185 results
A list of search results
-
Nearshore geotechnical surveys along the Neart na Gaoithe export cable corridor route are due to start off the Fife coast in Scotland later this month. The survey work is being carried out by Fugro using a ‘walking’ jack-up barge, Wavewalker 1. The survey is planned to start no earlier than 25 November and last approximately […]
-
Dutch offshore lifting equipment provider KenzFigee has won a contract to deliver two 3-ton electric hydraulic Ram Luffing offshore cranes to be installed on the Neart na Gaoithe (NnG) offshore substation topsides. KenzFigee was awarded the contract by HSM Offshore, in close collaboration with Iv-Offshore & Energy. The heavy duty 1300 type Ram Luffing design […]
-
A geotechnical borehole survey campaign is set to begin at the Neart na Gaoithe (NnG) offshore wind project on 1 September. Geotechnical drilling vessel Ocean Vantage is expected to survey 32 of the planned wind turbine and one of the offshore substation locations. The survey works are expected to last approximately 80 days. Neart na […]
-
Contracts & Tenders, Grid Connection
VolkerInfra has secured a new contract with Prysmian PowerLink for onshore cable services at the Neart na Gaoithe (NnG) offshore wind farm in Scotland. Under the GBP 15.5 million contract, VolkerInfra will install two 220kV onshore export circuits following the completion of the Pre-Construction Activities (PCA). The UK-based company is in charge of enabling works […]
-
Neart na Gaoithe Offshore Wind Limited will be carrying out 110 seabed Cone Penetration Tests (CPTs) at the Neart na Gaoithe offshore wind farm site, the KIS-ORCA announced on its website. The tests will commence between the 7th and 10th December 2013, and will be completed approximately within 26 days, weather permitting. The Neart na […]
-
Authorities, Business & Finance, Environment, Wind Farm Update
The Court of Session, Scotland’s supreme civil court, has overturned the ruling which halted further development of four wind projects with a total capacity of 2,284MW in the Firth of Forth and Firth of Tay.
-
Grid Connection, Wind Farm Update
The remaining seabed preparation works at the Neart na Gaoithe offshore wind project are set to recommence at the beginning of April, after the winter pause. The vessel Sartor will carry out the remaining boulder relocation operations in preparation for the installation of inter-array cables in the wind farm area. Boulder relocation is due to […]
-
Mainstream Renewable Power will be holding a number of pre-application consultation events in September and October in relation to the Marine Licence(s) for the 450MW Neart na Gaoithe wind farm project offshore Scotland.
-
Grid Connection, Wind Farm Update
Global wind and solar company Mainstream Renewable Power has been granted planning consent by East Lothian Council for the onshore cable works to connect its 450MW “Neart na Gaoithe” offshore wind farm, located off the coast of Fife, to the National Grid. East Lothian Council’s Planning Committee agreed on 18th June to grant consent for […]
-
Grid Connection, Wind Farm Update
Perth civil engineering company I & H Brown has secured a contract to construct the onshore substation for the Neart na Gaoithe (NnG) offshore wind farm in Scotland. I & H Brown said it is undertaking all the civil elements of the substation to enable the site, including five portal frame buildings in preparation for the […]
-
Grid Connection, Wind Farm Update
The first of the two shunt reactors for the Neart na Gaoithe (NnG) offshore wind farm has been transported under police escort from Scotland’s Port of Leith to the NnG onshore substation site near Innerwick, East Lothian. The second shunt reactor is due for delivery in the coming days, according to the latest update from […]
-
Neart na Gaoithe, the €2.1 billion offshore wind project located 30 km north of Torness will face an environmental challenge in a Scottish court this week. According to an assessment by the Scottish authorities the 450-megawatt Neart na Gaoithe along with three other wind energy project are projected to kill about 1,200 puffins and 1,100 gannets a […]
-
Vessels, Wind Farm Update
Scottish offshore wind farm Neart na Gaoithe (NnG) has entered the first phase of offshore construction. Saipem’s vessel S7000 set to start installing pile casings at the site some 15 kilometres off the Fife coast. The 197.5-metre semi-submersible crane vessel will also prepare the seabed for the jacket foundations for the project’s 54 wind turbines […]
-
Business & Finance, Wind Farm Update
EDF Renewables UK has received consent from the Scottish Government for an improved design of the Neart na Gaoithe offshore wind farm.
-
Business & Finance, Contracts & Tenders
Fugro has secured contracts to conduct surveys at EDF’s Neart na Gaoithe offshore wind farm in the UK and Ørsted’s Greater Changhua project in Taiwan. Under the deals, Fugro will carry out multiple unexploded ordnance surveys at Neart na Gaoithe and a geotechnical survey at Greater Changhua, according to the company’s latest financial report. Fugro reported a 5.7% increase […]
-
The EDF Group has launched the construction of the Scottish Neart na Gaoithe (NnG) offshore wind farm project along with the new partners, the Irish electricity company ESB, which is taking a 50% stake in the project. The 450MW Neart na Gaoithe will consist of 54 turbines and will be located in the North Sea […]
-
Grid Connection, Wind Farm Update
DEME Offshore has kicked off engineering activities for the Neart na Gaoithe offshore wind project in Scotland as part of its EPCI contract for the inter-array and interconnector cables. DEME’s scope includes the engineering, procurement, construction, and installation of the subsea cables for the 450MW wind farm, with execution expected in 2021. According to the […]
-
Grid Connection, Wind Farm Update
Export cable burial works are set to soon commence at the Neart na Gaoithe (NnG) offshore wind project in the UK. The burial of the first export cable is due to begin in the week commencing 21 June, with burial of the second cable planned to begin week commencing 19 July 2, at the earliest. […]
-
Mainstream Renewable Power has decided to divest its stake in a North Sea wind farm. According to the Irish media, Dublin-based offshore wind farm developer is in talks with InterGen and Siemens Project Ventures to sell its 450 MW Neart na Gaoithe. This would be InterGen’s first investment in the offshore wind sector. Neart na […]
-
Business & Finance, Wind Farm Update
Mainstream Renewable Power is in exclusive discussions with a consortium led by power company InterGen to take its 450 MW Neart na Gaoithe offshore wind farm to financial close and into construction. The consortium also includes Siemens Project Ventures, The Marguerite Fund and Infrared Capital. Speaking today at the Scottish Renewables Offshore Wind Conference in Glasgow, Mainstream’s […]
-
As previously announced, the Neart na Gaoithe Offshore Wind Limited has begun the seabed Cone Penetration Tests (CPTs) at the Neart na Gaoithe offshore wind farm site. The company will carry out a total of 110 CPTs with multi-purpose vessel Fugro Commander over the period of 26 days, starting 12th December 2013. With a capacity […]
-
Construction of the Neart na Gaoithe (NnG) offshore wind farm in Scotland is planned to begin this week after a pause due to the coronavirus pandemic. According to Matthias Haag, NnG Project Director, construction of the project was paused in March and is now expected to continue after the latest government guidance on infrastructure projects […]
-
Marubeni and Technip to Build Neart na Gaoithe Offshore Wind Farm Mainstream Renewable Power has appointed Marubeni and Technip Offshore Wind Limited (working in consortium) as the preferred supplier of balance of plant EPCI (Engineering, Procurement, Construction and Installation) services for the Neart na Gaoithe offshore wind farm. First OW Jack-Up Vessel Built in Germany […]
-
Wind farm developer, Mainstream Renewable Power, is inviting local people to have their say on the proposed Neart na Gaoithe offshore wind farm at a series of free community consultation exhibitions being held in November 2010. In February 2009, Mainstream was awarded the exclusive rights by the Scottish Government to develop the Neart na Gaoithe […]
-
FLiDAR has wrapped up the onsite wind measurements at Mainstream Renewable Power’s 448MW Neart na Gaoithe offshore wind farm. The FLiDAR floating LiDAR buoy provided on-site wind measurements and resulted in a considerable development time and cost saving compared to a traditional meteorological mast. The unit is now decommissioned and undergoing post validation at the ORE Catapult […]
-
Ports & Logistics, Wind Farm Update
Ravenna-based F.lli Righini Srl has started shipping out jacket pile grippers built for the Neart na Gaoithe wind project offshore Scotland. F.lli Righini Srl has been contracted to design, fabricate, and test 168 jacket pile grippers for the 450 MW project owned by EDF Renewables and ESB. Located some 15 kilometres off the Fife coast, […]