October 2020
    Wind Farm Update

    Smulders has sent off the final three upper jackets for the Moray East offshore wind farm from its yard in Hoboken, Belgium, to Newcastle upon Tyne. Smulders will deliver 55 turbine jacket foundations for the project, with the remaining 45 being delivered by Lamprell from its yards in the United Arab Emirates. The 55 jackets are […]

  • 9 November 2020
    Grid Connection, Wind Farm Update

    Work to install the onshore cable which will connect the 950 MW Moray East offshore wind farm to the Scottish grid has ended, Siemens Energy said. The onshore cable, which starts near Banff, Aberdeenshire, takes the power generated offshore from the three 220kV subsea cables, and transmits it to the new onshore substation at New […]

  • 17 August 2020
    Vessels

    Gulf Marine Services’ jack-up vessel GMS Endeavour is set to be deployed at the Moray East offshore wind farm site to support the commissioning of the project’s offshore transformer platforms. The vessel will arrive at the project site on or around 19 August, from when it will provide accommodation for workers carrying out commissioning works […]

  • 7 March 2019
    Business & Finance, Contracts & Tenders

    BiFab has won a contract by GeoSea to produce piles worth up to GBP 26.5 million for the 950MW Moray East offshore wind project. The contract represents the first in less than a year since DF Barnes, a subsidiary of the Canadian JV Drive, acquired BiFab. According to DF Barnes, the win will create 82 jobs at […]

  • 20 November 2020
    Business & Finance, Contracts & Tenders

    The Osprey Group has won a contract to provide handling and storage services for the spare export cable for the Moray East offshore wind farm. Under the contract, the company will receive and store approximately 2,500 metres of subsea cable and approximately 1,500 metres of HDD cable to be received from NKT’s cable laying vessel […]

  • 24 November 2020
    Wind Farm Update

    Seajacks Scylla has 28 jacket foundations to install at the Moray East offshore wind farm, before it wraps up one of the biggest offshore construction works on the project. Only this month (November 2020), the vessel has put in place 18 jackets, so the foundation installation is expected to be completed in January, weather permitting, […]

  • 17 June 2019
    Authorities, Wind Farm Update

    The Scottish Ministers have given marine consent for the construction and operation of the 850MW Moray West offshore wind project. This clears the way for the project to participate in the next Contracts for Difference (CfD) auction scheduled for this summer. If successful in the auction, the project could enter the construction phase in 2022. The […]

  • 8 February 2019
    Business & Finance, Grid Connection, Wind Farm Update

    The TFKable Group has produced the first part of the 220kV onshore high-voltage cable for the Moray East offshore wind farm in the UK. According to the company, the 220kV cable is now ready to be delivered from its Bydgoszcz plant in Poland for the 950MW offshore wind project. TFKable and VolkerInfra won the contract to […]

  • 26 May 2021
    Contracts & Tenders, Vessels

    The Island Crown vessel has started working at the Moray East offshore wind farm site, providing accommodation and walk-to-work (W2W) services during the project construction activities. Island Crown has joined the fleet of vessels deployed on the project after Moray Offshore Windfarm (East) Ltd (MOWEL) awarded Island Offshore with a contract for offshore accommodation and […]

  • 24 September 2020
    Wind Farm Update

    Seajacks Scylla installed the 33rd jacket foundation at the Moray East offshore wind farm site on 20 September, according to the project’s Notice of Operations from 21 September. The jack-up vessel is transporting the jacket foundations to the project site from Global Energy Group’s site in Nigg. The first jacket was installed at the beginning of […]

  • 27 May 2019
    Wind Farm Update

    The 950MW Moray East wind farm has entered the offshore construction phase with the start of piling operations earlier this month. The piling operations started on 19 May and are expected to take place over a period of approximately eleven months, a Notice of Operations said. Moray East contracted GeoSea NV Geotechnical & Offshore Solutions, […]