Search results for: hornsea one

11691 results

A list of search results

  • 18 February 2019
    Vessels, Wind Farm Update

    A2SEA’s wind turbine installation vessel Sea Challenger has left Hull with a first load of turbine components to be installed on the 1,218MW Hornsea Project One offshore wind farm. A2SEA is in charge of transporting and installing half of the wind farm’s 174 Siemens Gamesa 7MW turbines. The remaining half of the turbines is being […]

  • 27 November 2018
    Business & Finance, Wind Farm Update

    Ørsted has completed the divestment of 50% of the Hornsea Project One offshore wind farm in the UK to Global Infrastructure Partners (GIP).

  • 8 May 2019
    Ports & Logistics, Wind Farm Update

    Windhoist Limited has pre-assembled 78 out of 174 wind turbine towers for the 1,218MW Hornsea Project One wind farm at Siemens Gamesa’s pre-assembly site in Hull. The Ayrshire-based company is providing Siemens Gamesa with the pre-construction support for 174 Siemens Gamesa SWT-7.0-154 wind turbines which are currently being installed at the site some 120 kilometres offshore Yorkshire. […]

  • 15 September 2016

    DONG Energy will hold two community events in Grimsby and Stallingborough to give local people a chance to find out more about the Hornsea Project One offshore wind farm. When built, the 1.2GW Hornsea Project One will be the world’s largest offshore wind farm by a considerable margin, capable of providing enough renewable energy for well over […]

  • 5 January 2016
    Grid Connection, Wind Farm Update

    Onshore works for the Hornsea Project One wind farm are scheduled to start this month with the construction of an onshore substation at North Killingholme, North Lincolnshire.   This will be followed by burying an onshore cable underground and works around the landfall site where the onshore cable meets the offshore cable. The cable route on land will run approximately […]

  • 20 February 2019
    Vessels

    Danish company MH-O&C has held a naming ceremony for the crew transfer vessel (CTV) MHO Gurli. The 39m long Fast Supply Cat vessel was ordered by Ørsted for the Hornsea Project One offshore wind farm in the UK and is expected to enter service shortly. MHO Gurli has a 10.3m beam, a max draft of […]

  • 30 November 2018
    Vessels

    DEME Group’s new cable laying and multipurpose vessel Living Stone has started her first offshore wind assignment on the Hornsea Project One wind farm off the North Sea coast of the UK.

  • 6 February 2018
    Contracts & Tenders, Grid Connection, Operations & Maintenance, Technology, Wind Farm Update

    Ørsted has awarded Seaproof Solutions with a contract extension to supply all inter-array cable protection systems (CPS) for its 1.2GW Hornsea Project One offshore wind farm in the UK.

  • 23 June 2017
    Wind Farm Update

    DONG Energy has decided to use only monopile foundations on the 174-turbine Hornsea Project One offshore wind farm.

  • 23 January 2018
    Ports & Logistics, Vessels, Wind Farm Update

    GeoSea’s jack-up Innovation has loaded the first set of monopile foundations in Vlissingen, the Netherlands, and is now en route to install them on Orsted’s 1.2GW Hornsea Project One wind farm off the UK, DEME said.

  • 5 August 2019
    Wind Farm Update

    124 out of 174 Siemens Gamesa 7MW turbines have been installed and commissioned at the Hornsea Project One wind farm in the UK, a spokesperson from Ørsted told Offshore WIND. Fred. Olsen Windcarrier’s jack-up vessel Bold Tern is in charge of installing 88 out of the 174 turbines, with A2SEA’s Sea Challenger responsible for installing the remaining 86 […]

  • 5 July 2019
    Wind Farm Update

    The 100th Siemens Gamesa 7MW turbine has been installed at the Hornsea Project One offshore wind farm in the UK. Fred. Olsen Windcarrier’s Bold Tern is in charge of installing 88 out of the project’s total 174 turbines, with A2SEA’s Sea Challenger responsible for installing the remaining 86 units. According to Fred. Olsen Windcarrier, Bold Tern recently […]

  • 25 January 2018
    Operations & Maintenance

    CHC’s first flight for the initial phase of Ørsted’s Hornsea Project One offshore wind farm left the Humberside Airport, UK, on 24 January.

  • 1 February 2019
    Vessels, Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel Bold Tern has arrived in Hull, the UK, where it will begin its work for the Hornsea Project One offshore wind farm. According to Fred. Olsen Windcarrier, the vessel arrived in Hull yesterday afternoon and is ready to pick up the turbines for the 1.2GW project. Bold Tern is in charge of […]

  • 6 February 2018
    Environment, Grid Connection, Operations & Maintenance, R&D

    Wessex Archaeology has unearthed numerous archaeological remains in Lincolnshire, UK, and the surrounding area as part of the onshore construction works for Ørsted’s Hornsea Project One offshore wind farm.

  • 11 December 2018
    Grid Connection, Wind Farm Update

    Tideway BV, part of DEME Group, has completed the installation of the export cable at the Hornsea Project One offshore wind farm in the UK.

  • 11 March 2015
    Grid Connection, Wind Farm Update

    Dong Energy has awarded Ramboll the design of a reactive compensation substation for the Hornsea Project One offshore wind farm development. The scope of work comprises the conceptual development, detailed design and technical assistance during tendering, fabrication and installation. The requirement for an offshore reactive compensation substation is a direct consequence of wind farms moving […]

  • 22 May 2018
    Vessels, Wind Farm Update

    SMST has equipped the Platform Supply Vessel (PSV) Eurus Express with a motion compensated gangway ahead of the vessel’s deployment on Orsted’s Hornsea Project One offshore wind farm in the UK.

  • 23 December 2016
    Grid Connection, Wind Farm Update

    Prefabrication work on three substations for DONG Energy’s 1.2GW Hornsea Project One offshore wind farm is well under way, Danish offshore structure construction specialist Bladt Industries reports. Each substation will weigh 2,800 tons and the first unit will be delivered during the first half of 2018, the company said. The contract represents Bladt’s first ever order to fabricate […]

  • 21 December 2016
    Business & Finance, Technology, Wind Farm Update

    Rochdale-based Granada Material Handling Limited (Granada) is the latest UK firm to sign a contract with DONG Energy for the world’s biggest wind farm, the 1.2GW Hornsea Project One located some 120 kilometres off Yorkshire. Each of the Siemens 7MW turbines will require a davit crane and Granada will assemble and test all 174 at their […]

  • 5 April 2016
    Business & Finance, Grid Connection, Wind Farm Update

    NKT Cables has been awarded a contract by DONG Energy to deliver 170 kilometres of 220 kV high-voltage alternating current (AC) submarine export cable system for the 1.2GW Hornsea Project One offshore wind farm.  The wind farm will be placed 120 kilometres off the Yorkshire coast in the UK, and the cable system supplied by […]

  • 26 April 2018
    Grid Connection, Vessels, Wind Farm Update

    The first Hornsea Project One substation topside, Z12, has been installed at the site 120km off the Yorkshire coast.

  • 24 January 2017
    Grid Connection, Wind Farm Update

    Spain’s Dragados Offshore has awarded compatriot IKM Testing Spain with a contract to manufacture sheet metal panels which will be used for the construction of offshore substation jackets for the 1.2GW Hornsea Project ONE offshore wind farm. IKM Testing Spain, part of the IKM Group, plans to fabricate the steel plates at its newly opened steel works […]

  • 16 August 2019
    Wind Farm Update

    The Hornsea Project One offshore wind farm in the UK suffered a technical fault on 9 August due to grid problems. During the technical fault, the 1.2GW offshore wind farm significantly dropped its power production as it lost 800MW of electricity, around the same time as another generation source lost load, Ørsted said. “During a rare and […]

  • 3 June 2019
    Operations & Maintenance, Wind Farm Update

    Ørsted has officially started operations on the 1,214MW Hornsea One, the largest offshore wind farm in the world. The project’s first operational team of 32 set sail from Grimsby Royal Docks to the wind farm located 120 kilometres out to sea on 31 May. They are part of two shift-based teams that are responsible for […]

  • 1 October 2018
    Ports & Logistics, Vessels, Wind Farm Update

    ALE and their Conbit operation have loaded-out and discharged 54 of the contracted 106 transition pieces for Ørsted’s Hornsea Project One offshore wind farm.