  • 18 February 2019
    Vessels, Wind Farm Update

    A2SEA’s wind turbine installation vessel Sea Challenger has left Hull with a first load of turbine components to be installed on the 1,218MW Hornsea Project One offshore wind farm. A2SEA is in charge of transporting and installing half of the wind farm’s 174 Siemens Gamesa 7MW turbines. The remaining half of the turbines is being […]

  • 27 November 2018
    Business & Finance, Wind Farm Update

    Ørsted has completed the divestment of 50% of the Hornsea Project One offshore wind farm in the UK to Global Infrastructure Partners (GIP).

  • 16 August 2019
    Wind Farm Update

    The Hornsea Project One offshore wind farm in the UK suffered a technical fault on 9 August due to grid problems. During the technical fault, the 1.2GW offshore wind farm significantly dropped its power production as it lost 800MW of electricity, around the same time as another generation source lost load, Ørsted said. “During a rare and […]

  • 1 February 2018
    Business & Finance, Wind Farm Update

    Ørsted plans to complete a 50% farm-down of the 1.2GW Hornsea Project One offshore wind farm either in the second half of 2018 or in 2019.

  • 11 April 2018
    Grid Connection, Ports & Logistics, Wind Farm Update

    The Hornsea Project One offshore substation topside Z12 has been loaded onto a barge and is awaiting sail out to the installation site some 120 kilometres off Yorkshire, UK.

  • 28 June 2019
    Vessels, Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel Bold Tern has completed the installation of 53 turbines at the Hornsea Project One offshore wind farm in the UK. Bold Tern is in charge of installing 88 out of the project’s total 174 turbines, with A2SEA’s Sea Challenger responsible for installing the remaining 86 units. According to Fred. Olsen Windcarrier, the […]

  • 14 June 2016
    Vessels, Wind Farm Update

    Tideway BV has been awarded a Design and Build cable installation contract by DONG Energy for the Hornsea Project One offshore wind farm.  For the project, Tideway, a subsidiary of DEME, will deploy the new DP3 cable-laying vessel Living Stone, which is currently being built by the Spanish shipyard LaNaval and is scheduled to be delivered in April […]

  • 26 February 2019
    Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up Bold Tern has departed from Hull, the UK, carrying the second batch of turbines for the Hornsea Project One offshore wind project. The vessel installed the first Siemens Gamesa 7MW turbine at the site some 120km off the Yorkshire coast in early February. Bold Tern is in charge of transporting and installing half […]

  • 15 December 2015
    Grid Connection, Wind Farm Update

    Balfour Beatty has been awarded a £25 million project by DONG Energy to construct a high voltage onshore substation, as part of the new Hornsea Project One offshore wind farm. Work to construct the new onshore substation is planned to start in January 2016, with Balfour Beatty responsible for the build at North Killingholme, North […]

  • 3 January 2019
    Contracts & Tenders, Operations & Maintenance

    Siemens Gamesa has contracted Associated British Ports (ABP) to provide storage for 37 of its wind turbine blades destined for the Hornsea Project One offshore wind farm.

  • 6 February 2019
    Vessels, Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel Bold Tern has arrived at the Hornsea Project One offshore wind farm in the UK ready to install the first turbines. According to the UK-based company, the vessel left the Alexandra Dock in Hull yesterday morning after picking up the first batch of Siemens Gamesa 7MW turbines. Bold Tern is in […]

  • 28 November 2018
    Business & Finance

    The UK-based Aviva Investors has invested GBP 400 million to help fund the construction of Ørsted’s Hornsea Project One offshore wind farm.

  • 4 March 2020
    Business & Finance

    Ørsted has reported an increase of DKK 1 billion (circa EUR 134 million) in its full-year EBITDA guidance due to updated assumptions regarding the divestment of the transmission asset for the Hornsea One offshore wind farm. The Danish company said it now expects EBITDA excluding earnings from new partnership agreements to be DKK 16-17 billion this […]

  • 9 March 2017
    Grid Connection, Technology, Wind Farm Update

    The first of three substation topsides being built for DONG Energy’s 1.2GW Hornsea Project One offshore wind farm has arrived at Bladt Industries’ site in Aalborg, Denmark.

  • 1 October 2018
    Ports & Logistics, Wind Farm Update

    Rostock-based EEW SPC has loaded out and delivered 116 out of 174 monopiles for Ørsted’s Hornsea Project One offshore wind farm.

  • 30 October 2017
    Vessels

    DONG Energy has chosen Esvagt’s standby safety vessel Esvagt Castor to assist in establishing the 1.2GW Hornsea One offshore wind farm located off Grimsby in the UK part of North Sea.

  • 10 May 2016
    Vessels, Wind Farm Update

    A2SEA has won a contract to install a part of 174 Siemens 7MW turbines at the 1.2GW Hornsea Project One wind farm off the Yorkshire Coast. In spring 2019, A2SEA will deploy its offshore installation vessel, Sea Installer, to work on the turbines at the site located 120 kilometres off the coast. ”It is a great pleasure […]

  • 6 June 2017
    Grid Connection, Wind Farm Update

    VBMS, a subsidiary of Royal Boskalis Westminster, has been awarded a contract to assist DEME’s subsidiary Tideway with the installation of three nearshore and shallow water sections of export cables for DONG Energy’s 1.2GW Hornsea Project One offshore wind farm.

  • 12 September 2018
    Grid Connection, Ports & Logistics, Vessels, Wind Farm Update

    The Edda Mistral Service Operations Vessel (SOV) has arrived at the Royal Dock in Grimsby ahead of the vessel’s start of operations on Ørsted’s Hornsea Project One offshore wind farm.

  • 30 July 2018
    Grid Connection, Wind Farm Update

    Bladt Industries has sent off the last two offshore substation topsides for Ørsted’s Hornsea Project One offshore wind farm from its site in Aalborg, Denmark.

  • 13 September 2017
    Grid Connection, Wind Farm Update

    Bladt Industries has installed a helideck on the first out of the three substation topsides currently under construction for DONG Energy’s 1.2GW Hornsea Project One offshore wind farm in the UK.

  • 20 February 2020
    Grid Connection

    Ofgem has selected Diamond Transmission Partners as the preferred bidder for the offshore transmission of the Hornsea Project One wind farm in the UK.

  • 21 June 2019
    Business & Finance

    The Hornsea Project One offshore wind farm has begun receiving Contract for Difference (CfD) payments. The Low Carbon Contracts Company (LCCC) began allocating the payments for the first phase of the 1.2GW offshore wind project as it passed the required tests for its Operational Conditions Precedent (OCP). The first project phase, with a capacity of 400MW, achieved a […]

  • 3 May 2019
    Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up Bold Tern has completed the installation of 28 turbines at the Hornsea Project One offshore wind farm in the UK. The vessel, which is in charge of installing half of the project’s 174 turbines, has picked up the 8th batch of the Siemens Gamesa units in the Port of Hull and […]

  • 27 September 2018
    Grid Connection, Wind Farm Update

    Independent energy advisory and certification body DNV GL  has completed a lenders’ technical due diligence on Ørsted’s 1.2GW Hornsea Project One offshore wind farm.

  • 2 May 2018
    Ports & Logistics, Vessels, Wind Farm Update

    Osbit Ltd has recently delivered a height adjustable boat landing system to Gulf Marine Services’ self-elevating support vessel (SESV) GMS Endeavour currently deployed on Ørsted’s Hornsea Project One wind farm off Yorkshire.