  • 20 March 2014
    Grid Connection, Wind Farm Update

    Just nine months after the start of construction, Trianel, a German utility company, has installed 25 of 40 turbines at the Borkum West offshore wind farm. In spite of the strong winds from hurricanes “Christian” and “Xavier”, considerable progress has been made on this 200MW wind farm with 75 percent of array cables also completed. […]

  • 1 November 2019
    Contracts & Tenders

    The operators of the Trianel Windpark Borkum and the Trianel Windpark Borkum II offshore wind farms in the German North Sea have issued a tender for the provision of the Helicopter Emergency Medical Services (HEMS). Infrastruktur Windkraftwerk Borkum, Trianel Windkraftwerk Borkum, and Trianel Windkraftwerk Borkum II are seeking rescue services in accordance with the regulatory […]

  • 3 June 2014
    Wind Farm Update

    All 40 wind turbines of the first phase of Trianel Windpark Borkum (formerly known as  Borkum West II) offshore wind farm are now installed. MPI Adventure jack-up vessel has been working for eleven months to install forty Areva M5000-116 wind turbines, with a total capacity of 200 MW. “Now, the only thing missing is the […]

  • 14 May 2020
    Wind Farm Update

    The Blue Tern installation vessel is currently at the Trianel Windpark Borkum II (TWBII) project site with the last two turbines to be installed. OffshoreWIND.biz contacted Fred. Olsen Windcarrier after Buss Energy Group, which has been providing port logistics for wind turbine installation, reported it had completed its project for Trianel wind farm Borkum II. […]

  • 12 November 2015
    Business & Finance, Grid Connection, Operations & Maintenance, Wind Farm Update

    German municipal utility Trianel has partnered up with compatriot Gesy Green Energy Systems to jointly market and sell the electricity produced at the 200MW Trianel Wind Farm Borkum situated in the North Sea. With the latest agreement, the combined portfolio of the two companies now stands at 3.5GW. The Trianel Wind Farm Borkum is located approximately 45 kilometers […]

  • 26 October 2014

    TenneT Invites Tenders for BorWin4 TenneT-owned DC-Netz BorWin4 GmbH is inviting tenders for BorWin4 connection system located in the North Sea. Trianel Wind Farm Borkum Commissioning Pushed to 2015 The initial testing of the link between Trianel Wind Farm Borkum’s transformation platform and TenneT’s transformation platform “DolWin 1” failed. Seatower to Load Out Foundation from […]

  • 1 September 2020
    Contracts & Tenders

    SeaRenergy Offshore has signed a framework agreement with Trianel Windkraftwerk Borkum for client representative services. Under the two-year deal, SeaRenergy will provide client representatives for the Trianel Windpark Borkum (TWB) offshore wind farm in Germany. Most recently, the company said it cooperated with Trianel Windkraftwerk Borkum on several work scopes covering services at TWB’s onshore […]

  • 15 October 2019
    Operations & Maintenance

    Deutsche Windtechnik has received an order to provide maintenance for the 32 Senvion 6.3M 152 turbines at the Trianel Windpark Borkum II wind farm in the German North Sea. The main service tasks include troubleshooting the wind turbines, including guaranteed availability, remote fault elimination, spare parts management, and logistics from Borkum or Emden. “We are […]

  • 19 June 2017

    Wood Group’s clean energy business, previously known as SgurrEnergy, supported Trianel Windpark Borkum II (TWB II) to financial close, as it had been appointed by Trianel Windkraftwerk Borkum II GmbH & Co. KG to act as lender’s technical adviser.

  • 9 November 2018
    Wind Farm Update

    27 out of the 32 monopile foundations have been installed on the 200MW Trianel Windpark Borkum II (TWB II) offshore wind farm in the German North Sea.

  • 14 October 2019
    Operations & Maintenance, Vessels

    Trianel Windkraftwerk Borkum has issued a tender for the provision of two crew transfer vessels (CTVs) to service the 200MW Trianel Windpark Borkum I in the German North Sea and nearby offshore wind farms. The wind farm operator is looking for a provider or providers of two CTVs, one with a capacity of at least twelve persons […]

  • 5 December 2019
    Wind Farm Update

    The Trianel Windpark Borkum II (TWBII) offshore wind project has reached the halfway turbine installation point as 16 out of 32 units have been erected. Jan De Nul’s jack-up vessel Taillevent installed the 16 Senvion 6.2M152 turbines in the northeastern part of the project site offshore Germany, with the installation of the remaining 16 units […]

  • 14 March 2012
    Business & Finance

    AREVA announces the delivery of 20 M5000 turbines, out of a total of 40, to be installed in Trianel’s Borkum offshore wind park located in the German North Sea. The Borkum wind farm, situated 45 km away from the northern coast of the Borkum Island, is currently under construction close to “alpha ventus”, the first […]

  • 16 June 2020
    Contracts & Tenders, Wind Farm Update

    Trianel Windkraftwerk Borkum has issued a contract notice for insurance policy services covering the 200 MW Trianel Windpark Borkum I offshore wind farm in the German North Sea. The contract covers combined property damage and business interruption all risks insurance for the operational phase of the wind farm consisting of 40 offshore wind turbines including […]

  • 7 August 2018
    Contracts & Tenders, Ports & Logistics, Vessels, Wind Farm Update

    Trianel Windkraftwerk Borkum II GmbH has issued a tender for the provision of a guard vessel during the construction of the Trianel Windpark Borkum II wind farm in the German North Sea.

  • 5 February 2013

    A further project step for the Trianel wind farm Borkum has been successfully finished. The 40 wind energy turbines which were produced by AREVA Wind have been shipped from Bremerhaven to the Dutch town Eemshaven. In September last year the transport of the 40 nacelles, hubs and (S3) tower sections of the 5 Megawatt (MW) […]

  • 28 February 2018
    Contracts & Tenders, Wind Farm Update

    Senvion has contracted TÜV Rheinland to oversee the production of wind turbine blades for the Trianel Windpark Borkum II offshore wind farm.

  • 5 February 2016
    Operations & Maintenance, Vessels

    Trianel Windkraftwerk Borkum GmbH & Co. KG, the operator of the Trianel Windpark Borkum offshore wind farm, has awarded a new crew transfer contract to EMS Maritime Offshore GmbH (EMO), thus extending the cooperation for another year.  The one-year contract covers crew transfer services during the O&M phase. The vessel operating at the offshore wind […]

  • 13 November 2019
    Wind Farm Update

    Senvion has delivered the last turbine for the Trianel Windpark Borkum II (TWBII) offshore wind project in Germany. According to Senvion, all components for the 200MW wind farm have been finished and shipped to Eemshaven. Trianel Windpark Borkum II comprises 32 Senvion 6.2M152 turbines installed on monopile foundations at the site some 40km north of the […]

  • 15 November 2018
    Ports & Logistics, Wind Farm Update

    The Buss Terminal Eemshaven has received the first shipment of wind turbine tower sections for the Trianel Windpark Borkum II offshore wind project.

  • 12 May 2020
    Operations & Maintenance, Vessels

    EMS Maritime Offshore (EMO) has signed a charter contract for the WINDEA Three crew transfer vessel (CTV) to service the operating phase of the Trianel Windpark Borkum Phase I offshore wind project. WINDEA Three began the three-year charter in February, succeeding its sister vessel WINDEA One which has been operating on the project since 2013. […]

  • 17 March 2021
    Wind Farm Update

    EMS Maritime Offshore’s (EMO) VENTUSmarine control center has assumed coordination of the Trianel Windpark Borkum project in Germany. In November last year, EMO signed a five-year contract with Trianel Windpark Borkum GmbH & Co. to handle maritime, flight and emergency coordination for the project until the end of 2025. EMO currently transports personnel and freight […]

  • 9 December 2016
    Business & Finance

    EWE AG and Trianel have made a preliminary investment decision and agreed to jointly bring the Trianel Wind Farm Borkum II (TWB II) offshore wind farm to realisation with each having a 37.5% stake in the project.  For the remaining 25% of the project, talks are currently being held with interested third-party investors before the final investment […]

  • 29 June 2018
    Grid Connection

    Jan De Nul has completed the export cable installation works at the Trianel Windpark Borkum II and the Borkum Riffgrund 2 offshore wind farms in the German North Sea.

  • 2 February 2017
    Operations & Maintenance, Vessels, Wind Farm Update

    The EMS Maritime Offshore GmbH (EMO) has secured a new charter contract through Trianel Windkraftwerk Borkum for the provision of the crew transfer vessel, the WINDEA one. The special ship transports service engineers as well as freight and supply goods into the offshore wind farm, approximately 45 km from the island of Borkum. During the […]

  • 14 November 2019
    Wind Farm Update

    13 of the 32 Senvion 6.2M152 wind turbines have been installed on the 200MW Trianel Windpark Borkum II (TWBII) offshore wind farm in the German North Sea, Trianel GmbH said. Eleven out of the thirteen turbines installed have been commissioned, according to Trianel. The wind turbines are being loaded by Jan De Nul’s jack-up Taillevent at Buss […]