Bold Tern Comes For Moray East Wind Turbines
Fred. Olsen Windcarrier’s jack-up Bold Tern is en route to Port of Nigg in Scotland to start the wind turbine installation at the 950 MW Moray East offshore wind farm.
Prior to heading to Nigg, Bold Tern completed the mobilisation for the project at the Port of Esbjerg in Denmark.
Bold Tern will transport 100 MHI Vestas 9.5 MW units from Port of Nigg and install them at the site some 22 kilometres off the Aberdeenshire coast.
The turbine commissioning work will be carried out from Acta Centaurus and supported by two crew transfer vessels, HST Harri and Windcat 40.
Moray East is slated for full commissioning in 2022.
The project is being developed by Moray Offshore Windfarm East Ltd (MOWEL), a joint venture company owned by Ocean Winds (56.6%) Diamond Green Limited (33.4%), and CTG (10%).
List of related news articles
-
Posted: 4 days ago
Bold Tern Loads First Moray East Turbine Hardware
Fred. Olsen Windcarrier’s jack-up Bold Tern is on her way to install the first wind turbines a...
Posted: 4 days ago -
Posted: 18 days ago
Moray East Wind Turbine Installation Set to Start
Wind turbine installation at the Moray East offshore wind farm is scheduled to start in the first da...
Posted: 18 days ago -
Posted: 25 days ago
Moray East Jacket Installation in Home Stretch
Seajacks Scylla has installed 93 out of the 100 wind turbine jacket foundations at the Moray East wi...
Posted: 25 days ago -
Posted: 2 months ago
50 out of 100 wind turbine jacket foundations have been inst
50 out of 100 wind turbine jacket foundations have been installed at the Moray East wind farm offsho...
Posted: 2 months ago