220 results found for 'Neart na Gaoithe'

220 results found for 'Neart na Gaoithe'
Order results by

A list of search results

  • 15 October 2025
    Business & Finance, Fixed-Bottom, Grid Connection

    The UK’s energy regulator, Ofgem, has selected Equitix as the preferred bidder to acquire and operate the offshore transmission assets for the 448 MW Nearth na Gaoithe offshore wind farm in Scotland. Equitix has been selected in a GBP 450 million (approximately EUR 516 million) tender round for an Offshore Transmission Owner (OFTO). As an asset […]

  • 25 July 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    The 450 MW Neart na Gaoithe (NnG) offshore wind farm has become fully operational, with Scotland’s First Minister John Swinney visiting Eyemouth on 24 July to mark the launch of the country’s newest offshore wind project. Located 15.5 kilometres off the coast of Fife, NnG is co-owned by EDF power solutions UK and Ireland and […]

  • 6 November 2025
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    ARB Wind has been awarded a multi-year contract for above water foundation inspections and Balance of Plant (BoP) services by Neart na Gaoithe (NnG) Offshore Wind Limited for the 450 MW offshore wind farm in Scotland. ARB Wind will provide dedicated BoP technicians to deliver a wide range of services across NnG’s offshore and onshore […]

  • 27 August 2025

    F.lli Righini Srl, a leading engineering and manufacturing company in offshore energy solutions, has successfully delivered numerous Jacket Pile Grippers (JPGs) for multiple offshore wind projects across the North Sea and Baltic Sea. These tailor-made systems play a critical role in the precise installation of jacket foundations for Wind Turbine Generators and Offshore Substations, contributing […]

  • 7 April 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    The final Siemens Gamesa 8 MW turbine has been installed at the 450 MW Neart na Gaoithe (NnG) offshore wind farm in Scotland. The installation of the 54th wind turbine was completed in the early hours of this morning (7 April) at the site located some 15.5 kilometres off the Fife coast. The work was […]

  • 15 January 2025
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The second wind turbine installation campaign is about to start at the 450 MW Neart na Gaoithe offshore wind farm site off the coast of Fife, Scotland. According to a notice to mariners from the project, Fred Olsen Windcarrier’s jack-up vessel Brave Tern is scheduled to commence the work on or around 17 January. The vessel will load […]

  • 10 September 2019
    Authorities, Wind Farm Update

    Neart na Gaoithe Offshore Wind Limited, the developer of the 450MW Neart na Gaoithe wind farm offshore Scotland, has made an application to the UK Gas and Electricity Markets Authority for an electricity generation licence. The licence application will remain open for comments until 8 October. The Edinburgh-based Neart na Gaoithe Offshore Wind Limited is a special […]

  • 6 December 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Two-thirds of wind turbines have been installed at the Neart na Gaoithe offshore wind farm in Scotland, which produced its first power in October. According to notices to mariners from the project issued on 20 November and 3 December, 35 wind turbines are up at the project site with three more partially installed. Owned by […]

  • 24 October 2023
    Fixed-Bottom, Project Updates, Wind Farm Update

    Saipem has completed the foundation installation works for the Neart na Gaoithe (NnG) wind farm offshore Scotland. Located 15 kilometres off the east coast of Scotland, the NnG offshore wind farm will be able to generate around 450 MW of low-carbon electricity and supply enough energy to the National Grid to power around 375,000 homes. […]

  • 30 November 2017
    Contracts & Tenders, R&D, Wind Farm Update

    Mainstream Renewable Power has begun the selection process to bring on board a majority equity partner to help take its 450MW Neart na Gaoithe offshore wind project into construction and commercial operation.

  • 5 May 2014
    R&D, Technology, Wind Farm Update

    Offshore WIND’s photo of the day: A floating LiDAR deployed on Mainstream Renewable Power’s 450MW Neart na Gaoithe offshore wind farm site.  On April 20, FLiDAR NV (a joint venture between DEME and 3E), has set up the device at Mainstream Renewable Power’s Neart na Gaoithe offshore wind farm site, almost 21km off the Fife coast. The […]

  • 16 August 2023
    Contracts & Tenders, Wind Farm Update

    Global Wind Projects has been awarded a contract by Siemens Gamesa for the pre-assembly of 54 wind turbine towers for the 450 MW Neart na Gaoithe (NnG) offshore wind farm, being developed by EDF Renewables and ESB off the coast of Scotland. Global Wind Projects said that this is the company’s first standalone offshore wind […]

  • 28 December 2020
    Wind Farm Update

    The geotechnical borehole survey campaign at the Neart na Gaoithe offshore wind farm site has been completed. According to the project’s Notice to Mariners from 26 December, the Ocean Vantage vessel, which has been deployed for the work, has been demobilised. As reported earlier this year, the borehole survey campaign at the Neart na Gaoithe […]

  • 18 November 2022
    Vessels, Wind Farm Update

    Heerema Marine Contractors’ semisubmersible crane vessel Balder has replaced Saipem 3000 at the Neart na Gaoithe offshore wind farm in Scotland, taking over the installation of piles for the project’s jacket foundations. Balder arrived at the project site in October to install the first ten jacket foundations and completed the work on 7 November, and moved on […]

  • 18 November 2019
    Wind Farm Update

    Nearshore geotechnical surveys along the Neart na Gaoithe export cable corridor route are due to start off the Fife coast in Scotland later this month. The survey work is being carried out by Fugro using a ‘walking’ jack-up barge, Wavewalker 1. The survey is planned to start no earlier than 25 November and last approximately […]

  • 27 July 2016
    Authorities, Business & Finance, Wind Farm Update

    Mainstream Renewable Power has urged Scottish ministers to appeal the recent judicial review of Scottish Court of Session which has ruled in favour of the Royal Society for the Protection of Birds (RSPB) and has put a stop to four offshore wind projects off the Fife coast, including Mainstream’s 450MW Neart na Gaoithe.  In October 2014, Mainstream was granted consent […]

  • 22 March 2024
    Cables, Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    Cable burial activities at the inter-array routes within the Neart na Gaoithe offshore wind farm site have been completed, following the wrap-up of cable installation works in January. The pre-lay grapnel run (PLGR) along the inter-array cable (IAC) routes was completed in November 2023 by the vessel Pacific Discovery. The PGLR work started in March […]

  • 10 December 2013
    R&D, Wind Farm Update

    Mainstream Renewable Power is undertaking planned survey work on the Neart na Gaoithe Offshore Wind Farm site from Thursday December 12th 2013 (earliest) for approximately 26 days. The work relates to the site of the proposed 450MW Neart na Gaoithe offshore wind farm which is located in the outer Forth Estuary approximately 15 km to […]

  • 4 December 2013
    R&D

    Neart na Gaoithe Offshore Wind Limited will be carrying out 110 seabed Cone Penetration Tests (CPTs) at the Neart na Gaoithe offshore wind farm site, the KIS-ORCA announced on its website. The tests will commence between the 7th and 10th December 2013, and will be completed approximately within 26 days, weather permitting. The Neart na […]

  • 10 March 2020
    Contracts & Tenders

    Dutch offshore lifting equipment provider KenzFigee has won a contract to deliver two 3-ton electric hydraulic Ram Luffing offshore cranes to be installed on the Neart na Gaoithe (NnG) offshore substation topsides. KenzFigee was awarded the contract by HSM Offshore, in close collaboration with Iv-Offshore & Energy. The heavy duty 1300 type Ram Luffing design […]

  • 27 March 2020
    Contracts & Tenders, Grid Connection

    VolkerInfra has secured a new contract with Prysmian PowerLink for onshore cable services at the Neart na Gaoithe (NnG) offshore wind farm in Scotland. Under the GBP 15.5 million contract, VolkerInfra will install two 220kV onshore export circuits following the completion of the Pre-Construction Activities (PCA). The UK-based company is in charge of enabling works […]

  • 8 June 2021
    Grid Connection, Wind Farm Update

    The first of the two shunt reactors for the Neart na Gaoithe (NnG) offshore wind farm has been transported under police escort from Scotland’s Port of Leith to the NnG onshore substation site near Innerwick, East Lothian. The second shunt reactor is due for delivery in the coming days, according to the latest update from […]

  • 10 September 2020
    Grid Connection, Wind Farm Update

    Perth civil engineering company I & H Brown has secured a contract to construct the onshore substation for the Neart na Gaoithe (NnG) offshore wind farm in Scotland. I & H Brown said it is undertaking all the civil elements of the substation to enable the site, including five portal frame buildings in preparation for the […]

  • 4 August 2017
    Wind Farm Update

    Mainstream Renewable Power will be holding a number of pre-application consultation events in September and October in relation to the Marine Licence(s) for the 450MW Neart na Gaoithe wind farm project offshore Scotland.

  • 16 May 2017
    Authorities, Business & Finance, Environment, Wind Farm Update

    The Court of Session, Scotland’s supreme civil court, has overturned the ruling which halted further development of four wind projects with a total capacity of 2,284MW in the Firth of Forth and Firth of Tay.

  • 24 August 2020
    Wind Farm Update

    A geotechnical borehole survey campaign is set to begin at the Neart na Gaoithe (NnG) offshore wind project on 1 September. Geotechnical drilling vessel Ocean Vantage is expected to survey 32 of the planned wind turbine and one of the offshore substation locations. The survey works are expected to last approximately 80 days. Neart na […]