671 results found for 'hornsea one'

671 results found for 'hornsea one'
Order results by

A list of search results

  • 10 May 2016
    Vessels, Wind Farm Update

    A2SEA has won a contract to install a part of 174 Siemens 7MW turbines at the 1.2GW Hornsea Project One wind farm off the Yorkshire Coast. In spring 2019, A2SEA will deploy its offshore installation vessel, Sea Installer, to work on the turbines at the site located 120 kilometres off the coast. ”It is a great pleasure […]

  • 2 November 2018
    Ports & Logistics

    The first of the 174 wind turbine towers for the 1.2GW Hornsea Project One has been upended at Siemens Gamesa’s pre-assembly site in Hull.

  • 1 April 2019
    Contracts & Tenders, Grid Connection

    Semco Maritime has signed a service contract for Ørsted’s Hornsea Project One offshore wind farm in the UK. Under the two-year agreement, Semco will service and maintain the project’s reactive compensation station (RCS) and the three offshore substations (OSS). The contract runs until the beginning of 2020 and will be carried out from Semco’s office in Grimsby, […]

  • 23 January 2018
    Ports & Logistics, Vessels, Wind Farm Update

    GeoSea’s jack-up Innovation has loaded the first set of monopile foundations in Vlissingen, the Netherlands, and is now en route to install them on Orsted’s 1.2GW Hornsea Project One wind farm off the UK, DEME said.

  • 25 January 2018
    Operations & Maintenance

    CHC’s first flight for the initial phase of Ørsted’s Hornsea Project One offshore wind farm left the Humberside Airport, UK, on 24 January.

  • 5 August 2019
    Wind Farm Update

    124 out of 174 Siemens Gamesa 7MW turbines have been installed and commissioned at the Hornsea Project One wind farm in the UK, a spokesperson from Ørsted told Offshore WIND. Fred. Olsen Windcarrier’s jack-up vessel Bold Tern is in charge of installing 88 out of the 174 turbines, with A2SEA’s Sea Challenger responsible for installing the remaining 86 […]

  • 5 January 2016
    Grid Connection, Wind Farm Update

    Onshore works for the Hornsea Project One wind farm are scheduled to start this month with the construction of an onshore substation at North Killingholme, North Lincolnshire.   This will be followed by burying an onshore cable underground and works around the landfall site where the onshore cable meets the offshore cable. The cable route on land will run approximately […]

  • 5 April 2016
    Business & Finance, Grid Connection, Wind Farm Update

    NKT Cables has been awarded a contract by DONG Energy to deliver 170 kilometres of 220 kV high-voltage alternating current (AC) submarine export cable system for the 1.2GW Hornsea Project One offshore wind farm.  The wind farm will be placed 120 kilometres off the Yorkshire coast in the UK, and the cable system supplied by […]

  • 7 August 2024
    Fixed-Bottom, Operations & Maintenance, Project Updates, Technology, Wind Farm Update

    Ørsted has deployed heavy-lift cargo drones (HLCDs) for maintenance work at the Borssele 1&2 offshore wind farm in the Netherlands. This is the first time heavy-lift cargo drones are being used in an operational campaign, according to the company which tested the concept in 2023 at its Hornsea One offshore wind farm in the UK. […]

  • 20 February 2018
    Business & Finance, Wind Farm Update

    Ørsted has entered exclusive discussions regarding a 50% farm-down of the 1.2GW Hornsea Project One offshore wind farm.

  • 2 March 2018
    Vessels, Wind Farm Update

    A2SEA’s jack-up vessel Sea Installer has installed the first of the 174 transition pieces on Ørsted’s 1.2GW Hornsea Project One offshore wind farm.

  • 22 May 2018
    Vessels, Wind Farm Update

    SMST has equipped the Platform Supply Vessel (PSV) Eurus Express with a motion compensated gangway ahead of the vessel’s deployment on Orsted’s Hornsea Project One offshore wind farm in the UK.

  • 26 April 2018
    Grid Connection, Vessels, Wind Farm Update

    The first Hornsea Project One substation topside, Z12, has been installed at the site 120km off the Yorkshire coast.

  • 20 February 2019
    Vessels

    Danish company MH-O&C has held a naming ceremony for the crew transfer vessel (CTV) MHO Gurli. The 39m long Fast Supply Cat vessel was ordered by Ørsted for the Hornsea Project One offshore wind farm in the UK and is expected to enter service shortly. MHO Gurli has a 10.3m beam, a max draft of […]

  • 27 October 2016
    Vessels, Wind Farm Update

    DONG Energy Wind Power A/S has awarded Royal Boskalis Westminster with a contract for the transport and installation of the foundations for a part of the 1.2GW Hornsea Project One offshore wind farm located some 120 kilometers off the Yorkshire coast, UK. The transport and installation of the foundations will be executed by Boskalis’ new […]

  • 27 November 2018
    Business & Finance, Wind Farm Update

    Ørsted has completed the divestment of 50% of the Hornsea Project One offshore wind farm in the UK to Global Infrastructure Partners (GIP).

  • 1 December 2017
    Contracts & Tenders, Grid Connection, Vessels, Wind Farm Update

    Norway’s Ocean Yield ASA has entered into a time charter contract for the vessel Lewek Connector which will conduct cable lay operations for Ørsted’s Hornsea Project One offshore wind farm project in the UK.

  • 6 February 2018
    Environment, Grid Connection, Operations & Maintenance, R&D

    Wessex Archaeology has unearthed numerous archaeological remains in Lincolnshire, UK, and the surrounding area as part of the onshore construction works for Ørsted’s Hornsea Project One offshore wind farm.

  • 1 November 2018
    Wind Farm Update

    104 out of 174 turbine monopile foundations and 66 out of 174 inter-array cables have been installed on the 1,218MW Hornsea Project One wind farm, Ørsted said.

  • 11 December 2018
    Grid Connection, Wind Farm Update

    Tideway BV, part of DEME Group, has completed the installation of the export cable at the Hornsea Project One offshore wind farm in the UK.

  • 1 October 2018
    Ports & Logistics, Vessels, Wind Farm Update

    ALE and their Conbit operation have loaded-out and discharged 54 of the contracted 106 transition pieces for Ørsted’s Hornsea Project One offshore wind farm.

  • 21 December 2016
    Business & Finance, Technology, Wind Farm Update

    Rochdale-based Granada Material Handling Limited (Granada) is the latest UK firm to sign a contract with DONG Energy for the world’s biggest wind farm, the 1.2GW Hornsea Project One located some 120 kilometres off Yorkshire. Each of the Siemens 7MW turbines will require a davit crane and Granada will assemble and test all 174 at their […]

  • 15 September 2016

    DONG Energy will hold two community events in Grimsby and Stallingborough to give local people a chance to find out more about the Hornsea Project One offshore wind farm. When built, the 1.2GW Hornsea Project One will be the world’s largest offshore wind farm by a considerable margin, capable of providing enough renewable energy for well over […]

  • 3 June 2019
    Operations & Maintenance, Wind Farm Update

    Ørsted has officially started operations on the 1,214MW Hornsea One, the largest offshore wind farm in the world. The project’s first operational team of 32 set sail from Grimsby Royal Docks to the wind farm located 120 kilometres out to sea on 31 May. They are part of two shift-based teams that are responsible for […]

  • 20 September 2018

    Mech-Tool Engineering (MTE) has completed a fabrication project comprising a series of transportation cradles for the 1.2GW Hornsea Project One offshore wind farm.

  • 3 October 2018
    Wind Farm Update

    GeoSea has installed half of the monopile foundations at the Hornsea Project One offshore wind farm in the UK.