Search results for: moray east

139 results

A list of search results

18 July 2019 Grid Connection

JGC has, on behalf of Siemens, completed the construction of high voltage equipment containers for the Moray East offshore substation platforms. JGC fabricated eight of twelve containers at its site in Thurso and have also supported Siemens with other offshore projects in the UK. From Thurso, the containers will make their way to Fabricom-Smulders in Belgium […]

15 July 2019 Contracts & Tenders, Grid Connection

Siemens has placed multi-million pound contracts with companies across the UK for the construction of the transmission infrastructure for the Moray East offshore wind farm. As the lead contractor for onshore transmission infrastructure construction works for the 950MW wind farm, Siemens has placed several subcontracts since work began in September 2018. BAM Nuttall has been […]

1 July 2019 Wind Farm Update

UAE-based Lamprell has held a steel cutting ceremony to mark the start of construction of jacket foundations for the 950MW Moray East wind project offshore Scotland. GeoSea, part of DEME Offshore, the Engineering, Procurement, Construction and Installation (EPCI) contractor for the project's 100 wind turbine foundations and three offshore substation foundations, contracted Lamprell to fabricate 45 wind turbine and […]

28 June 2019 Contracts & Tenders

Granada Handling has contracted Hutchinson Engineering for davit crane fabrication for the Moray East offshore wind farm in the UK. Granada Material Handling secured a contract by Engie Fabricom in March to provide davit cranes for the substations of the Moray East and Triton Knoll offshore wind projects. Shortly after, the UK company won a […]

27 June 2019 Grid Connection, Wind Farm Update

TFKable has installed the first sections of the 220kV onshore high-voltage cable system at the Moray East offshore wind farm in Scotland. Each of the sections includes three circuits of ducted cable, the company said, adding that the next phase of production is in progress. At the beginning of the year, TFKable and VolkerInfra won […]

26 June 2019 Contracts & Tenders, Grid Connection, Wind Farm Update

ABB has won an order from MHI Vestas Offshore Wind to supply its WindSTAR transformers for installation in wind turbines on the 950MW Moray East wind farm offshore Scotland. Under the project, 100 transformers manufactured in ABB’s transformer factory in Vaasa, Finland, will be supplied for Moray Offshore Renewable Power’s Moray East offshore wind project. […]

11 June 2019 Vessels

Kinnaird Marine Limited is providing guard vessels for the piling campaign at the Moray East offshore wind farm in the UK. GeoSea commenced the piling activities at the project site at the end of May, with operations so far completed on seven locations, according to the Moray East Weekly Notice of Operations. The GV Replenish and KMS […]

7 June 2019 Ports & Logistics

DEME Offshore has selected Global Energy Group to provide the Port of Nigg as a staging port for the Moray East offshore wind farm. Under the contract, the Port of Nigg will be used for receiving the completed turbine jacket foundations destined for the 950MW project. “Using Nigg for jackets complements our previous announcement of the Port […]

6 June 2019 Contracts & Tenders

Denmark's  Welcon has received an order from MHI Vestas to deliver tower sections for the 950MW Moray East wind farm offshore Scotland. In total, Welcon will manufacture and deliver 70 bottom sections, 34 middle sections and 34 top sections for the project. The sections are scheduled to be delivered from the fourth quarter of 2019 until […]

28 May 2019 Ports & Logistics, Vessels

Invergordon-based PSG Marine & Logistics Ltd has started loading in and loading out the jacket prepiles and the related equipment from the Port of Cromarty Firth as part of the port marshalling contract awarded by DEME Offshore in support of the Moray East offshore wind project. As reported earlier, DEME's installation vessel Apollo is carrying out […]

27 May 2019 Wind Farm Update

The 950MW Moray East wind farm has entered the offshore construction phase with the start of piling operations earlier this month. The piling operations started on 19 May and are expected to take place over a period of approximately eleven months, a Notice of Operations said. Moray East contracted GeoSea NV Geotechnical & Offshore Solutions, […]

17 May 2019 Contracts & Tenders, Wind Farm Update

James Fisher Marine Services (JFMS) will deliver marine coordination and provide communications infrastructure during the construction of the 950MW Moray East wind farm offshore Scotland. JFMS will provide Moray East, being built 22 kilometers off the coast of Scotland, with its offshore wind management system (OWMS) to deliver real-time data from various sources, together with […]

2 May 2019 Contracts & Tenders

Fred. Olsen Windcarrier has secured a contract for the transport and installation of turbines at the Moray East offshore wind project in Scotland. Fred. Olsen Windcarrier is in charge of transporting and installing 100 MHI Vestas V164-9.5MW turbines at the 950MW wind farm located off the East coast of Scotland. The company will deploy one of […]

17 April 2019 Contracts & Tenders

The UK-based Granada Material Handling has secured a contract to provide 100 davit crane units for the turbine jacket foundations of the Moray East offshore wind project. Granada is in charge of designing, manufacturing and commissioning Python crane units that will be fitted to each of the project's 100 jacket foundation platforms. According to the company, each […]

28 March 2019 Vessels

DEME Offshore's newbuild jack-up vessel Apollo is currently undergoing mobilization for the Moray East offshore wind project at Damen Shiprepair Dunkerque in France. The multi-purpose, self-propelled jack-up vessel will carry out one-month mobilization to prepare for pre-piling works at the 950MW project in the UK. Apollo was constructed by Croatian shipbuilder Uljanik Shipyard and was delivered to DEME in […]

26 March 2019 Business & Finance

Lamprell is on track to cut the first steel for the jacket foundations destined for the Moray East offshore wind farm in the second quarter of the year, according to the company's latest financial report. Lamprell won the contract to fabricate 45 wind turbine and three substation jacket foundations at the end of last year, with […]

14 March 2019 Contracts & Tenders, Wind Farm Update

DEME Offshore, previously GeoSea, has selected tier 1 suppliers for the foundations of the Moray East offshore wind project in the UK. According to DEME, Smulders will carry out a major part of the fabrication works on 55 of 100 jackets in Newcastle, including all final assembly, with Lamprell producing the remaining 45. The balance […]

7 March 2019 Business & Finance, Contracts & Tenders

BiFab has won a contract by GeoSea to produce piles worth up to GBP 26.5 million for the 950MW Moray East offshore wind project. The contract represents the first in less than a year since DF Barnes, a subsidiary of the Canadian JV Drive, acquired BiFab. According to DF Barnes, the win will create 82 jobs at […]

1 March 2019 Grid Connection, Wind Farm Update

TELE-FONIKA Kable (TFKable) has conducted the first Factory Acceptance Test (FAT) of a 220kV onshore high-voltage cable for the UK's Moray East offshore wind farm at its Bydgoszcz plant in Poland. The cable supplier informed via social media that it had successfully FAT-tested 1,600mm² and 2,000mm² sizes to industry international standards. At the beginning of […]

27 February 2019 Contracts & Tenders, Vessels

Solstad Offshore ASA has secured a contract with GeoSea for the Moray East offshore wind project in the UK. Solstad Offshore will provide the vessel Normand Service, previously Sea Spider, to support wind farm installation operations at the 950MW project. The vessel will be chartered for a period of 180 days firm, with up to […]

8 February 2019 Business & Finance, Grid Connection, Wind Farm Update

The TFKable Group has produced the first part of the 220kV onshore high-voltage cable for the Moray East offshore wind farm in the UK. According to the company, the 220kV cable is now ready to be delivered from its Bydgoszcz plant in Poland for the 950MW offshore wind project. TFKable and VolkerInfra won the contract to […]

7 February 2019 Contracts & Tenders, Wind Farm Update

Engie has signed a Power Purchase Agreement (PPA) with Moray Offshore Windfarm (East) Ltd to purchase 23.3% of the electricity generated from the 950MW Moray East wind farm. The PPA is for a 15-year period, starting from commercial operation of the wind farm which is scheduled to commence in 2022. Engie currently holds a 23.3% […]

6 February 2019 Contracts & Tenders, Wind Farm Update

UK utility Centrica plc has entered into a long-term contract with Moray Offshore Windfarm (East) Ltd to trade and balance 76.7 percent of the electricity generated from the 950MW Moray East offshore wind farm. Centrica’s Energy Marketing and Trading division has signed a Power Purchase Agreement (PPA) that covers all Balance Responsible Party (BRP) services […]

1 February 2019 Contracts & Tenders, Grid Connection

Pfisterer has won a contract for the supply of the 220kV land cable accessories for the grid connection of the 950MW Moray East offshore wind farm in Scotland. The company won the contract in cooperation with the cable manufacturer TELE-FONIKA Kable and the international cable and pipeline installation contractor VolkerInfra. Pfisterer will supply the 220kV […]

29 January 2019 Contracts & Tenders, Grid Connection, Wind Farm Update

The TFKable Group and VolkerInfra have won a contract to provide the onshore high voltage cable for the 950MW Moray East offshore wind farm in Scotland. Siemens is in charge of connecting the offshore wind farm to the Scottish grid. TFKable Group's HV production plant in Bydgoszcz, Poland will manufacture the 220kV cable, with the production […]

15 January 2019 Contracts & Tenders, Operations & Maintenance

Utility ROV Services (URS) has won a contract to provide boulder relocation services on the 950MW Moray East offshore wind farm in the Scottish waters. The Fife-headquartered company plans to begin the work in the first quarter of the year using its load bearing ROV system UTROV. “This contract is a welcome start to 2019 for […]