First Hornsea One Transition Piece Stands

The first of the 174 transition pieces has been installed on Ørsted’s 1.2GW Hornsea Project One offshore wind farm.

GeoSea’s Innovation and A2SEA’s Sea Installer are involved in the installation of the transition pieces on the site some 120 kilometres off the coast of Yorkshire.

The first monopile foundation was installed on the wind farm by Innovation in late January.

Hornsea Project One consists of 174 Siemens 7MW wind turbines, connected to three offshore collector substations and a reactive compensation substation (RCS), the latter located between the offshore wind farm and the shore.

Once commissioned in 2020, Hornsea One will be the largest operating wind farm in the world.

Related news

List of related news articles

Posted: about 1 year ago

Half of Hornsea One Foundations Up

GeoSea has installed half of the monopile foundations at the Hornsea Project One offshore wind farm ...

Categories:
  • Wind Farm Update
Posted: about 1 year ago
Posted: about 1 year ago

Waves Group Joins Hornsea One Ranks

Waves Group is providing Marine Warranty Surveyor services during the construction of the world’s la...

Categories:
  • Wind Farm Update
Posted: about 1 year ago
Posted: about 1 year ago

Gulliver Gives Living Stone a Hand

The heavy lift vessel Gulliver has installed a 253 t Huisman crane on board DEME Group’s cable...

Categories:
  • Vessels
Posted: about 1 year ago
Posted: about 1 year ago

Wind of Change Takes to Water (VIDEO)

Turkey’s Cemre Shipyard has shared a video showing the launch of Ørsted’s service operat...

Categories:
  • Operations & Maintenance
Posted: about 1 year ago