Search results for: Trianel Borkum

258 results

A list of search results

  • 5 February 2016

    Trianel Windkraftwerk Borkum II GmbH & Co. KG, the developer of the second phase of the already existing Trianel Windpark Borkum, Manufacturing, has invited tenders for the supply, on- and offshore logistics, and installation of monopiles, transition pieces and scour protection. The offshore wind project’s site is located 45 km north of the island of […]

  • 4 August 2013

    Petrofac Bags €40 Million Contract for Two German Offshore Wind Farms Petrofac has won a €40 million contract from Siemens Energy to provide support during the commissioning phase of two offshore wind converter station platforms in the German North Sea. Germany: First Wind Turbine Installed at Borkum West 2 “The first wind turbines are standing,” […]

  • 10 June 2020
    Contracts & Tenders, Operations & Maintenance

    Trianel Windkraftwerk Borkum is seeking a provider of marine, flight, and emergency response coordination services at the Trianel Windpark Borkum I wind farm in the German North Sea. The tender is divided into two lots. Lot 1 covers the marine, flight, and emergency response coordination services, plus operations control at the 200 MW wind farm. […]

  • 2 October 2015
    Business & Finance, Wind Farm Update

    EWE AG and Trianel have set up a joint venture to develop the second stage of the Trianel Windpark Borkum (TWB II) with a capacity of 200MW. Ines Kolmsee, Chief Operating Officer of EWE AG, stated: “EWE brings in its expertise from the development and operation of the first German offshore wind farm alpha ventus and the first […]

  • 10 June 2011
    Business & Finance, Contracts & Tenders

    German Offshore Wind Farm developer, Trianel,  invites tender for development of Borkum West II. Contractor’s tasks will be: Provision of a vessel for traffic control and monitoring of the construction phase of the Offshore wind farm Borkum West II. Use of a vessel for traffic safety programme (VSF), including the necessary crew to secure safety […]

  • 24 July 2019
    Wind Farm Update

    Jan De Nul’s offshore installation vessel Taillevent has begun loading the first turbine components for the Trianel Windpark Borkum II (TWBII) offshore wind farm. The 200MW TWBII offshore wind farm will comprise 32 Senvion 6.2M152 turbines installed at the project site some 40km north of the island of Borkum in Germany. Taillevent loaded the first three towers, blades […]

  • 5 May 2020
    Operations & Maintenance, Wind Farm Update

    Trianel Windkraftwerk Borkum has issued a tender for the provision and installation of scour protection at one wind turbine location in the Trianel Windpark Borkum (TWB) offshore wind farm in Germany. The contractor is responsible for the provision of the scour protection material (rocks) and its installation. Therefore, the chosen company will also provide any […]

  • 1 June 2017
    Grid Connection, Wind Farm Update

    Jan De Nul has contracted Seaproof Solutions to supply its export cable protection systems (CPS) for the Borkum Riffgrund 2 offshore wind farm and Trianel Windpark Borkum II.

  • 14 November 2018
    Business & Finance, Wind Farm Update

    German wind turbine manufacturer Senvion has started the production of the turbines for the 200MW Trianel Windpark Borkum II offshore wind farm.

  • 30 November 2018
    Vessels, Wind Farm Update

    EMS Maritime Offshore GmbH (EMO) deployed one of its specialist vessels at the Trianel Windpark Borkum II (TWB II) offshore wind farm site in early November 2018 to secure the shipping traffic during construction. 

  • 2 August 2019
    Wind Farm Update

    Jan De Nul’s jack-up Taillevent has started installing the first wind turbine on the 200MW Trianel Windpark Borkum II (TWBII) wind farm offshore Germany. Taillevent loaded the first three sets of turbine components at Buss Terminal Eemshaven prior to transporting them to the site some 40 kilometres north of the island of Borkum in the German North Sea. […]

  • 15 January 2021
    Contracts & Tenders

    Trianel Windkraftwerk Borkum has issued a tender for subsea works on the cable protection systems (CPS) and bolt exchanges at diffusor plates at the Trianel Windpark Borkum project in Germany. The selected company will be in charge of installing 20 preventive CPS retrofits, four corrective CPS retrofits, as well as bolt exchange at six steel […]

  • 16 July 2020
    Contracts & Tenders, Operations & Maintenance

    Siemens Gamesa will service the offshore wind turbines at the Trianel Windpark Borkum II (TWB II) in Germany, which comprises 32 Senvion 6.33-MW turbines. The contract, signed in late June, is effective as of 1 August and covers full scope maintenance for five years, including extension options. The operational base for the service campaigns will […]

  • 3 July 2020
    Wind Farm Update

    The Trianel Windpark Borkum II (TWB II) offshore wind farm is now fully commissioned. As of 30 June, all 32 Senvion 6.33 MW turbines have been spinning and the project was thus completed exactly two years after the start of construction. The inauguration of the 200 MW offshore wind farm, located some 45 kilometres off the […]

  • 24 September 2013
    Technology, Wind Farm Update

    The installation phase of the first AREVA M5000 turbines has begun for the German offshore wind farm Global Tech I and Trianel Windpark Borkum in the North Sea. By 2014, these two parks will host 120 turbines (40 at Trianel Windpark Borkum, 80 at Global Tech I) for an installed capacity of 600 megawatts, providing […]

  • 24 January 2023
    Contracts & Tenders, Vessels

    Trianel Windkraftwerk Borkum II (TWBII) GmbH has issued a contract notice seeking crew transfer vessel (CTV) services for its offshore wind farm in Germany. TWBII requires CTV services for the transportation of personnel as well as material, components, and spare parts to the Trianel Windpark Borkum II offshore wind farm as well as possibly other wind […]

  • 28 March 2019
    Ports & Logistics, Wind Farm Update

    The first wind turbine nacelles built by Senvion for the Trianel Windpark Borkum II wind farm have started their journey to the Buss Terminal Eemshaven in the Netherlands. The first of the 32 Senvion 6.2M152 wind turbines are expected to be installed at the site some 40 kilometres north of the island of Borkum in the German North Sea […]

  • 4 June 2018
    Vessels

    Vroon has christened its newest platform supply vessel (PSV) VOS Patriot, which is set to be deployed at the Trianel Windpark Borkum II offshore wind farm in the German North Sea.

  • 15 August 2019
    Wind Farm Update

    Jan De Nul’s vessel Taillevent has installed the first turbine at the Trianel Windpark Borkum II (TWBII) offshore wind farm. The 200MW TWBII wind farm will comprise 32 Senvion 6.2M152 turbines installed on monopile foundations at the site some 40km north of the island of Borkum in the German North Sea. Taillevent is loading the turbine components in sets […]

  • 21 February 2017
    Business & Finance, Wind Farm Update

    Swiss utility Elektrizitätswerk der Stadt Zürich (ewz), together with its compatriot Fontavis, today signed an agreement to invest in German Trianel Windpark Borkum II (TWB II) offshore wind farm by acquiring 24.5% stake in the EUR 800 million project.

  • 15 July 2019
    Wind Farm Update

    Jan De Nul’s offshore installation vessel Taillevent is en route to Eemshaven in the Netherlands to start loading the first turbine components for the Trianel Windpark Borkum II (TWBII) offshore wind farm. Located in the German North Sea, the 200MW TWBII wind farm will comprise 32 Senvion 6.2M152 wind turbines installed at the site some 40 […]

  • 22 January 2016
    Business & Finance, Contracts & Tenders, Grid Connection, Operations & Maintenance, Wind Farm Update

    Oldenburg-based Trianel Windkraftwerk Borkum II has invited tenders for the production and turnkey installation of the inner park cabling at the 200 MW Trianel Windpark Borkum (TWB) Phase 2, situated in the German exclusive economic zone in the North Sea. The TWB Phase 2 sits 45 kilometers north of the island of Borkum at a water depth […]

  • 10 January 2014
    Business & Finance, Operations & Maintenance, Wind Farm Update

    Trianel Windkraftwerk Borkum GmbH & Co. KG has invited tenders for the provision of offshore wind vessels for Borkum West 2 project. Trianel is looking for vessels which can accommodate and transfer crew to and from the construction site, as well as supply vessels to transfer goods and materials to, from and within the offshore […]

  • 15 November 2013

    Trine Borum Bojsen has been named Managing Director of the German Offshore division at Dong Energy, thus replacing Christoph Mertens, who is leaving the company. Borum Bojsen has been working in the Danish company since 2008 and was responsible for the Engineering & Project Certification. Together with her two colleagues in the Board, Lars Thaaning […]

  • 10 September 2015

     SgurrEnergy has acted as technical advisor on behalf of the 200MW Borkum wind farm lenders during the financing and construction monitoring phases of the project. The project was officially opened by the developer, Trianel GmbH, at a ceremony held on 31 August 2015. The project, located approximately 45 km to the north of the East […]

  • 18 March 2016
    Wind Farm Update

    First purely municipal offshore wind farm installed off German coast, Trianel Windpark Borkum, has been in operation for half a year now, and has generated 452.33GWh of electricity, with January 2016 as the month with the highest yield so far – 95.12GWh. Construction on the wind farm began in September 2011. From July 2013, all 40 AREVA Wind M5000-116 […]